161 P. 933 | Nev. | 1916

Lead Opinion

By the Court,

Colem:an, J.:

This is an appeal from a judgment and decree of foreclosure of a mechanic’s lien, entered in the district court in and for Nye County. Appellants, who were the owners of a certain lot, and a building situated thereon, in the town of Tonopah, entered into a contract with Kelleher & Kuhlman, on or about September 1, 1913, for the making of certain alterations and additions to the said building. Pursuant to the contract, the contractors were to furnish all materials necessary in the making of the alterations and additions. The respondent, the Verdi Lumber Company, furnished and delivered to the contractors, upon their request, at the property mentioned, certain lumber and other building material, which were used by the contractors in making the alterations and additions contemplated by the contract. The contractors having failed to pay for the lumber and material so purchased, the company filed its lien statement, and in due time brouglit this action to foreclose the same.

Section 1 of an act entitled "An act to secure liens to mechanics and others, and to repeal all other acts in relation thereto, ” approved March 2, 1875 (Stats. 1875, c. 64), being section 2213 of the Revised Laws of 1912, read s:

*321"Every person performing labor upon, or furnishing material of the value of five (5) dollars or more, to be used in the construction, alteration or repair of any building or other * * * structure, has a lien upon the same for the work or labor done or material furnished by each, respectively, whether done or furnished at the instance of the owner of the building or other improvement, or his agent; * * * and every contractor, subcontractor, architect, builder, or other persons, having charge or control of any * * * or of the construction, alteration or repair, either in whole or in part, of any building or other improvement, as aforesaid, shall be held to be the agent of the owner, for the purposes of this chapter. ”

Section 9 of the same act reads as follows:

"Every building or other improvement mentioned in section 1 of this act, constructed upon any lands with the knowledge of the owner or the person having or claiming any interest therein, shall be held to have been constructed at the instance of such owner or person having or claiming any interest therein, and the interest owned or claimed shall be sub j ect to any lien filed in accordance with the provisions of this chapter, unless such owner or person having or claiming an interest therein shall, within three days after he shall have obtained knowledge of the construction, alteration, or repair, or the intended construction, alteration or repair, give notice that he will not be responsible for the same, by posting a notice in writing to that effect in some conspicuous place upon said land, or upon the building or other improvement situate thereon. ”

Several days after work had been commenced upon the property pursuant to the contract, a notice of nonliability, such as contemplated by said section 9, was posted upon the property by appellants.

Several reasons are urged why the judgment should be reversed; but, in the view which we take of the case, we deem it necessary to consider only one question, and that is, conceding that the notice of nonliability was posted in apt time, and in a conspicuous place, did it accomplish the purpose intended by it?

*322While appellants contend that they never became liable to respondent, because of the posting of the notice, respondent asserts that it was not the intention of the legislature that section 2221 should apply to a situation such as is here presented, upon the theory that, under section 2213, Kelleher & Kuhlman were the agents of appellants, and that the appellants were bound by the acts of their agents just as much as they would have been had they ordered the lumber and other supplies themselves, and that, if appellants had themselves ordered the materials, they could not have relieved the property from the liability by posting a notice of nonliability.

A clause similar to the last one in section 2213, supra, making "the contractor, subcontractor, architect, builder, or other person having charge of the work, ” the agent of the owner, is embodied in. the mechanic’s lien statutes of many of the states; and, so far as we have been able to find, the courts have uniformly given such language its plain and ordinary meaning, and have held that supplies and other materials ordered by persons in any of the named classes were proper to be secured by a lien, with the same force and effect as if ordered by the owner himself. In fact, the intention of the legislature in using the language making the contractor, etc., the owner’s agent is so clear that the courts have not found it necessary to construe it very often.

1. If the language of section 2213, supra, is given its plain meaning, and if the principal is as much bound by the acts of his agent as if he had acted for himself, how can the mere posting of a notice, such as contemplated in section 2221, supra, by the owner of the property,' relieve him of liability under circumstances such as are presented, in the case at bar? To sustain appellants’ contention, we must hold that in so far as the circumstances of this case are concerned, so much of section 2213, supra, as provides that the contractor, etc., is the agent of the owner is repealed by section 2221, supra. Courts do not favor any such consequence when it can be avoided, but rather seek to so harmonize the different parts of acts, *323and different acts which, are in pari materia, as to enable them all to stand. We are convinced that the legislature never intended by section 2221 to convey any such idea as contended for by appellants, for if it did, we would have the absurd situation of an owner of property being ' able to order supplies, directly or through a duly authorized agent, procure their delivery, and then, pursuant to the preconceived plan, post a nonliability notice and escape liability therefor. It ought to require no argument to refute such a preposterous contention.

But, fortunately, it has not been left for us to become pioneers in interpreting this statute, for similar questions have received the consideration of other courts. The most recent case in point is that of Oregon Lumber & Fuel Co. v. Nolan, 75 Or. 69, 143 Pac. 935, 146 Pac. 474. That was a case in which Nolan, the owner of a certain lot, gave a lease upon condition that the lessee should erect thereon a building, by the terms of which lease it was agreed that the lessee should not suffer any lien to be filed against the property. The lessee entered into a contract with a builder for the erection of a building upon the lot. During the erection of the building the contractor failed, and liens were filed. On the day following the commencement of the work of digging the foundation for the building, Nolan posted a nonliability notice. In the foreclosure suit he took substantially the same position as has been taken by appellants in this case. In passing upon Nolan’s contention, the court said:

"The terms of the contract between himself [Nolan] and Blanchard [the lessee] required the latter, without any choice on his part, to construct a building. Although this stipulation was coupled with a lease and an option to purchase the premises, yet .its legal effect is to make Blanchard a contractor for the erection of a building which, by the terms of the contract, was eventually to become the property of Nolan and. to increase the value of his holdings. These conditions made Blanchard the statutory agent of Nolan within the scope of section 7416, L. O. L., so that one furnishing material or labor at the *324instance of such an agent for the erection of a building would be entitled to a lien on the realty on which it was situated if Nolan owned the fee. Under such circumstances the law imposed upon Nolan’s property certain obligations to those who should furnish materials for the erection of the house at the instance of his statutory agent. Laborers and materialmen, covenanting with Blanchard either directly or through subcontractors, have rights in the premises arising by operation of law which Nolan and Blanchard cannot destroy by contract between themselves. Although each for himself could properly stipulate to waive the provisions of the statute in his own favor, yet without the consent of materialmen who are strangers to that contract, 'they cannot waive nor impair the rights which the law confers upon such claimants. (Hume v. Seattle Dock Co., 68 Or. 477, 137 Pac. 752, 50 L. R. A. n. s. 123.) If Blanchard had been only a tenant of the premises, without any obligation on his part to erect a building, and under such circumstances had contracted for the erection of the structure, only his leasehold estate would have been primarily liable, under section 7417, L. O. L., for the materials and labor furnished. Yet even then the fee owned by Nolan also would have been liable under section 7419, if he knew of the work, unless he had given the notice mentioned therein, and this because there would then have been no contract to which Nolan was a party contemplating the compulsory erection of the building. This is in accordance with the principle, so often announced by this court, that to support a lien there must be some contractual relation, either directly or indirectly between the lien claimants and the holder of the realty interest sought to be charged. Here, however, Nolan himself has in unmistakable terms directly made an agreement with his contractor, Blanchard, to build the house. He holds out Blanchard to the world as the person having charge of the construction of a building on Nolan’s land. He cannot repudiate any of the terms or conditions which the law itself visits upon such a convention *325for the benefit of persons named in the statute. The distinction between cases where improvements are at the option of a tenant or mere acquiescence of the landlord, entailing no right to a lien when proper notices are given, and the other class of cases where the improvement is compulsory on the part of the tenant, making him a contractor with the landlord, with the consequence that liens may be claimed against the fee for materials or labor furnished, is clearly pointed out by Mr. Justice Dunbar in Stetson-Post Mill Co. v. Brown, 21 Wash. 619, 59 Pac. 507, 75 Am. St. Rep. 862. See, also, Hall v. Parker, 94 Pa. 109; Boyer v. Keller, 258 Ill. 106, 101 N. E. 237, Ann. Cas. 1916b, 628; Curtin-Clark Hdw. Co. v. Churchill, 126 Mo. App. 462, 104 S. W. 476; Western Lumber & Mill Co. v. Merchants’ Amusement Co., 13 Cal. App. 4, 108 Pac. 891; Arctic Lbr. Co. v. Borden, 211 Fed. 50, 127 C. C. A. 486.”

See, also, Warde v. Nolde, 259 Mo. 285, 168 S. W. 596; Western L. & M. Co. v. Merchants’ Amusement Co., 13 Cal. App. 4, 108 Pac. 892.

2. We have quoted at some length from the case mentioned because it fully and clearly presents the views of the courts which have been called to pass upon the question involved, as well as our interpretation of the statute. We are clearly of the opinion that by section 2221, supra, it was not the intention of the legislature that an owner might exempt his property from a lien for materials furnished for improvements, alterations, or additions upon his property, no matter whether the materials were ordered by himself or by his legally constituted agent, but that it was the intention of the legislature that the owner might be enabled to exempt his property from a lien in cases where improvements were made by one who occupied a relationship to the owner pursuant to which the owner was not charged with knowledge that improvements were to be made at the time the relationship was created, but became aware of the making of improvements thereafter. Any other construction of the section in question would necessitate our holding that *326section 2221 substantially repeals section 2213, so far as they are in conflict.

Section 2221 was not, in our opinion, intended to narrow the scope and effect of section 2213, but rather to give a lien in cases not covered by the latter section. In other words, section 2213 expressly provides that liens might be acquired where materials were furnished at the request of the owner or his legally constituted agent, while by section 2221 an active duty is imposed upon the owner to repudiate liability for improvements made or materials furnished without his consent, within three days after acquiring knowledge-thereof, and by his failure to do so he is, in effect, estopped from denying the authority of his tenant, or other person authorizing the improvements, because of which the property must be held subject to a lien. No other construction can be-given to section 2221 which will harmonize the two sections.

For the reasons given, it is ordered that the judgment appealed from be affirmed.






Concurrence Opinion

McCarran, J.:

I concur.

Norcross, C. J.,

did not participate.






Rehearing

Per Curiam:

Petition for rehearing denied.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.