On this appeal, we decide whether there was sufficient mutual assent for the parties to form a valid new contract or modify an existing one. Also at issue are the application of the doctrine of laches to demurrage claims and the proper calculation of damages on demurrage claims.
Plaintiff Venus Lines Agency, Inc. (Venus) appeals the district court’s ruling in favor of Defendant CVG International America, Inc. (CVGIA) on Venus’ claim that CVGIA breached its contract with Venus, the ruling that Venus’ 1995 and 1996 demurrage claims were barred by the doctrine of laches, and the district court’s calculation of damages with respect to its 1997 demurrage claim. CVGIA cross-appeals the district court’s finding that CVGIA was liable for Venus’ 1997 demur-rage claim.
I. BACKGROUND
CVGIA is a Florida corporation that arranges and secures the shipment of goods for a large Venezuelan conglomerate. Pri- or to its relationship with Venus, another Venezuelan company (Compañía Anónima Venezolana de Navegación (CAVN)) handled CVGIA’s freight pursuant to annual contracts that were renewed each year. In March 1994, CVGIA began doing business with Venus after CAVN went bankrupt by arranging one round-trip voyage carrying the products of the Venezuelan conglomerate northward to Mobile and carrying the CVGIA procured shipments southward to Venezuela. Later, CVGIA solicited bids for the shipment of goods southward from Miami, Port Everglades, and Mobile to Venezuela. CVGIA requested bids to carry goods for one year at a fixed tariff rate, and the bid request contained terms similar to CAVN’s last contract with CVGIA. Venus filed its tar
Over the next few months, Michael Ko-biakov, Venus’ President, met with representatives from CVGIA on several occasions to discuss the possibility of a long-term agreement. Venus contends the parties agreed to a four-year service contract in October 1994 at a meeting between Ko-biakov and CVGIA’s Executive Vice President Ramon Iglesias, and that the terms of this contract were recorded in Kobiakov’s notes, which he took on the face of an earlier contract between CVGIA and Seafreight Line Ltd. CVGIA, however asserts the parties never finalized a long-term contract. Over the next two years, Venus and CVGIA discussed possible written agreements, but were never able to agree on written terms. CVGIA rejected several drafts that Venus proposed. In September, 1997, CVGIA informed Venus that its services were no longer needed for the Miami to Venezuela run.
Venus sued CVGIA in the Southern District of Florida, alleging that CVGIA breached its contract with Venus, and seeking liquidated damages provided for in the 1994 oral “agreement.” Alternatively, Venus sought damages for misrepresentation and promissory estoppel, alleging CVGIA’s actions led Venus to believe it was engaged in a contractual relationship, and to rely on that belief to its detriment. Venus also alleged CVGIA failed to pay demurrage 2 and freight charges specified in the bills of lading Venus issued CVG with each voyage.
After a five day bench trial, the district court found that no long term contract existed between Venus and CVGIA, as there had never been any agreement on the fundamental issues of duration and price. The district court rejected Venus’ promissory estoppel and misrepresentation claims, finding that CVGIA made no “clear and unambiguous promise” upon which Venus relied, that any additional expenditures Venus made to service CVGIA were necessary expenditures, and that there was insufficient evidence to support a misrepresentation claim. The court found that the doctrine of laches barred Venus’ demurrage claims for 1995 and 1996, because Venus had an obligation to demand payment from CVGIA rather than waiting until this lawsuit to file its demurrage claims for those years. The court found Venus “made a timely pre-suit demand for the 1997 demurrage and [was] entitled to recover from CVGIA under the terms of the bills of lading.” The court ordered that Venus was entitled to collect $78,629.49 “plus ten percent ... interest per annum running from the date the freight or demurrage was due, and for the attorneys’ fees relating to the prosecution of freight and demurrage claims.”
II. DISCUSSION
A. Jurisdiction and Standard of Review
An appeal from a final judgment entered by a United States District Court provides us with jurisdiction under 28 U.S.C. § 1291.
We review a district court’s factual findings when sitting without a jury in admiralty under the clearly erroneous standard.
See Marine Transp. Servs. Sea-Barge Group, Inc. v. Python High Performance Marine Corp.,
Venus contends the district court erred when it framed the central issue of whether a long-term contract existed between CVGIA and Venus as one of formation and not modification. Venus also argues the district court misstated the rule governing parties contemplating a written agreement, because the intention to sign a written agreement does not prevent the parties from agreeing to an enforceable oral contract. Venus asserts it had an enforceable four-year oral contract to ship goods for CVGIA that arose from a modification of the contract formed when CVGIA accepted Venus’ bid, and that the modified terms were the contract’s extended duration and modified scope of service.
“It is not necessary ... to reduce an agreement to writing to bind the parties, as long as the parties intend to be bound at the time of the oral agreement.”
Nautica Int’l, Inc. v. Intermarine USA, L.P.,
In order to form an enforceable oral contract, “there must be a meeting of the minds on all essential terms and obligations of the contract.”
Browning v. Peyton,
Even if Venus were correct that the central issue in this case is not whether the parties formed a new contract, but whether they modified an existing one, the conduct of the parties after they reached the purported agreement demonstrates there was no valid modification of the contract formed when CVGIA accepted Venus’ bid. A meeting of the minds on modified terms is necessary to validly modify a contract.
See United Contractors, Inc. v. United Constr. Corp.,
C. Doctrine of Laches
The equitable doctrine of laches will bar a claim when three elements are present: “(1) a delay in asserting a right or a claim; (2) that the delay was not excusable; and (3) that there was undue prejudice to the party against whom the claim is asserted.”.
Kason Indus., Inc. v. Component Hardware Group, Inc.,
In admiralty claims, we look to the analogous statute of limitations only as a benchmark in determining whether to apply the doctrine of laches. The former Fifth Circuit held that: “the analogy rule serves primarily to determine where rests the burden of proof. ‘[W]hen a plaintiff files a claim in admiralty within the analogous statutory period, defendant must show inexcusable delay and resulting prejudice in order to establish a laches defense.’ ”
Mecom v. Levingston Shipbuilding Co.,
During 1995 and 1996, Venus accepted payment from CVGIA’s consignees (the Venezuelan conglomerate that owned CVGIA), and failed to demand payment from CVGIA for any outstanding demur-rage. The district court found, and we agree, that Venus had a responsibility to demand payment from CVGIA on demur-rage rather than to wait until filing this suit. As Venus admitted at oral argument, the invoices for 1995 and 1996 demurrage
Venus, however, did make a timely pre-suit demand for payment of the 1997 de-murrage charges. Because there was no inexcusable delay in making that demand, the district court correctly held that the doctrine of laches does not bar that claim.
D. Calculation of Damages
The tariff Venus submitted with the Federal Maritime Commission clearly indicates that the interest rate on costs of collection of freight and demur-rage was twelve percent. In calculating damages, the district court used an interest rate of ten percent. What interest rate to apply in calculating damages is a factual determination subject to a clear error standard of review.
See Marine Transp. Servs. Sea-Barge Group, Inc.,
III. CONCLUSION
For the foregoing reasons, we affirm the district court’s decision that the parties did not make a long-term oral contract in October 1994, and we find that there was no valid modification of the existing contract between CVGIA and Venus. We also affirm the district court’s decision that the doctrine of laches barred Venus’ 1995 and 1996 demurrage claims, but did not bar its 1997 demurrage claim. We reverse the district court’s calculation of damages, and remand this case to the district court for recalculation of damages.
AFFIRMED IN PART, REVERSED AND REMANDED IN PART.
Notes
. Rule 7-02 of the tariff filed with the Federal Maritime Commission allowed the carrier (Venus) to recover all costs of collection for freight charges past due, plus twelve percent annual interest compounded daily. This interest rate in the tariff is relevant to our discussion of the district court’s calculation of damages, infra.
. Demurrages are penalties for delays in the loading and unloading of goods.
. In
Bonner v. City of Prichard,