Ventres v. Goodspeed Airport, LLCVentres v. Goodspeed Airport, LLC
Opinion
This appeal arises out of a complaint filed by the plaintiffs, the inland wetlands and watercourses commission (commission) of the town of East Lladdam (town) and its enforcement officer, James Ventres, against the defendants, Timothy Mellon, Goodspeed Airport, LLC (airport), Timothy Evans, the East Haddam Land Trust (land trust) and the Nature Conservancy (conservancy). The plaintiffs alleged that Mellon, Evans and the airport (collectively, airport defendants) violated the town’s inland wetlands regulations by failing to obtain a permit before cutting down trees and other vegetation on two properties owned, respectively, by the land trust and the conservancy (collectively, land trust defendants).
1
The land trust defendants filed a cross claim against the airport defendants claiming, inter alia, that they had: (1) trespassed on their land and converted their trees; (2) violated
The record reveals the following relevant facts and procedural history. The airport is located on Lumberyard Road in East Haddam. It is an “[ajirport available for public use” within the meaning of title 14 of the Code of Federal Regulations, § 77.2. 5 6Mellon is the sole member of Goodspeed Airport, LLC. Evans is an independent contractor who has been the manager of the airport since November, 2003, and is responsible for managing its day-to-day activities.
The airport’s southern boundary lies approximately along the centerline of a tidal creek that flows in a westerly direction into the Connecticut River. That boundary forms the northern boundary of property owned by the land trust, which extends for approximately 335 feet to the south, where it abuts property owned by the conservancy. The conservancy’s property extends for another 100 feet to the south, at which point it abuts Chapman Pond. The airport has a 2100 foot runway that runs in a north-south direction. The southern end of the runway is approximately 630 feet north of the airport’s southern boundary and 1100 feet north of Chapman Pond.
Between November 29 and December 5, 2000, Evans, at the direction of Mellon and without the permission of the land trust defendants, cut down all of the trees, bushes and woody vegetation on approximately 2.5 acres of land located between the southern boundary of the airport property and Chapman Pond. Approximately 340 trees were destroyed, including some that were 100 years old and seventy-two feet high. The airport defendants claim that the trees and vegetation posed a danger to aircraft landing at and taking off from the runway. The 2.5 acres were entirely within a regulated wetlands area as defined by
Thereafter, the plaintiffs brought this action alleging that the airport defendants had failed to obtain from
the commission a permit to conduct a regulated activity
7
within a wetlands area as required by
On appeal, the airport defendants claim that the trial court improperly determined that: (1) federal aviation law does not preempt state and local wetlands regulations; (2) the failure to obtain a wetlands permit can give rise to an independent action under
We conclude that the trial court properly determined that the airport defendants had a prescriptive easement to maintain an approach slope over the land trust defen
dants’ property, but that they exceeded the scope of the easement by clear-cutting the land.
13
We further conclude that, because the airport defendants had no right under state property law to clear-cut the land, they had no such right under federal law and, accordingly, we need not reach their claim that federal law preempts state and local land use law. With respect to the plaintiffs’ claims on cross appeal, we conclude that the trial court properly determined that the airport defendants should not be required to restore the land to its original condition and properly determined the amount of monetary penalties pursuant to
I
We first address the airport defendants’ claim that the trial court improperly determined that federal aviation law does not preempt local wetlands regulations. We conclude that we need not reach this claim because we conclude that the airport defendants had no right under state property law to clear-cut the land belonging to the land trust defendants and because the airport defendants have conceded that, in the absence of a property right, federal law would not confer such a right.
The airport defendants claim that they removed the vegetation from the land trust defendants’ properties
pursuant to federal regulations and guidelines governing the maintenance of unobstructed “runway protection zones”
14
and approach surfaces
15
for airports like the one in the present case. They further argue that the regulations and guidelines are designed to protect navigable airspace,
16
over which
We conclude that the trial court properly determined that the airport defendants have acquired a prescriptive easement to enter the land trust defendants’ property for the purpose of maintaining an approach slope to the runway. We also conclude that the trial court properly determined that the airport defendants had no right under the prescriptive easement to clear-cut the land trust defendants’ property.
We first address the issue of whether the airport defendants have a prescriptive clearance easement in the land trust defendants’ properties and, if so, the scope and purpose of the easement. We conclude that the trial court properly determined that the airport defendants have a prescriptive easement to maintain an approach slope over the land trust defendants’ property.
The distinction between an avigation easement and a clearance easement was discussed in
United States
v.
Brondum,
The status of both prescriptive avigation easements and prescriptive clearance easements is unsettled under Connecticut law. See
Westchester
v.
Commissioner of Transportation,
“2. If under Connecticut law a clearance easement is distinct from an avigation easement, can a clearance easement be acquired by prescription in the State of Connecticut?
“3. Whether conceived as incident to an avigation easement or as constituting a separate clearance easement, would a clear zone include whatever air space is necessary to use the easement?” (Internal quotation marks omitted.) Id., 497 n.2. Because we concluded that, under the facts and circumstances of the case, the plaintiff could not establish a prescriptive avigation easement, we declined to answer the certified questions. Id., 502, 504.
In making that determination, we recognized that, in order to establish a prescriptive avigation or clearance easement, the party claiming the easement must meet the requirements of state law that “the use be adverse. It must be such as to give a right of action in favor of the party against whom it has been exercised. ... In order to prove such adverse use, the party claiming to have acquired an easement by prescription must demonstrate that the use of the property has been open, visible, continuous and uninterrupted for fifteen years and made under a claim of right.” (Citation omitted; internal quotation marks omitted.) Id., 501. “A use by express or implied permission or license cannot ripen into an easement by prescription.” (Internal quotation marks omitted.) Id. We concluded that the plaintiff could not establish that its use of the airspace gave a right of action in favor of the defendants, thereby giving rise to a prescriptive easement, because: (1) “[t]he defendants . . . had no right of action against the plaintiff to stop the overflights because federal law prohibits landowners from obtaining injunctive relief against aircraft using the navigable airspace of the United States”; id., 502; and (2) although the defendants had a right “to seek compensation from the plaintiff for aircraft flights so low and so frequent as to be a direct and immediate interference with the enjoyment and use of the land”; (internal quotation marks omitted) id., 503; there was no evidence of such interference in the case. Id., 504.
In the present case, unlike in
Westchester
v.
Greenwich,
supra,
There is no dispute in this case that the airport defendants’ use of the land trust defendants’ property was “open, visible, continuous and uninterrupted for fifteen years and made under a claim of right.” (Internal quotation marks omitted.)
Westchester
v.
Greenwich,
supra,
A
The following additional facts are relevant to the resolution of the land trust defendants’ claim that the airport defendants failed to meet their burden of establishing the scope of the easement. Arthur D’Onofrio, a previous owner of the airport, testified at trial that, between 1979 and 1999, trees located within the 2.5 acres at issue in the present case were periodically trimmed or removed. The cuttings took place approximately every four or five years. The trees usually were trimmed or removed in response to complaints from pilots that the trees were protruding into the airspace and becoming a safety hazard. D’Onofrio testified that the procedure for trimming the trees was not “very scientific. Basically, [he] sent people in there with chainsaws and they cut down whatever . . . trees they thought were in the way of the approach.” Shrubs were also removed in order to provide access to the trees. The cutting area was approximately 100 to 150 feet wide and was centered on the center line of the runway. Landing area inspection reports showed that, in 1981, the runway operated with a fourteen to one approach slope; 21 in 1983, it operated with a thirteen to one approach slope; in 1984 and 1985, it operated with a nineteen to one approach slope with a displaced threshold of 340 feet; 22 in 1986, it operated with a twenty to one slope with a displaced threshold of 340 feet; in 1987 and 1988, it operated with a twenty to one slope with a displaced threshold of 150 feet; in 1993, it operated with a fourteen to one approach slope; and in 1997, it operated with a thirteen to one approach slope.
On the basis of this evidence, the trial court determined that the airport defendants had acquired a prescriptive easement to enter the land trust defendants’ property to trim and cut trees growing in the 2.5 acres at issue for the purpose of removing obstacles in the runway takeoff and landing corridors. After the trial court issued its memorandum of decision, the land trust defendants filed a motion for articulation requesting that the trial court provide the precise boundaries of the easement. The trial court denied the motion,
The land trust defendants claim that the trial court improperly found that the airport defendants had established a prescriptive easement because the easement “must be defined in terms of height, in addition to the more traditional length and width of a pathway” and because the evidence showed that “there has been no uninterrupted fifteen year period in which the airport maintained anything resembling a consistent glide path.” We disagree.
“[A] prescriptive right extends only to the portion of the servient estate actually used . . . and is circumscribed by the manner of its use .... A prescriptive right cannot be acquired unless the use defines its bounds with reasonable certainty.” (Citations omitted.)
Kaiko
v.
Dolinger,
The burden is on the party claiming a prescriptive easement to prove all of the elements by a preponderance of the evidence.
Schulz
v.
Syvertsen,
supra,
The only issue in the present case is whether the vertical dimensions of the prescriptive easement claimed by the airport defendants were sufficiently defined. During the years that the approach slope was measured without a displaced threshold, it ranged from thirteen to one to fourteen to one. During the years
that the approach slope was measured with reference to a displaced threshold of 340 feet, it ranged from nineteen to one to twenty to one. Our calculations show that these slopes are relatively consistent with the
In light of the type of use at issue, we conclude that the variations in the angle of the approach slope maintained by the airport defendants did not prevent them from acquiring a prescriptive easement. First, trees grow. It is clear, therefore, that it would be virtually impossible to maintain an absolutely uniform slope over the course of time. Second, a very localized and relatively small change in the topography of the vegetation could cause a major change in the approach slope. For example, a sudden growth spurt in a single tree near the border between the land trust and airport properties could cause the approach slope to become much steeper in a short period of time. Third, although the angle of the approach slope changed from year to year, it appears to have stayed within a relatively narrow range centering around twenty to one with a 340 foot displaced threshold. See footnote 24 of this opinion.
Finally, although D’Onofrio testified that he would both trim and cut down trees that protruded into the airspace, the
purpose
of the easement was to
maintain a maximum tree height
over the land, not to eliminate the trees altogether, and that was the actual result of the airport defendants’ use of the property. See
United States
v.
Brondum,
supra,
B
We next address the land trust defendants’ claims that the trial court improperly determined that the airport defendants had acquired a prescriptive easement in their properties because the existence of a boundary line agreement between the predecessors in title to the airport and the land trust prevented the airport from obtaining a prescriptive
The following additional facts are relevant to our resolution of this claim. On December 3, 1970, Edward Vynalek and Dorothy Vynalek (collectively, the Vynaleks), predecessor landowners to the land trust, and William H. Bradway and Ruth E. Bradway (collectively, the Bradways), predecessor landowners to the airport, entered into a boundary line agreement. The purpose of the agreement was to resolve a dispute over the location of the boundary between their properties by making the boundary the center of the tidal creek. The agreement provided that “the said BRADWAYS do hereby remise, release, and forever QUIT-CLAIM unto the said VYNALEKS, their heirs and assigns forever, all the right, title, interest, claim and demand whatsoever as the said BRADWAYS have or ought to have in or to the lands situated generally south of said division line between the lands of the parties herein TO HAVE AND TO HOLD the said premises unto the said VYNALEKS, their heirs and assigns forever, so that the said BRAD-WAYS, their heirs nor any other person shall hereafter have any claim, right or title in or to the said premises, or any part thereof and they are by these presents forever barred and excluded therefrom.” The trial court concluded that the agreement did not prevent the airport defendants from acquiring a prescriptive easement in the land trust’s property because, although “entering the [land trust defendants’] land may contravene the rights to exclusive possession conveyed by the boundary agreement, eveiy prescriptive easement is similarly acquired.”
The land trust defendants argue that the trial court improperly failed to recognize that the agreement constituted notice, under
“A fence was constructed along the [private way] in 1960. In 1960 . . . the defendants’ [predecessor] in title, obtained a permanent injunction . . . against ... a plaintiff in [the] action, enjoining him, his servants and agents from interfering with [the predecessor’s] use and enjoyment of said right-of-way . . . .” (Internal quotation marks omitted.) Id., 585-86.
“In 1964, the plaintiffs removed a section of the fence. The plaintiffs used the front portion of the [private way] to the opening of the fence as a means of gaining vehicular access to their property from River Road.” (Internal quotation marks omitted.) Id., 586. Thereafter, the plaintiffs commenced an action seeking to enjoin the defendants from interfering with their use of the private way. Id. The trial court concluded
On appeal, this court agreed with the trial court that the plaintiffs had violated the permanent injunction issued by the trial court in 1960 by using the private way. Id., 589. We further concluded that, although the plaintiffs’ use of the private way was not permissive and was made without any recognition of the defendants’ rights to prevent it and, therefore, ordinarily would have established that the plaintiffs had acted under a claim of right, the existence of the permanent injunction precluded the plaintiffs from acquiring a prescriptive easement. Id., 591-93. In support of this con
elusion, we stated that, under
We conclude that the present case is distinguishable from
Crandall.
In
Crandall,
the injunction issued by the trial court in 1960 had been sought and was issued for the express purpose of prohibiting the plaintiffs from using the private way as an easement. In the present case, the purpose of the boundary line agreement was to resolve a property line dispute. The language of the agreement providing that neither the “BRADWAYS, their heirs nor any other person shall hereafter have any claim, right or title in or to the [Vynaleks’] premises, or any part thereof and they are by these presents forever barred and excluded therefrom” was intended merely to recognize that the Bradways had agreed to disavow any property interest in any formerly disputed land on the Vynaleks’ side of the newly agreed upon property line and that their successors would have no such interest by virtue of anything that had occurred up to the date of the agreement. Nothing in the agreement suggests that the Vynaleks were aware of any past use or anticipated any future use, for any purpose, of the portion of their land that had not been in dispute or that they intended to forestall the acquisition of a prescriptive easement in the land. We conclude, therefore, that the trial court properly determined that the boundary line agreement did not constitute notice of intent to prevent the airport defendants from acquiring an easement under
C
We next turn our attention to the trial court’s determination that the airport defendants exceeded the scope of the prescriptive easement by clear-cutting the land trust defendants’ properties. We note that the airport defendants do not challenge that determination on appeal.
26
II
We next address the airport defendants’ claim that, even if we conclude that federal law did not preempt the application of state and local wetlands regulations to their conduct, the trial court improperly rendered judgment for the land trust defendants on their cross claim that cutting the trees constituted unreasonable pollution under
The following additional procedural history is relevant to our resolution of this claim. In the sixth count of their cross claim against the airport defendants, the land trust defendants claimed that the clear-cutting of their land had “removed a natural buffer that existed between Chapman Pond and any [a]irport disturbances, threaten[ed] the integrity of Chapman Pond and the lower Connecticut River Watershed, and involve [d] conduct which has, or is reasonably likely to have, the effect of unreasonably polluting, impairing or destroying the public trust in Chapman Pond by increasing noise pollution and other destruction and impairment of wetlands, watercourses and other environmentally sensitive habitats in breach of the public trust. For example, the stream that these trees helped to shade and retain has a documented population of wild brook trout and the removal of the shade trees will adversely affect the stream water quality, temperature, and habitat. The trees also served to buffer Chapman Pond’s breeding waterfowl and wintering bald eagle habitat from the airport.” (Internal quotation marks omitted.)
The trial court found that the “clear-cutting was unreasonable under all of the circumstances. In the past, only trimming and selective cutting of trees was employed to remove such obstacles to air navigation, which the growing trees created. There existed no sound reason to abandon that conservative practice. To sever every tree and woody-stemmed bush, regardless of height and species, destroyed important floodplain forest excessively and unnecessarily.” Accordingly, the court rendered judgment for the land trust defendants on the sixth count of their cross claim.
The airport defendants argue that the sixth count of the land trust defendants’ cross claim was duplicative of the first count of the commissioner of environmental protection’s complaint in the companion case of
Rocque
v.
Mellon,
Because the airport defendants’ claim implicates the standing of the land trust defendants to raise a claim under
In
Connecticut Coalition Against Millstone
v.
Rocque,
supra,
Ill
We next address the airport defendants’ claim that the trial court improperly rendered judgment for the plaintiffs on their claim that the airport defendants violated the act by failing to obtain a permit to clear-cut the land trust defendants’ properties. They argue that the removal of vegetation from the properties was not a regulated activity under the act because it did not disturb any wetlands soils. We disagree.
The trial court found that “[t]he floodplain forest which was clear-cut comprised diverse species of hardwood trees and woody shrubs. . . . [A]round 340 trees and tree sprouts were severed on land trust property and a few more on conservancy land. These trees acted as a flood brake, slowing the velocity of the occasional floodwaters of the Connecticut River which regularly spill into the floodplains and eventually into Chapman’s Pond. The slower the flow of floodwater, the less erosion, scouring, and damage to the submerged land and water bodies is done. The taller and denser the floodplain forest, the greater the buffering capacity to slow floodwaters. Undoubtedly, the felling of all trees and
woody vegetation over 2.5 acres in the midst of a floodplain corridor between the Connecticut River and Chapman’s Pond altered that wetlands and the abutting floodplains and wetlands.” Accordingly, the trial court concluded that the airport defendants had violated
We first address the standard of review. “Whether the trial court properly concluded that the commission had jurisdiction over the activities proposed by the plaintiff involves a legal question involving statutory interpretation, over which our review is plenary.”
AvalonBay Communities, Inc.
v.
Inland Wetlands Commission,
We begin with the language of the statute.
The airport defendants argue, however, that our opinion in
AvalonBay Communities, Inc.
v.
Inland Wetlands Commission,
supra,
We
IV
We next address the airport defendants’ claim that the trial court improperly determined that Mellon was personally liable for clear-cutting the trees on the land trust defendants’ property. We disagree.
The following additional procedural history is relevant to our resolution of this claim. At trial, Evans testified that Mellon instructed him to cut “everything” within the 2.5 acres. Mellon testified that he directed Evans to cut all of the trees within the approach slope. Mellon did not specifically recall instructing Evans to cut shrubs, but stated that he took “responsibility for whatever [Evans] cut,” and that everything that Evans did was under Mellon’s authority.
During trial, the airport defendants filed a motion to dismiss the claims against Mellon personally on the ground that the plaintiffs and the land trust defendants had not established a prima facie case that he had acted in his individual capacity and not merely as a corporate officer of the airport. The trial court denied the motion. In its memorandum of decision, the court found that, “[b]etween November 29 and December 5, 2000, at the direction of Mellon, the owner of the airport, Evans, an independent contractor, clear-cut approximately 2.5 acres of floodplain forest located on land owned by the land trust and land owned by the conservancy.” The court rendered judgment against the airport defendants on the plaintiffs’ claims pursuant to
It is well established that “an officer of a corporation does not incur personal liability for its torts merely
because of his official position. Where, however, an agent or officer commits or participates in the commission of a tort, whether or not he acts on behalf of his principal or corporation, he is liable to third persons injured thereby.”
Scribner
v.
O’Brien, Inc.,
Because the issue of whether a corporate officer has committed or participated in the wrongful conduct of a corporation is a question of fact, it is subject to the clearly erroneous standard of review. See
Sargent
v.
Smith,
We conclude in the present case that the trial court’s determination that Mellon personally directed Evans to clear-cut the trees is amply supported by the record. Accordingly, we conclude that the trial court properly determined that Mellon was personally liable for cutting the trees under
Mellon makes two arguments in support of his claim to the contrary. First, he argues that his conduct did not fall within the responsible corporate officer doctrine adopted by this court in
BEC Corp.
v.
Dept. of Environmental Protection,
In
BEC Corp.
v.
Dept. of Environmental Protection,
supra,
In the present case, the airport defendants argue that, because
We next address the airport defendants’ claim with respect to
V
We next address the claim of the plaintiffs on cross appeal that the trial court improperly failed to exercise its jurisdiction to order the airport defendants to restore the land trust defendants’ properties to their condition prior to the violation of
The following additional facts and procedural history are relevant to our resolution of this claim. Christopher Allan, a senior associate with Land Tech Consultants and an expert witness for the plaintiffs, testified that restoration of the properties would require planting new trees and shrubs and fencing each tree and shrub individually to protect them from deer. He estimated that the cost of the restoration would be $158,092. Sigrun Gadwa, the principal ecologist for REMA Ecological Services and an expert witness for the airport defendants, testified that Allan’s plan could be implemented for a cost of at least 20 percent less.
The airport defendants began their clear-cutting operation on November 29, 2000. Thirty-five days later, on January 2, 2001, Ventres issued a cease and desist order prohibiting the airport defendants from engaging in any further regulated activity at the site.
The plaintiffs argue on appeal that trial court’s decision to assess $17,500 in civil penalties and not to order
the airport defendants to restore the properties was an abuse of discretion because “[t]here was simply no testimony from which the court could conclude that $17,500 was sufficient to restore” the land to the condition it was in before the clear-cutting, and because
“A party seeking injunctive relief has the burden of alleging and proving irreparable harm and lack of an adequate remedy at law. ... A prayer for injunctive relief is addressed to the sound discretion of the cotut and the court’s ruling can be reviewed only for the purpose of determining whether the decision was based on an erroneous statement of law or an abuse of discretion.” (Internal quotation marks omitted.)
Pequonnock Yacht Club, Inc.
v.
Bridgeport,
This court has not previously had occasion to consider the scope of the trial court’s discretion in ordering
a civil penalty pursuant to
As the airpoit defendants point out, the trial court determined that the restoration plan proposed by the plaintiffs’ expert would not have restored the land to its prior condition, but would have improved the condition of the land. The plaintiffs have not disputed that finding. We conclude that the court was not required to create and impose on the airport defendants a plan of its own to restore the land to its condition prior to the violation. Nor was it required to issue a general order to the airport defendants that they restore the land to its prior condition, which almost certainly would have led to additional litigation. Accordingly, we conclude that the trial court did not abuse its discretion in declining to order the airport defendants to restore the land.
We also reject the plaintiffs’ argument that the $50,000 contribution imposed pursuant to
VI
We next address the plaintiffs’ claim on cross appeal that the trial court improperly suspended the calcula tion of per diem civil penalties upon the commission’s issuance of the cease and desist order. We disagree.
The following additional facts are relevant to our resolution of this issue. As we have indicated, on January 2,2001, Ventres issued an order to the airport defendants ordering them to cease and desist from all regulated activity on the airport property and on the land trust defendants’ properties. The order identified the prohibited regulated activity as “clear-cutting of a flood plain forest . . . and disturbance of the flood plain soils around the tidal inlet at the end of the property . . . .” The order stated that “[satisfactory corrective measures are not to be done without a permit from the [c]ommission” and required the airport defendants to appear at a hearing on January 11, 2001, to show cause why the order should not remain in effect. Because several commission members had recused themselves from the matter, however—apparently because the airport defendants had alleged a conflict of interest—no quorum was available on the date of the hearing. At a June 11, 2001 commission meeting on a related matter, counsel for the airport defendants withdrew the conflict of interest claim as to two of the three commission members who had recused themselves.
40
The cease and desist hearing was never rescheduled, however, and the plaintiffs never issued any order to the airport defendants to correct the condition of the land trust defendants’ land. See
As we have indicated, the trial court imposed a $500 per diem fine on the airport defendants for the thirty-five days between the day that they began cutting the trees on the land trust defendants’ properties, November 29, 2000, and the day that the cease and desist order was issued, January 2, 2001. The court reasoned that, because the order was never lifted, it prevented “the airport defendants from implementing any corrective or remedial plan because such action would necessarily involve the removal and deposition of material at the site and would alter wetlands, albeit for environmentally beneficial purpose.” The plaintiffs argue that the trial court improperly limited the per diem penalties to the thirty-five day period because the cease and desist order did not prevent the airport defendants from submitting a restoration plan to the commission. They further argue that, because they requested restoration of the land in their complaint, which listed a return date of May 8, 2001, and because the airport defendants made no effort to submit a restoration plan up to the date of the court’s decision, May 21,2004, the trial court should have imposed civil penalties for that entire period.
We conclude that the plaintiffs’ argument is flawed in several respects. First,
VII
We next address the land trust defendants’ claim on cross appeal that the trial court improperly struck their cross claim under CUTPA. We disagree.
The following procedural histoiy is relevant to our resolution of this issue. The land trust defendants alleged in the fifth count of their cross claim that: (1) the airport defendants had violated CUTPA by threatening expensive and protracted litigation “in an attempt to stifle the [land trust] and its individual volunteer members’ participation in government process”; (2) Mellon had a history of using bad faith litigation to further his business interests and had initiated litigation against the members of the land trust board in an effort to “squelch opposition”; and (3) the trees were clear-cut to facilitate the expansion of the airport’s runway, which otherwise would not have been permitted, and directly injured the land trust defendants’ business interests of protecting and preserving property for public enjoyment. The airport defendants filed a motion to strike the CUTPA claim on the grounds that they were merely defending themselves against the action filed by the plaintiffs and that their defense against the action was not their “trade or business.” They also argued that the airport defendants had not alleged any facts that would support a claim under CUTPA. The trial court granted the motion to strike on the ground that the land trust defendants were not competitors or customers of the airport defendants.
The land trust defendants now claim that the trial court improperly determined that CUTPA imposes a requirement that the plaintiff be either the defendant’s competitor or its customer. They argue that CUTPA protects businesspersons in general, not just consumers and competitors, and that the airport defendants’ conduct interfered with their business of protecting natural resources. The airport defendants counter, essentially as an alternate ground for affirmance, that the land trust defendants’ claims that the airport defendants were using litigation to intimidate and stifle the participation of the land trust and its volunteers in government process and that Mellon had a history of initiating baseless litigation to further his business interests are entirely without factual basis and, in any event, cannot support a CUTPA claim as a matter of law. The airport defendants do not address the claim that clear-cutting the land trust defendants’ land to advance their own business interest in facilitating the expansion of the runway was a CUTPA violation.
“The standard of review in an appeal challenging a trial court’s granting
“[General Statutes §] 42-110b (a) provides that [n]o person shall engage in unfair methods of competition and unfair or deceptive acts or practices in the conduct
of any trade or commerce. It is well settled that in determining whether a practice violates CUTPA we have adopted the criteria set out in the cigarette rule by the federal trade commission for determining when a practice is unfair: (1) [W]hether the practice, without necessarily having been previously considered unlawful, offends public policy as it has been established by statutes, the common law, or otherwise—in other words, it is within at least the penumbra of some common law, statutory, or other established concept of unfairness; (2) whether it is immoral, unethical, oppressive, or unscrupulous; (3) whether it causes substantial injury to consumers, [competitors or other businesspersons]. . . . All three criteria do not need to be satisfied to support a finding of unfairness. A practice may be unfair because of the degree to which it meets one of the criteria or because to a lesser extent it meets all three.” (Internal quotation marks omitted.)
Hartford Electric Supply Co.
v.
Allen-Bradley
Co.,
“[W]e previously have stated in no uncertain terms that CUTPA imposes no requirement of a consumer relationship. In
McLaughlin Ford, Inc.
v.
Ford Motor Co.,
With respect to the land trust defendants’ allegations that the airport defendants had threatened and actually engaged in oppressive litigation tactics, we conclude that the trial court properly determined that the allegations did not support a CUTPA claim. We note that the allegations are vague in that they do not indicate whether the land trust defendants are claiming that the
airport defendants’ litigation conduct in the present case was improper or that they had initiated a separate action against the members of the land trust board. To the extent that the land trust defendants claim that the conduct of the airport defendants in defending themselves from the claims against them in the present action was improper, they have not cited any authority for the proposition that a defendant’s vigorous defense against a lawsuit may form the basis for a CUTPA claim in that very lawsuit. Although the land trust defendants make a passing reference in their brief to this court to an action filed by the airport defendants in federal court, they do not discuss the nature or status of that action. We recently have held that claims based on the improper litigation conduct of the defendant in another pending action
With respect to the land trust defendants’ claim that the trial court improperly struck their allegation that the airport defendants’ violated CUTPA by clear-cutting
their land to advance their business interest in expanding the runway, the land trust defendants argue that this court expressly has held that CUTPA does not require the existence of a consumer relationship and implicitly has held that a competitor relationship is not necessary. See
Macomber
v.
Travelers Property & Casualty Corp.,
supra,
The land trust defendants argue, alternatively, that a CUTPA plaintiff is not required to allege any business relationship with the defendant. They have provided no authority, however, for that proposition. Cf.
Macomber
v.
Travelers Property & Casualty Corp.,
supra,
VIII
Finally, we address the claim of the land trust defendants on cross appeal that the trial court improperly determined that they were precluded from introducing evidence concerning the replacement value of the trees in support of their claim for damages pursuant to
The following additional procedural history is relevant to our resolution of this claim. The land trust defendants claimed in the second count of their cross claim that the airport defendants had intentionally trespassed on their property and had intentionally destroyed their trees, entitling them to treble damages under
The trial court concluded that the claim was precluded by the Appellate Court’s decision in
Stanley
v. Lincoln,
“This common-law rule has been embodied in
“ [R] eplacement value is not a proper measure of damages in tree cutting cases because [sjuch a measure of damages . . . would lead to unreasonable recoveries in excess of the market value of the land . . . would raise impossible issues in resolving the replacement values of healthy or partially damaged trees . . . [and] cannot be practically applied.” (Internal quotation marks omitted.) Id., 789 n.7, quoting
Maldonado
v.
Connecticut Light & Power Co.,
In order to resolve this claim, it is necessary to clarify the Appellate Court’s ruling in
Stanley.
The Appellate Court suggested in that case that the common-law rule that the diminution in property value is a proper measure of damages in tree cutting cases had been embodied in
The land trust defendants argue, however, that this court should “recognize an exception to the limitation on damages set forth in
[Stanley]”
and permit damages to be calculated on the basis of the replacement cost of the trees when “the value of the property lies in its place within the environment, rather than as a potential building lot or a working woodlot.” As we have indicated, however, the plain language of the statute precludes such a reading. “[This] court is precluded from substituting its own ideas of what might be a wise provision in place of a clear expression of legislative will.” (Internal quotation marks omitted.)
Skindzier
v.
Commissioner of Social Services,
The judgment is affirmed.
In this opinion the other justices concurred.
Notes
The plaintiffs alleged in the second count of the complaint that the aiqport defendants wilfully had violated the town’s inland wetlands regulations. The trial court subsequently dismissed the second count of the complaint and the plain! iffs have not challenged that ruling on appeal.
The case was tried jointly with an action brought by Arthur J. Rocque, the commissioner of environmental protection, against Mellon, the airport, the land trust and the conservancy. The trial court’s ruling in that case is the subject of the airport defendants’ appeal in the companion case of
Rocque
v.
Mellon,
The airport defendants appealed to the Appellate Court and we transferred the appeal to this court pursuant to
Title 14 of the Code of Federal Regulations, § 77.2, defines an “[ajirport available for public use” as “an airport that is open to the general public with or without a prior request to use the airport.”
The town’s inland wetlands regulations were prepared in accordance with the Inland Wetlands and Watercourses Act,
In this opinion, we use the phrase “clear-cut” to mean cutting close to the ground all trees and vegetation on a given property.
The Federal Aviation Administration has issued an advisory circular setting forth federal standards and recommendations for airport design. See Federal Aviation Administration, Advisory Circular No. 150/5300-113 (September 29, 1989). The advisory circular states that “[t]he standards and recommendations contained in this advisory circular are recommended by the Federal Aviation Administration for use in the design of civil airports.” The circular recommends that airports maintain a “[rjunway protection zone”; id., § 211 (a) (7); from which “incompatible objects and activities” should be cleared. Id., § 212 (a) (1). The purpose of the runway protection zone “is to enhance the protection of people and property on the ground.” Id., § 212. For runways like the one in the present case, the circular recommends that the runway protection zone extend 1000 feet beyond the end of the runway and increase in width from 250 feet at the end nearest the runway to 450 feet at the far end. Id., p. 19, table 2-4.
The Federal Aviation Administration has issued regulations establishing “standards for determining obstructions to air navigation” that “apply to the use of navigable airspace by aircraft . . . .”
Title 14 of the Code of Federal Regulations, § 91.119, provides in relevant part: “Except when necessary for takeoff or landing, no person may operate an aircraft below the following allitudes:
“(a) Anywhere. An altitude allowing, if a power unit fails, an emergency landing without undue hazard to persons or property on the surface.
“(b) Over congested areas. Over any congested area of a city, town, or settlement, or over any open air assembly of persons, an altitude of 1,000 feet above the highest obstacle within a horizontal radius of 2,000 feet of the aircraft.
“(c) Over other than congested areas. An altitude of 500 feet above the surface, except over open water or sparsely populated areas. In those cases, the aircraft may not be operated closer than 500 feet to any person, vessel, vehicle, or structure. . . .”
The airport defendants point, to two federal statutes that they claim preempt state and local environmental legislation as applied to their conduct in this case. Section 40103 (a) (1) of title 49 of the United States Code provides: “The United States Government has exclusive sovereignty of airspace of the United States.” Section 41713 (b) (1) of title 49 of the United States Code provides in relevant part: “[A] State . . . [or] political subdivision of a State . . . may not enact or enforce a law, regulation, or other provision having the force and effect of law related to a price, route, or service of an air carrier that may provide air transportation under this subpart.”
The
Westchester
case had a long subsequent history and, as we discuss later in this opinion, eventually came before this court. See
Westchester
v.
Greenwich,
Neither the trial court nor the parties characterized the easement at issue in the present case as a clearance easement. The trial court concluded, however, that the airport defendants had “acquired a prescriptive easement to go onto the 2.5 acre area, on occasion, and trim or cut trees which interfered with the safety of air traffic taking off or landing on the runway.” As we discuss later in this opinion, this is essentially the definition of a clearance easement.
In other words, for every fourteen feet that the approach slope advanced horizontally, it rose one vertical foot.
When an approach slope is steeper than the twenty to one ratio required by Federal Aviation Administration regulations; see footnote 15 of this opinion; the permissible landing point is shifted from the end of the runway to a point where the twenty to one approach slope is achieved. This point is known as a “displaced threshold.” In such cases, the approach slope is calculated with reference to the displaced threshold.
See also
O’Brien
v.
Hamilton,
15 Mass. App. 960, 962,
If a 340 foot displaced threshold is used and auniform slope of vegetation and the absence of obstacles south of the conservancy’s property are assumed, a 14 to 1 approach slope becomes approximately an 18 to 1 approach slope (the distance from the end of the runway to Chapman Pond, 1100 feet, divided by 14 is 78.57 feet, the presumptive height of the approach slope at Chapman Pond; the distance from the displaced threshold to Chapman Pond, 1440 feet, divided by 78.57 is approximately 18); using the same form of calculation, a 13 to 1 approach slope becomes approximately a 17 to 1 approach slope; and a 20 to 1 approach slope with a 150 foot displaced threshold becomes approximately a 23 to 1 approach slope. Thus, over the course of 18 years, the approach slope ranged from approximately 17 to 1 with a 340 foot displaced threshold to 23 to 1 with a 340 foot displaced threshold. We recognize that this calculation is somewhat rough. It is reasonable to conclude, however, that, because the runway had an approach slope ranging from 14 to 1 to 13 to 1 both before and after the 10 years in which the approach slope was calculated in reference to a displaced threshold, the approach slope during those 10 years was not radically different.
The land trust defendants also point to a letter dated June 7,1978, from the airport, operator at the time to the Connecticut bureau of aeronautics. The operator stated that he was in the process of obtaining permission to remove or trim trees on the land to the south of the airport property in order to reduce the approach slope. The land trust defendants argue that this letter defeats any claim that the airport defendants trimmed and removed trees from their property under a claim of right, but they point to no evidence that the airport or its predecessors actually obtained permission to enter the land. Accordingly, we reject this claim.
As we have indicated, the vertical dimensions of the easement varied within a relatively narrow range centered around a twenty to one slope with a 340 foot displaced threshold. As we have also indicated, when the airport defendants clear-cut (he land, some of the trees within the easement were up to seventy-two feet high. It is clear, therefore, that it was not reasonably necessary to clear-cut the trees to maintain an approach slope within the specified ranges. See
Gioielli
v.
Mallard Cove Condominium Assn., Inc.,
It seems somewhat counterintuitive that federal aviation law might preempt state and local law governing the use of real property even though it does not preempt state property law. There is some precedent for that proposition, however. See National Aviation v. Hayward, 418 F. Sup. 417, 424-25 (N.D. Cal. 1976) (exercise of municipal police power to regulate aircraft noise is preempted by federal law but right of municipal proprietor of airport to determine permissible noise level is not preempted). It is implicit in National Aviation that, although neighboring landowners could seek compensation if airport noise interfered with the use and enjoyment of their property, if a municipal airport proprietor obtained noise easements from the landowners, state and local governments could not regulate noise levels. See id., 421. As we have indicated, however, we need not consider in the present case the extent to which the principles cited in National Aviation apply to privately owned airports and prescriptive clearance easements because the airport defendants have not established that they have aproperty right to clear-cut the land trust defendants’ trees.
We note that the plaintiffs do not claim that the type of activities allowed by the prescriptive easement would violate state or local land use regulations. Accordingly, we need not consider whether federal law would preempt local regulations with respect to those activities. Nor need we consider the plaintiffs’ alternate ground for affirmance that, in the absence of any factual foundation that the airport defendants had initiated proceedings with the Federal Aviation Administration to identify and eliminate obstructions on the land trust defendants’ property, there was no factual predicate for the airport defendants’ claim of preemption.
We conclude elsewhere in this opinion that the clear-cutting constituted a regulated activity for which a permit was required. See part Hi of this opinion. In
Waterbury
v.
Washington,
Brian Golembiewsld, an environmental analyst with the inland water resources division of the bureau of water management and the department of environmental protection, appeared at trial as the plaintiffs’ expert witness. He testified that, “[u]nfortunately, all of this woody material has been left in place, so even . . . where you would have sunlight and you’d have . . . herbaceous or soft-stemmed short plants that would now have sunlight that they didn’t have prior . . . [that] could grow and establish, that would even be somewhat limited by this blanket of woody materials left out there.”
The legislature responded to our ruling in
AvalonBay Communities,
Inc., by enacting No. 04-209 of the 2004 Public Acts, now codified at
That finding was, in turn, supported by the trial testimony of Brian Golembiewski, the plaintiffs’ expert witness.
The airport defendants make no claim that a violation of § 22a-16 or § 22a-42a does not constitute tortious conduct.
The plaintiffs’ experts did not propose returning the land to the condition that it was in before the clear-cutting because, as the trial court found, “invasive species, such as ailanthus trees, had already established themselves at this site for many years, and it is highly desirable ecologically to eradicate such invaders and replace them with native species.”
The plaintiffs argue that the trial court’s discretion to impose civil penalties is limited by subdivision (1) of § 22a-44 (b), which provides that civil penalties imposed pursuant to that statute '‘shall be used solely ... to restore the affected wetlands or watercourses to their condition prior to the violation, wherever possible . . . .” We disagree. That language merely provides that any penalties that are assessed should be used to restore the wetlands. It does not require the court to impose a penalty that is sufficient to restore the wetlands.
We previously have held that, in assessing penalties under other civil penalty provisions of title 22a that provide no specific guidance to the court, the factors to be considered by the court “include, but are not limited to: (1) the size of the business involved; (2) the effect of the penalty or injunctive relief on its ability to continue operation; (3) the gravity of the violation; (4) the good faith efforts made by the business to comply with applicable statutory requirements; (5) any economic benefit gained by the violations; (6) deterrence of future violations; and (7) the fair and equitable treatment of the regulated community.”
Carothers
v.
Capozziello,
supra,
The airport defendants represent in their brief that the June 11, 2001 meeting concerned an application submitted by the airport to extend its runway. They argue that they did not intend to withdraw their motion to disqualify the commission members in proceedings on the pending cease and desist order. We need not decide whether the commission members were recused after June 11, 2001, however, because the issue is irrelevant to our analysis.
The Appellate Court has suggested in dicta that “a party’s use of its economic powers in an attempt to stifle individual citizens’ use of valid governmental processes by threat of expensive litigation potentially constitutes a violation of CUTPA, which is expressly modeled on § 5 (a) (1) of the Federal Trade Commission Act,
The land trust defendants made no such claim under the common law. Accordingly, there is no need to decide in this case whether the enactment of § 52-560 preempted a common-law cause of action.