149 Conn. 518 | Conn. | 1962
The plaintiff brought this action to recover a balance claimed to be due for services rendered as an architect under a written contract. The defendant admitted the execution of the contract but denied any indebtedness under it. By way of special defense, the defendant alleged that the plaintiff’s services were not done in accordance with
The court found the following facts: The defendant corporation was organized to erect a building to provide offices for persons engaged in the practice of medicine, dentistry and kindred professions in the metropolitan area of Bridgeport. On July 15, 1955, the plaintiff and the defendant entered into a contract in which the plaintiff was designated as the architect responsible, among other things, for the completion of plans and specifications based on preliminary drawings prepared by another architect who specialized in projects of this type. The contract required the plaintiff to supply all mechanical, electrical, structural and site consultants for the other architect during the preparation of the preliminary drawings. Difficulties arose because of the failure of the plaintiff to cooperate with the other architect, and in January, 1956, a meeting was called to correct the situation. At that time, the plaintiff agreed to complete the plans within a maximum of four months after receiving final instructions. These instructions were given in writing in February, 1956. The preliminary plans, as finally
On these facts, the court concluded that the plaintiff had performed his contractual obligations to the point of submitting partial plans for the proposed medical center, that in all other essentials the plaintiff had failed to perform his contract, that the plaintiff could not recover since he had failed to substantially perform his obligations under the contract and that he had failed to offer
The plaintiff has attacked the conclusion of the court that he failed to perform his contract in certain essentials. From the contract, it clearly appears that the plaintiff was under a duty to perform many specified obligations, in addition to those stated in the finding. In view of the manifold obligations imposed on the plaintiff under the contract and the silence of the finding concerning them, it is impossible to determine which, if any, of the essentials the plaintiff failed to fulfil. The plaintiff has attacked the conclusion that he could not recover on the contract since he had failed substantially to perform his obligations under it. The question raised by the pleadings was whether the plaintiff was entitled to any compensation in addition to that already received. The contract makes specific provision for the contingency which occurred in this case. The total sum fixed for the plaintiff’s services was to be used as a guide in the determination of what amount, if any, the plaintiff should receive if the defendant abandoned the project. The issues framed by the pleadings, together with the evidence adduced at the trial, presented this problem for determination. Its answer may be found in the language of the contract itself when applied to such of the facts as are outlined in the finding.
The plaintiff has also attacked the conclusion that he failed to offer any factual basis for a right of
There is error only as to the judgment on the complaint, the judgment on the complaint is set aside and the case is remanded for a new trial of the issues framed on the complaint.
In this opinion the other judges concurred.