82 W. Va. 658 | W. Va. | 1918
The Vaughan Construction Company, Incorporated, a Virginia corporation doing business in this state, in June, 1913, entered into a contract in writing to furnish the necessary labor, implements and material and to do and perform certain construction work for the Virginian Railway Company between Mullens and Bud on its main line, and between Mullens and Tam on its Winding Gulf branch line. As permitted by the contract and with the approval of the Virginian Railway Company, the other party thereto, the Vaughan Construction Company, Incorporated, sublet a part of the work to Gist Brothers Company, a partnership, and the residue to the Vaughan Construction Company, a West Virginia corporation, and the subcontractors completed the part undertaken by them sometime prior to November 10, 1914.
The parties did not stipulate a gross sum as compensation for the work in its entirety, but. did classify it and fix a schedule of prices for each class, ninety per cent thereof to be paid
The work undertaken by them the subcontractors completed sometime before November 10, 1914, apparently to the satisfaction of the Virginian Railway Company, and on that day the engineer estimated and certified the balance due under the terms of the contract to be $15,663.56. Being dissatisfied with this estimated balance for the labor and material furnished and the work done by them, Gist Brothers Company caused to be prepared, filed and .recorded as required by law a mechanics lien amounting to $79,959.02, this amount including extra work done by them by way of amendments or modifications later agreed to by the parties to the contract, as well as work expressly stipulated in the original contract. The Vaughan Construction Company of West Virginia did not undertake to bind the property of the Virginian Railway Company by a like lien for any balance due it. Gist Brothers Company in due time instituted in Wyoming County a suit to enforce the lien so acquired, and made parties thereto the Virginian Railway Company, Vaughan Construction Company, Incorporated, and the Vaughan Construction Company of West Virginia. The Vaughan Construction Company, Incorporated, by an answer in the nature of a cross-bill, to which all persons interested were made parties defendant and served with process to answer, sought an accounting with the Virginian Railway Company and the two subcontractors of all matters arising out of the performance of the construction contract, and a decree for any balance that might be found to be due upon such audit. This answer the circuit court dismissed as insufficient and inappropriate in a inechanics lien suit. This court upon appeal sustained
After the decree in that case, the Yaughan Construction Company, Incorporated, brought this action in assumpsit in Mercer County to recover as upon a quantum meruit, the declaration containing the common counts only, and when, upon oyer craved, the contract between the plaintiff and defendant was produced, filed and made part of the record, the defendant demurred to the declaration, and, that challenge being overruled, as properly it was, tendered and was permitted to file the general issue plea and two special pleas, which, though they differ in phraseology, purport to present one issue only. Stripped of verbal formalities the defense interposed by each of them rests upon a provision of the contract requiring the plaintiff to secure and deliver to the defendant a release of all claims, demands and accounts for labor, material and supplies that are or may become liens against the property of the defendant company as a condition precedent to any suit or action by the plaintiff for a cause arising out of the contract.
To each of the pleas plaintiff tendered and was permitted to file a special replication to the effect that by an inequitable, unjust and inadequate final estimate of the balance due plaintiff upon the termination of the work undertaken, amounting to gross disparity between the estimate and the actual sum claimed to be due, defendant had rendered compliance with the terms of the contract specified impossible or impracticable. These replications the trial court held insufficient upon defendant’s demurrer thereto and dismissed the action upon plaintiff’s refusal to join issue upon the general and special pleas, and plaintff assigns this action as erroneous and prejudicial.
The recovery sought embraces the entire amount due for the work done under the terms of the contract without regard as to whether Grist Brothers Company or the Vaughan Construction Company of West Virginia did it, subject to deduction by the amount of the compensation paid upon monthly estimates made as the work progressed. In other words, plaintiff seeks in this action what plaintiff sought but
There is no dispute and no doubt regarding the right of the parties to specify the conditions upon which an action' upon a contract may or may not be maintained without compliance with the conditions imposed by it and agreed to by them. Such provisions are not unusual and as a general rule courts uphold them. But though they are common and upheld, the rule sustaining them is not inexorable. It obtains and is enforceable only when the final estimate of the engineer is fair, just and commensurate with the work done and performed under the contract. If the estimate is unfair and not reasonably commensurate with the work done and performed, and unjustly fails to report a correct balance due to the contractor, he is not bound to comply with the strict letter of the contract, where to do so would necessitate the assumption of grievous burdens and subject him to risk of imperiling his entire claim. Such danger obviously appears in this case. For if plaintiff be required to pay Gist Brothers Company 'the full amount of their mechanics lien as a condition precedent to its right to maintain this action upon the contract, and the proof should show the justness and fairness of the engineer’s final estimate, the plaintiff would lose the difference between the two amounts, or $68,295.46, a loss wholly disproportionate to the amount certified to be the balance due upon the contract, which paintiff claims is so far inadequate as to constitute actual or constructive fraud on the part of the engineer.
The general rule, as Ave have said, is that where a contract requires payments for labor and materials entering into the .performance of the work agreed upon by the parties thereto to be based upon estimates made by an architect, in the case
The only provision which could produce that result is the
There are some, though we think not such material or significant differences between the facts of this case and those cited as forbids the application of the same legal principle. They vary only in this that in the cited eases there appears not to have been involved directly the rights of a subcontractor who had converted his claim for compensation into a lien created under the mechanics lien statute and binding upon the property of the owner. It is not perceived wherein this fact alters the relation of the contracting parties as to the principal liability. The only perceivable effect is to render their situation, as here, slightly more intricate and complicated, and certainly some intricacy and complication may arise as a result of the pendency of the two proceedings at
These conclusions require the reversal of the judgment, the overruling of the demurrer to the two special replications and the remand of the case for further proceedings.
Reversed, demurrer overruled, remanded.