Varnum v. Village of Morrisville

84 Vt. 302 | Vt. | 1911

Rowell, C. J.

The plaintiffs are contractors, and as such, on July 2, 1906, contracted with the defendant for the labor, materials, and construction of a concrete masonry dam and steel penstock for the improvement of the defendant’s electric light and power plant, as per a written agreement of that date, signed by both parties, which, and the specifications thereto attached under which the work was to be undertaken and performed, with certain exceptions, are set out in haec verba in the declaration. The only exception important to be noticed here is the one providing that the work should be performed according to the plans and drawings of such an engineer, which plans and drawings are made a part of the contract.

The action is assumpsit to recover the balance due from the defendant for the performance of said contract, and for certain extra work and material required to excavate and fill a fissure in the bed of the river where the dam was to be built, discovered simultaneously by the parties after the contract was executed and the work begun:

The declaration contains four counts. The defendant demurred generally to the first, second, and third by enumeration, and pleaded to the fourth count. The demurrer was sustained as to the first and the - third counts, and those counts adjudged insufficient; but was overruled as to the second count, and that count adjudged sufficient, and the defendant concedes that it is sufficient, whereupon the plaintiffs claim that the demurrer is too large, and ought *306to be overruled altogether. But as it enumerates the counts it is equivalent to a separate demurrer to each count, and so is not too large. Darling v. Clement, 69 Vt. 292, 37 Atl. 779. The plea to the fourth count was adjudged insufficient on demurrer.

It is objected that the first count is bad because it contains no allegation of a promise by the defendant to pay for the work specified therein, and claimed that such a promise should have been expressly and.positively alleged. And it is true that there is nothing in that count that amounts to an express promise by the defendant to pay, though there are allegations of abundant evidence of a quasi promise to pay. But that is not enough. There should have been an averment of assumpsit super se or its equivalent, for assumpsit, without assuming, is no assumpsit. Mr. Gould says that whenever the promise is implied, it is declared upon as an express promise, and that upon the face of the record it is always taken to be an express promise; that there is no such thing as an implied promise in pleading, or rather, that the fact of its being implied appears only in the evidence and never upon the record. Gould, PI. chap. Ill, sec. 19. He says in a note to that section that it is held in declaring in assumpsit on a bill of exchange against the drawer or on a promissory note against the maker, that a, statement of the facts that render the defendant liable to pay is sufficient without expressly alleging a promise on his part, the reason assigned being that the drawing of the bill or the making of the note is itself an actual promise, so that alleging the act of drawing or of making is virtually alleging a promise by the drawer or the maker, to pay. He says that whether this rule as far as it regards the declaration on a bill of exchange, (in which the drawer makes no express promise,) is agreeable to the analogies and principles of pleading, appears at least questionable, for in all other cases of indebitatus assumpsit the facts stated in the declaration as the ground of the defendant’s liability are regarded upon the face of the record only as the consideration of the promise that it alleges and must allege. So Mr. Lawes says that if no express promise is alleged nor other equivalent words used, the declaration will be bad even after verdict, for where the plaintiff declared *307that in consideration he would surrender a term the defendant would pay him so much, it was moved in arrest after verdict for the plaintiff on non assumpsit that there was no promise laid and therefore none to be tried, and the court being of that opinion, stayed the judgment. Lawes, PI. [*88], referring to Buckler v. Angel, 1 Lev. 164; s. c. 1 Sid. 246; s. c. 1 Keb. 878. Candler v. Rossiter, 10 Wend. 488, is a good illustration of this rule. There thé plaintiff declared in assumpsit for money paid, etc., omitting the ordinary assumpsit super se, but stating instead, the circumstances of his case, namely, that he bought a quantity of fish for the purpose of shipping it to a foreign port; that the defendant put on board the same vessel an equal quantity of fish for the purpose and with the intent of creating a joint adventure so that the parties should share in the profit and loss; and that the fish was so damaged at sea or elsewhere that after it arrived at the port of destination it was sold at a loss, the whole of which the plaintiff sustained and paid without having received any part thereof from the defendant, whereby the plaintiff had suffered damage to such an amount. After verdict for the plaintiff on non assumpsit, the defendant moved in arrest for that the declaration was bad in not laying a promise by the defendant. Mr. Wendell for the plaintiff contended that though the declaration was informal it was good after verdict; that it was not a case of defective title, for the agreement was stated, the liability charged, and a promise need not be alleged, for it was enough that the evidence justified the jury in finding a promise. But the court held otherwise and arrested the judgment. The plaintiffs make much the same argument here, and say that in respect of recovery for the extra work sued for, concerning which the promise is not express but implied by law, the test of the sufficiency of the allegations of fact in the count to show a promise by the defendant is, whether the plea of non assumpsit would put those allegations in issue, or, in other words, whether proof of the facts alleged would establish such promise. But that is no test, as shown by the case just cited, for if it would establish such promise, the necessity of a promise in the declaration would not be thereby obviated, for recovery must be had, if at all, according to the allegations as well as according to the proof.

*308The count is double, as it declares upon two different causes of action though of the same nature, namely, one growing out of the written contract, and the other, out of the extra work. In respect of both of these the plaintiffs claim that the final estimate article of the specifications contains a promise by the defendant to pay therefor. That article provides that upon the completion of the work to the satisfaction and acceptance of the defendant, a final estimate.of the total amount of contract and extra work performed by the plaintiffs by order of the defendant shall be made, and that this total sum, less all previous payments, shall be paid to the plaintiffs within thirty days of the date of said final estimate.

It is enough to say of this claim that there is no allegation in the count of any estimate of work under the written contract, and none of any such estimate of extra work sufficient to bring the case in that respect within said article. The allegation in respect of extra work is, that the amount and character of material used and labor performed for the excavation and filling of said fissure by the plaintiffs were, on the day next before their demand of payment thereinafter alleged, duly estimated by the defendant’s engineer. But that allegation goes only to the amount and character of the material used and the labor performed, and not at all to the sum to be paid therefor, which said article mainfestly called for, as the “total sum”, less all previous payments, was what the defendant promised to pay, if indeed a promise sufficient to support the count can be deduced therefrom in any circumstances. It follows, therefore, no promise being alleged in either cause of action, that the count is wholly bad for that reason.

It is further objected that the count is bad for not stating the facts relied upon to constitute the alleged waiver of the contract by the defendant in respect of the extra work and material required to fill the fissure in the bed of the river.

The contract provides, as we have seen, that the work should be performed thereunder according to the plans and drawings of such an engineer, which plans and drawings are made a part of the contract. The contract also provides that any work found necessary to be performed and not covered by the specifications and the contract, must be covered by an *309order in writing by the defendant, and that no allowance nor payment would be made for any work performed nor material furnished, not covered by the contract or such order.

The count avers that it was impossible to construct the dam as contemplated by the contract in accordance with said plans and drawings, because they represented the bed of the river at that place as substantially an even surface of rock or hardpan, whereas there was near the bank of the river a very deep fissure full of a substance unsuitable for the foundation of a dam, which required excavating and filling with concrete masonry in order to construct a dam suitable for the defendant’s purpose, which said condition could not have been discovered beforehand without experimenting at a great and disproportionate expense, and was not discovered by the plaintiffs until after they had executed the contract and begun work on the dam, in the progress of which they discovered the condition stated, which condition the defendant discovered at the same time, and thereupon waived the provisions of the contract as far as they related to the work required to be done by the plaintiffs and the material necessary to be furnished in order to fill the fissure and make the bed of the river at that point correspond with what was represented as its conformation in the plan of the engineer.

The defendant stops here when it says that the count is bad for not stating the facts relied upon to constitute the alleged waiver. But this is not warrantable, for the count goes on to allege the facts relied upon in this behalf, and avers that neither party had taken into account the possibility of any such work and material being required as were afterwards found necessary by reason of said fissure, and that neither could determine nor form any estimate as to how much labor and material would be necessary to fill the fissure, and that therefore no change was made in the plans and specifications, but that it was treated and considered by both parties that the work required for the perfection of the bed of the river was an independent undertaking in addition to, and entirely outside of, said written contract, and not covered by the provisions thereof requiring that any work found necessary to be performed and not covered by the specifications and the contract must be covered by an *310order in writing by the defendant, 'and paid for at actual cost plus ten per cent.

The count further avers that the plaintiffs compared the plans and specifications with the site of the dam before submitting their bid, and made every reasonable inspection requisite to submit a bid for a lump sum to cover the total expense of securing a proper foundation and building the work specified to the lines and levels and in the manner called for by the plans and specifications, and according to the plans and drawings of' the engineer, and that, relying upon the contract and said plans and specifications, they undertook and agreed to furnish all labor and material and perform all work called for thereby at and for the price of $50,727.80, as the defendant then and there well knew; that they performed accordingly, and in addition thereto, filled up said fissure with concrete masonry at a further and reasonable expense of $18,000, and thereafter, on such a day, delivered said construction and said additional masonry to the defendant, which, with full knowledge of all and singular the facts aforesaid, it then and there received and accepted; that in the execution of said contract and in fixing the price for doing the work called for thereby, neither party anticipated nor took into consideration the possibility of any such work and material being required as was ' thereafter found to be required by reason of said fissure; that because it could not be known until said work was done how expensive it would be, the cost thereof could not be estimated in advance within reasonable limits, all which the defendant well knew when it received and accepted the construction as aforesaid; that the amount and character of the material used and the work performed by the plaintiffs in and about excavating and filling said fissure were duly estimated by the defendant’s engineer; that when the plaintiffs discovered said difficulties of securing a suitable foundation for the dam, the defendant was present by its inspector, and witnessed the daily progress of the plaintiffs’ work, and knew and realized what the plaintiffs were doing, and that in the performance of said work they were not following, nor working in accordance with, the plans and drawings of the engineer, and that if they followed them, the dam would be insufficient and would not hold water, and that *311by reason of said fissure no sufficient dam could be constructed without excavating the fissure to bed rock or hardpan and filling with masonry; that with said knowledge, the defendant, desiring a satisfactory construction under said contract, and considering the conditions discovered as aforesaid as not covered by the specifications and the contract, but unforeseen when the contract was executed, permitted the plaintiffs to continue said work, well knowing that the contract provided that any work found necessary to be performed, not covered by 'the specifications and the contract, must be covered by its order in writing, and that no such order had been given, and the plaintiffs continued said ‘ work, and excavated and filled said fissure without such order, both parties treating the matter while such work was in progress and until after -the -delivery and acceptance of the completed structure, as entirely outside of any of the stipulations of said contract, unforseen, and in no wise provided for therein; and that the defendant by its. conduct aforesaid, then and there, as far as the provisions of the contract applied to said excavation and filling, waived the same, by reason of all which and of law, the defendant became and is liable to pay the plaintiffs the unpaid balance of the price named in said contract and said additional sum for extra work, whereof the plaintiffs, at such a time and place, notified the defendant and requested payment, which it neglects and refuses to make.

Thus do the facts appear upon which the plaintiffs rely to constitute a waiver. It is to be noticed that the count alleges that it was treated and considered by both parties that the work required for perfecting the bed of -the river was an independent undertaking in addition to, and entirely outside of, said written contract, and not covered by the provisions thereof requiring that any work found necessary to be performed and not covered by the specifications and the contract must be covered by an order in writing by the defendant, and be paid for at the actual cost plus ten per cent.

This allegation, being admitted by the demurrer, is more-than a waiver. It is a construction of the contract by the-parties, which, having been acted upon by the plaintiffs as it. was, precludes the defendant from repudiating it now, after *312it has received and accepted the completed structure, and is enjoying the use and benefit of the plaintiff’s outlay in respect of it. Thus, if one party to a contract knowingly leads the other party, even by silence, to believe when he executes it that a certain construction will be put upon it, he is thereby estopped from gainsaying that construction to the prejudice of the other party. Flint v. Babbitt, 59 Vt. 190, 9 Atl. 364.

But if it were otherwise, and the work necessary to perfect the bed of the river required an order in writing by the defendant, yet the allegations of the count are sufficient to show a waiver of that requirement; and it is not claimed otherwise, and can not well be, for the defendant could waive that requirement, as it was made for its benefit, and when, by its inspector, it stood by day after day and saw the work go on without objection, and was content to let it continue until finally completed, knowing that no such order had been given, and also knowing, as it must have known, that the plaintiffs were expecting extra compensation therefor, and then receiving and accepting the completed structure without objection, and ever since using the same as its own, it must be taken to have waived its right in respect of such an order. Thus, where one holding a mortgage as collateral security, agreed to accept policies of insurance on a mill, if built of such and such dimensions, and discharge the mortgage, saw the mill being built of different dimensions without objection, and when completed, accepted policies upon it, but refused to discharge his mortgage because the dimensions of the mill were varied, — it was held that he could not be heard to complain of that, as he had acquiesced in it, and therefore must discharge his mortgage. Swain v. Seamens, 9 Wall. 254, 19 L. ed. 554.

Smith v. Alker, 102 N. Y. 87, 5 N. E. 791, was an action on a building contract for the balance due and for extra work. It was held that the owner could waive a stipulation in the contract that the final payment to be made by him should not be required unless the architect certified that the contract had been fully performed to his satisfaction, and that an acceptance of the building as under a completed contract was such a waiver, and entitled the contractor to recover the sum due although no certificate had been given, and although the architect was not satisfied.

*313In Hill v. South Staffordshire Railway Co., 11 Jurist, Pt. 1 n. s. 192, the plaintiff contracted with the defendant to build a section of its road. The contract contained provisions for the execution by the plaintiff of extra, additional, and altered works, and for monthly payments by the defendant to the plaintiff during the progress of the work, of sums to be certified by the defendant’s engineers. Such certified sums were paid for a while, and until the engineers refused to certify more because they said the plaintiff had already been overpaid.' The suit was to recover the balance claimed to be due. The defendant objected, among other things, that a certificate of the engineers was necessary to a recovery of any balance. But the court said it would be a fraud on the part of the defendant to have desired, by its engineers, the alterations, additions, and omissions to be made; to have stood by and seen the expenditures going on upon them; to have taken the benefit of that expenditure; and then to refuse payment on the ground that the expenditure was incurred without proper orders having been given for the purpose.

In the specifications attached to the written contract for building the dam, is an article for referring all matters of dispute concerning the work, etc., to the defendant’s engineer, whose decision was made final. It is objected that the count is bad for not showing compliance with that article by the plaintiffs, for that such compliance is a condition precedent to their right to maintain the action. But that article applies only to disputes arising under the written contract, and not to disputes arising under the subsequent independent verbal agreement alleged in the count concerning the extra work. But treating it as applying to disputes arising under both contracts, it cannot be construed as embracing the dispute here involved, which goes to nothing concerning the work itself, but only to the question whether the defendant shall pay after having received and accepted it, and thereby waived all objection thereto, and made itself liable to pay therefor.

This objection is no more applicable to the third count than to the first count. But it is objected that the third count is bad for want of a promise by the defendant to pay. That count declares upon a new and an independent subsequent *314agreement between tbe parties for doing the extra work mentioned in the first count, in consideration of a reasonable price therefor “to be paid said plaintiffs by said defendant”. This, the plaintiffs say, is equivalent to an express promise to pay, and we think it is, for the agreement was that the defendant should pay, and that amounts to a promise to pay. 1 Chit. PL, 13 Am. ed. [*302]; Powers v. N. E. Fire Ins. Co., 69 Vt. 494, 38 Atl. 148.

The defendant pleads the arbitration article and noncompliance therewith by the plaintiffs in bar of the fourth count,which is the ordinary common count in assumpsit. The plea professes to answer the whole count, but answers, at most,only a part of it, for although the count declares generally for work and labor, materials furnished, and money laid out and expended; yet it also declares for goods sold and delivered, money lent, money had and received, and money due on an account stated, to none of which does the plea conform nor constitute an answer, for there is nothing on the face of either pleading to indicate that they relate to anything here involved; and though this objection was not taken at the hearing, it must be taken here, for the rule is that when pleadings end in a- demurrer, no fact can be treated as in the case that does not appear from the pleadings and is not admitted by the demurrer though admitted at the hearing. Columbian Granite Co. v. Townshend Co., 74 Vt. 183, 52 Atl. 432.

Judgment affirmed as to the insufficiency ■ of the first count, the sufficiency of the second count, and the insufficiency of the plea to the fourth count; but reversed as to the insufficiency of the third count, and that count adjudged sufficient. Both parties having excepted, and neither having fully prevailed thereon, neither are allowed costs vh this Court.