*1 VANCE, John H. D/B/A Co., Petitioner,
Construction
MY APARTMENT STEAK HOUSE OF ANTONIO, INC., Respondent.
SAN
No. C-2623.
Supreme Court of Texas.
May *2 prevented by
that he was Steak House completing from contract. Steak against House then filed a cross-claim seeking $43,488.75 Vance the sum of for and defective construction failure to com- plete stipulated by the contract. It was all parties en- that Interiors was Consolidated Antonio, Rogers, peti- David W. for San claim, on its titled to recover and it is not tioner. appeal. party to this Davis, Antonio, E. Charles San re- evidence, of all At the conclusion the trial spondent. granted court motions for instructed ver- against dict Vance and both Steak House BARROW, Justice. Only on the filed cross-actions each. Vance, appeal by This is an H. John perfected appeal. Vance an The court Company Vance d/b/a Construction appeals after concluding affirmed that (Vance) from a take-nothing judgment ren- to Vance had failed the cost of reme- against Apartment his suit My dered dying or necessary omissions (Steak Antonio, House Steak of San Inc. building make the conform to the contract. House) to recover on a construction con- outset, At we shall restate the well- appeals The court of tract. affirmed. We Texas rules concerning established the judgments reverse of the lower courts building measure in a contract and remand the cause to court. the trial as dispute such this. We first note that 1978, In March of Vance into a entered both Steak House Vance and are construction contract with House Steak have breached their contract. They both whereby agreed to construct a res- via have filed affirmative claims for relief 10,1978 completed by taurant to be August Moreover, their cross-actions. the evidence payment $116,000. return Vari- substantially per- indicates that Vance did delays ous occurred for which each form and that all the contract of the build- Finally, September blames other. on ing defects remediable. were 1978, 25, Steak House notified Vance the was contract terminated and de- thereafter substantially aWhen contractor has nied him access to property for further performed building he is enti undisputed work. contract that the full tled to recover contract less fully performed not was the res- although remedying the cost of those defects that completed. taurant had been substantially remediable. are $20,000 The sum was Steak withheld 848, (Tex. 270 S.W. Comm’n price. House from the contract 1925, holding approved); Dietz Memo App. subcontractor, Bldg. rial Co. v. Texas Steel One Consolidated Interior Inc., Systems, 1979,. paid, brought was not it S.W.2d — Waco Sims, n.r.e.); Perryman suit Vance and Steak writ ref’d seeking House to recover sum of (Tex.Civ.App. Tyler $2,484. n.r.e.); Vance answered and filed a cross- writ Corbin 3A A. ref’d § (1964 seeking Steak to re- Contracts Supp. action House 334-37 $8,298 1984); Perillo, remaining cover sum of due and Contracts J. Calamari & J. Guittard, 11-22, (2d 1977); under owing original contract. at 412 ed. contract Building Damages petition, Vance Contracts: Resti conceded that the tution, fully urged (1969).1 performed, had not been but 32 Tex.B.J. settings proper that 1. There numerous factual contract cases. measure of building in the arise context of a construction any allowance as well as offsets must be deter- disput, imply contract and we do not that the generally facts of the See mined case. building apply rules set forth herein will all correctly House also has a claim for Atkinson court stated the doctrine perform of substantial damages under Texas law. The measure merely equitable ance doctrine that damages for an owner when the contrac adopted was to allow a contractor who has alleged to of a construc tor is be breach substantially completed a construction con completing tion contract is the cost of *3 tract to sue the on contract rather than that are job remedying or of those defects relegated being to his cause of action for only part If of the contract remediable. not, quantum meruit. The doctrine does contractor, paid the then price has been to however, permit the contractor to recover cred the amount of the owner’s is provided the full consideration for in the payments the of his ited balance definition, By contract. this doctrine rec Turner, Braden, unpaid. still & Collie ognizes totally that the contractor has not Brookhollow, Inc., 160, Inc. v. 642 S.W.2d bargain fulfilled his under the contract—he (Tex.1982); Fuess, 164 v. Allert & Graves Nonetheless, in he is to is breach. allowed 614, 869, (1912); 870 3A Tex. S.W. recovery sue on the but his 1089, A. on Corbin Contracts remedying decreased the cost of those (1964 Supp.1984); & 485-92 & J. Calamari responsible. he is “To defects which § 14-29, (1977); Perillo, at 560 J. Contracts recovery without allow full deductions Guittard, Building Damages Contracts: compensation for some defects is to award Restitution, 91, and 32 Tex.B.J. 118-20 thing contractor not done.” Id. at has] [the (1969). recovery The formulae of we have in the The court Atkinson announced comprise damage ele just set forth the following measuring compensa- “for rule ments of the contractor’s and the owner’s tion or ... to the contractor accepted causes of action. is a well and the owner:” postulate of the common that a civil law performance, the cases of substantial litigant an affirmative claim who asserts by the contractor is amount recoverable persuade the burden to for relief has price, the contract less the reasonable finder of fact of the existence of each ele remedying the defects or omis- cost of Grieger his cause of action. v. ment of make the way sions in such a as to 85, Vega, 153 Tex. 271 S.W.2d 89-90 This building conform to the contract. Albright Long, S.W.2d allowed deduction measures 1969, writ). no part the owner for failure on — Amarillo Therefore, alleged facts enti when Vance speci- fully comply contractor to with tling him to recover for his fications. allegations denied and his were a con- The court concluded that when Id.
House, placed position in was Vance per- recovery a substantial tractor seeks on having prove every to fact essential to theory he has the burden formance Lamb, case. Shell Chemical Co. remedying the prove the reasonable cost of (Tex.1973). cross-plaintiff con- defects. Because the any on present failed to evidence tractor primary contention raised action, damage element of its cause should re-examine the is that this Court that it was not enti- held Commission Bros., 270 holding in Atkinson v. Jackson tled to recover. and shift the burden S.W. building defects to and com- remedying recognize that some courts the cost We instances, placing argue even when in favor of the owner all mentators defects on proving for relief. the cost of asserting a claim burden of contractor instances; however, we arguments for in all After consideration of the the owner underly- have concluded that the rationale change, we decline to over- law does not ing change our such rule Atkinson. (1969). tution, Guittard, Damages Building Resti- 32 Tex.B.J. 91 Cntracts: justify proposal. suggest- One reason but one conclusion under the available evi- placing proof upon is, ed for dence. That there must be no evidence owner is the owner is in a better regarding to raise a fact issue the cost of position to know of the existence and ex- remedying the defects in Steak House’s remedying tent of defects and the cost of review, building. In our we must consider such may defects. While this be true in light all of the evidence most favor- instances, some the Texas Rules of Civil Vance, disregarding contrary able to all Procedure contain various tools which a evidence inferences. See Williams may require contractor the owner to define Bennett, (Tex.1980). alleged and enumerate the in a defects replete record of this case is with building. See Tex.R.Civ.P. 166b-169. Fur- testimony concerning and other evidence ther, right the contractor obtain the repairing the cost of premises purpose enter the owner’s for the *4 by with, begin have been left Vance. To inspecting observing of what defects Bare, part-owner who Robert was a 166b(2)(c). present. Tex.R.Civ.P. House, manager of Steak testified that he Therefore, we refuse to conclude that a $20,000 price retained of the contract lack justifies changing of access or control $116,000. amount, Of that Bare estimated the rule. Atkinson $14,000 $15,000 paid that he had to to sub- point, On a related urged it has been that for work done repairs contractors or for the owner a defense establish to the building. Bare later stated that the contractor’s cause simply by of action rais- paid suppliers total amount to and subcon- ing a concerning fact issue a defect not $13,549.41; addition, in tractors was Bare by addressed Again, contractor. our $2,000 spent around for maintenance and discovery rules of permit party to limit repair work. opponent his to certain facts and defenses. $8,298. by lien filed Vance was for See Tex.R.Civ.P. 166b-169. Under these rules, figure a contractor Vance he would be allowed to testified that derived this require the owner to set by deducting forth his list of the amount of bills he Thereafter, defects. the contractor having paid $11,702— was aware of Bare — may forego any undisputed discussion of $20,000 from the withheld from Vance simply by defects at trial proffering the $8,298 Bare. The claimed includ- interrogatories discovery or other into evi- $2,484 upon by ed the owed and sued bill to effectively preclude dence. This will Thus, Consolidated. Vance’s net claim was raising owner from an issue on a defect not $5,814. A third witness on cost of previously disclosed to the contractor. repairs expert was called Steak House, Bernie Fuller. He testified that he today We holding reaffirm the in Atkin- repairing estimated the cost of the defects Therefore, breaching son. when a contrac- $12,684. not, in building Fuller was brings tor to suit recover for his substan- however, specific to itemize the able mat- performance alleges tial and the owner re- gave ters that to rise this total. construction, in mediable defects required contractor is that he did testimony concerning Bare’s the amounts substantially perform, the consideration paid by suppliers him to workmen and was contract, due him under the and the cost of competent repairs. evidence of the cost of remedying the defects due to his errors or Likewise, jury the estimate related omissions. by Bernie Fuller constituted some evidence repairing as to the the defects in cost We must now decide whether the Finally, testimony the structure. appeals affirming in court of was correct jury sufficient to directing the trial Vance was enable court’s action verdict concerning in favor of House A confront and resolve issue Vance. remedying in the defendant is entitled to a directed verdict the cost of only building. when reasonable minds could reach manship
There was a substantial conflict
and material used in the construc-
building.
jury
tion of the
found that
regard
with
to the exact cost
evidence
Bros,
Moreover,
substantially complied
Jackson
had
repairs.
Vance’s and Bare’s
with the contract and had built the house in
testimony
inwas
conflict on what
items
plans
specifica-
accordance with the
were “extras” and what items were called
agreed upon. The
tions
trial court award-
the contract. These inconsistencies
Bros,
recovery
ed Jackson
for the full
not, however, negate
and conflicts do
amount owed on the contract.
question.
injured
existence of a fact
If an
produced
has
the best evidence avail
appeal,
complained
On
that the
able, and if it
is sufficient
to afford a
Bros,
awarding
trial court erred in
Jackson
loss,
determining
reasonable basis for
jury,
the full contract
because the
recovery
Bros,
he is not to be denied a
because
although it found
had
Jackson
sub
damage
incapa
the exact amount of the
contract,
stantially complied with the
also
Coast Invest
ble of ascertainment.
Gulf
found several defects
the construction.
Rothman,
Corp.
ment
506 S.W.2d
1924),
485
party
dam
own
a
proof of the measure of a defendant’s
his
such
ages
party bringing
party
on the
suit on a sub
exactly
case allows each
to recover
stantially complete
contract.
construction
that to which he is entitled under the con-
cases,
In
nonsubstantial
tract.
general rule
Texas is that
independent
action
a con
prov
asserting a claim has the burden of
of a construction con
tractor for breach
evidence,
ing, by
preponderance
of the
tract,
proof
is on the owner
every
necessary
element
to sustain
existence,
to establish
contract’s
claim.
Northern
International — Great
Harkness,
(Tex.
Franks v.
Pacific
any damages
sustained.
(Tex.Civ.App.
S.W.2d 300
[14th
— Houston
Sweeney
County
Tarrant
Butcher &
court,
1975, writ).
no
The Atkinson
Dist.]
Constr.
however, departed from the traditional bur
n.r.e.);
1969, writ ref’d
—Fort Worth
see
proof by effectively requiring
den of
Inc.,
Center,
Franks v. Associated Air
contractor to establish the
ele
(5th Cir.1981)(“Under
F.2d
Texas
ment of the owner’s cause of action. This
law,
repairs
the reasonable cost of
is an
departure was founded on the belief that at
plaintiff’s proof
essential element
common law the contractor could not recov
damages.”)
In a suit
an owner
er under the contract in the absence of the
complete
failure
a contractor for
performance.
doctrine of substantial
“No
time,
meet the
contract on
the owner must
part
such rule has ever
been
as to the measure of dam
burden
law,
equity.”
common
much less a rule of
ages.
generally
v. Methodist
See
Walsh
A.L.
3A Corbin on Contracts
South,
Episcopal
lessened our WALLACE and of a position and awkward giously unfair concurring opinion. compliance attempting to show
contractor contract while simulta a construction
with required to dam
neously being establish that same from his
ages breach Therefore, I is indefensible.
contract previous decision in At
would overrule our Bros, adopt the rule v. kinson
that in an action
for collection
substantially
of a
com
the contract
ALBRIGHT, Petitioner,
M.
James
defendant,
pleted
contract the
construction
v.
for
to avail himself of a set-off
order
al., Respondent.
et
CITY OF HOUSTON
incomplete
from
or de
sustained
work,
has the burden of
as to
fective
No. C-2891.
damages.
the measure of such
United
of Texas.
Supreme Court
En
use Acme Maintenance
States for
Contracting
gineering Co. v. Wunderlich
June
(10th Cir.1955);
Co.,
Surety Morley rel v.
United States ex
Johnson
Cir.1938);
Co.,
(2d
Const. States, Cooperage Baltimore
ed
use
(D.C.1928);
McCay,
Alaska
v. Walsh
State
1980);
Co., Inc.,
(Alaska
& (La.App. Busby, 141
Charest v. So.2d 1962); Basso, 347 Mich. Antonoff (1956);
N.W.2d 604 Rickertsen Carska (1961);
don, 172 Neb.
Dyer Burton, Durkee,
(1908);
A.
Inc. v.
Charles
(1954);
433,
162 Ohio St. Drive-In, Indemnity Inc. v. Home
Exton
480,
mont Steel Structural
man, A.2d De 126 Vt. Kittitas, 57 Wash.2d v. Town
Blasio (1960); A.L. 3A P.2d 606 § (2d ed. on Contracts
Corbin rule re supplement) (stating the
and 1962 placing of the burden on
quiring the self-evident”); S. is “sensible owner
Williston, on Contracts Williston 1962) (“The establishing
(3d ed. burden
