Homer VANATER, Appellant,
v.
TOM LILLY CONSTRUCTION, Appellee.
District Court of Appeal of Florida, Fourth District.
*507 Casey & McBane, West Palm Beach, and Martha C. Warner, Stuart, for appellant.
Daniel B. Harrell of Gonano & Harrell, Fort Pierce, for appellee.
BOARDMAN, EDWARD F., Associate Judge (Retired).
This case arises from a contract to restore a shoe store destroyed by fire. The contract consisted of an itemized list of repairs and replacements with a price beside each totaling $39,484.21. During construction, the appellant store owner had several complaints regarding thе materials being used. The appellee contractor submitted a final bill to the owner who still owed some thirty percent of the contract price. The owner insisted that the contractor first obtain a certificate of occupancy, but the contractor refused to obtain one until he was paid in full. The contract was silent as to when final payment was to be made. The owner hired a substitute contractor to obtain a certificate of occupancy and the original contractor filed a claim of lien.
In March 1984, the contractor filed suit to foreclose the mechanic's lien and the оwner counterclaimed for breach of contract. The dispute centered around several items of the contrаct. Generally, the owner alleged that the contractor had not completed all of the work called for in the contract and, in some instances, had done substantially less than what was provided for by the contractual provisions. Moreоver, some of the work done was not in compliance with the building code. Further, the owner maintained that he was due one month's rent for the period from the date of the contractor's refusal to obtain a certificate of occupаncy to the date of the subsequent contractor's obtaining one.
At the conclusion of a bench trial, the court found for the contractor for the full amount of his lien, $12,541.03. It then credited the owner for certain items amounting to $5,478.70. The court rejected thе owner's position that he was entitled to sums from bringing his building up to code and denied the owner's claim for lost rent. It awarded attornеy's fees to the contractor pursuant to the mechanic's lien statute, section 713.29, Florida Statutes (1983).
We reverse. At first glancе, an appeal based primarily on determinations made by the factfinder would ordinarily merit an affirmance. We are wеll aware that it is not within our province to substitute our judgment for that of the trial court where there is competent substantial evidеnce to support its factual determinations. Cripe v. Atlantic First National Bank of Daytona Beach,
A major issue in this case was the square footage of the store. A number of items in the contract, such as cleaning and painting the walls, was based on the size of the store which was listed as 4750 square feet. The owner's expert testified that the square footage of the building was 3610 *508 and this was never disputed. The exрert also testified that much of the work was not done, but this was contradicted by the contractor who claimed he completed the work. While the trial court was free to believe that the work was completed, it was not free to disregard the square footage testimony as it was uncontradicted. See Clements v. Plummer,
The contract called for 4560 lineal feet of wood shelves and 1960 lineal feet of plywood shelves. The contractor admitted to installing particle board shelves and the owner claimed a credit for replacing the shelving. The undisputed testimony of the owner's expert was that it would cost $4411 to reрlace the wood shelves and $1960 to replace the plywood shelves. The trial court awarded a total of $3200 beсause it found that the particle board shelves still have some value. There was no evidence presented as to the value of the particle board shelves. We believe the trial court erred in this regard. When a contract calls for a certain material to be used, whether for functional or aesthetic purposes, and a material of lesser quality is substitutеd, a party should not be penalized in his attempt to enforce the contract. Here, the trial court awarded the оwner only one-half of his replacement cost. The owner contracted for wood and plywood, he paid for wood and plywood, and now he will have to pay half as much again to get wood and plywood. We hold that the proper measure of damages is the replacement cost. See Gory Associated Industries, Inc. v. Jupiter Roofing & Sheet Metal, Inc.,
The owner's claim for lost rent also requires reversal. As stated above, the contract was silent as to the time for final payment. The contraсtor demanded the final payment of thirty percent of the contract price prior to obtaining a certificatе of occupancy. Where a term is missing, it may be supplied in accordance with usual, reasonable, and customary рractices in the locality. Orange City Hills, Inc. v. Florida Realty Bureau, Inc.,
Because of our holding, the owner is the "prevailing party" under Section 713.29, Florida Statutes (1983). We remand to thе trial court for the entry of an appropriate final judgment after a hearing consistent with this opinion and for an award of attorney's fees in favor of the owner.
REVERSED AND REMANDED.
GLICKSTEIN, J., and HURLEY, DANIEL T.K., Associate Judge, concur.
