95 Wash. 643 | Wash. | 1917
On November 19, 1908, W. F. Hays of Seattle and Henry Hewitt, Jr. entered into the following contract :
“Tacoma, Wash., November 19, 1908.
“This memorandum, Witnesseth, That whereas W. F. Hays of Seattle, Washington, has this day assigned all his right, title, and interest to Henry Hewitt, Jr., in Certificates of Purchase of certain timber lands sold' by the sheriff of Skagit county, and also by the sheriff of Whatcom county, and also by the sheriff of King county, in pursuance of a judgment in favor of the said Hays in the King county*644 court of June 13, 1908, in Cause No. 54037. In consideration for which, the said Hewitt has this day paid said Hays the full sum of Forty-seven thousand five hundred ($47,500) dollars, and in the event that the lands conveyed by said certificates be redeemed thereunder said certificates, then the said Hewitt is to pay said Hays the further sum of forty-two thousand five hundred ($42,500) dollars, but if said lands shall not be redeemed and the sheriff of said respective counties shall execute his deed for said lands, the said Hewitt hereby agrees to hold for the said Hays, an undivided one-half interest thereto and he shall then pay to said Hays, when title thereto shall have been perfected, the said sum of forty-two thousand five hundred ($42,500) dollars. Said Hays is to prosecute any suit, action, or defense that may be necessary in the premises, to finally vest title to said lands in the said Hewitt or the payment to him of the full amount of said judgment with its interest and costs. Said Hewitt in the event that he shall take title as aforesaid, to execute to said Hays or his assigns, a good and sufficient deed to the undivided one-half interest in said lands. In the event title to said lands finally vests in said Hewitt said Hewitt is to deed to said Hays one-half thereof and to pay the further sum of $42,500 this to be in full.”
Although the contract recites the payment of $47,500 in money, only $2,500 was paid. In June, 1908, Hays attached certain property as the property of M. N. Richardson et al., and took a default judgment which, with interest and costs, aggregated about $87,000. There can be no question that, at the time the contract between Hays and Hewitt was entered into, both parties assumed that the judgment was a valid lien upon the lands which had been attached and which Hays had bid in at execution sale. The legal effect of the contract was that Hays, who did not deal in timber. lands, Sold the lands, subject to redemption, to Hewitt, who did deal in such property. After the time for redemption had passed, the sheriff executed deeds to Hewitt who, with the consent of Hays, conveyed the land to the Sumpter Lumber Company, an Oregon corporation. It afterwards being made to appear that the execution had been improvidently
Hays thereafter conveyed to appellant all his interest in the contract, and suit is brought against Hewitt to recover the amount alleged to be due under the contract which, with interest, is $127,800.
After a trial upon issues joined, judgment was rendered in favor of defendants. Appellant seeks to sustain a right of recovery upon several grounds; but, stripped of verbiage and detail, they all rest in the contentions that Hewitt got all he ever contracted for, that is, sheriff’s deeds to the property, and that the vacation of the judgment upon which the sales rested is no defense in law to an action on the contract; that, if he was not satisfied with the “titles” evidenced by the sheriff’s deeds, he should have made the certificates, or the sheriff’s deeds, over to Hays so as to enable him to “perfect” the title instead of placing them on record as he did and thereafter conveying the land to a third party, thus putting it beyond the power of Hays to furnish a better title.
We think the trial court arrived at a correct conclusion. The rights of the parties are to be measured by the contract. It is in writing, and its intent is manifest. The subject-matter of the contract was the sale and purchase of certain lands against which there appeared to be a lien of a valid judgment. That title would fail, other than by redemption, seems not to have occurred to either party. Now, for causes entirely beyond the control of Hewitt, causes chargeable to Hays’ omissions and oversights, if chargeable to anyone, the title failed. The subject-matter of the contract ceased to exist, and Hewitt is not liable either to Hays or his assignee unless it can be said that he is responsible for the failure of the title.
Hewitt made the contract, conveyed the land to the Sumpter Lumber Company, and defended the title with the full
Respondents did not buy caveat emptor. The subject-matter of the contract having failed, there is no object to which the doctrine of caveat emptor can apply. Hays sold nothing and Hewitt bought nothing. The one financed a hope. The other discounted the issue of a possible lawsuit. As it transpired and as it was held by this court, there was no title in Hays, either actually or in expectancy. The fund out of which the parties expected to reap a rich harvest having been exhausted, we know of no rule of law that could be applied to the facts in this case that will permit them to prey upon- each other.
Appellant stands in the shoes of Hays and will take nothing.