VANALT ELECTRICAL CONSTRUCTION INC., Aрpellee/Cross-Appellant v. SELCO MANUFACTURING CORPORATION, Appellant/Cross-Appellee.
Nos. 05-5239, 06-1434.
United States Court of Appeals, Third Circuit.
Argued March 27, 2007. Filed: May 8, 2007.
233 Fed. Appx. 105
For the reasons set forth above, we will DENY the Petition for Review and GRANT the Petition for Enforcement of the Decision and Order of the Board.
Mason Avrigian, Jr., [ARGUED], Jeffrey P. Wallack, Wisler, Pearlstine, Talone,
Stephen R. Knox, [ARGUED], Michael T. Hensley, Wilson, Elser, Moskowitz, Edelman & Dicker, Newark, NJ, for Appellant/Cross-Appellee.
Before: FISHER, JORDAN and ROTH, Circuit Judges.
OPINION OF THE COURT
JORDAN, Circuit Judge.
In this contract casе, Selco Manufacturing Corp. (“Selco“) appeals from a judgment of the United States District Court for the Eastern District of Pennsylvania, entered on October 26, 2005 following a jury trial, against Selco in favor of Vanalt Electrical Construction, Inc. (“Vanalt“) in the amount of $300,000. Vanalt cross-appeals from the District Court‘s order, entered on December 15, 2005, denying Vanalt‘s request for prejudgment interest.
For the reasons that follow, we will vacate the judgment against Selco and remand for a new trial to determine whether Vanalt may reсover damages in this case and, if so, in what amount.
I.
In September 2000, Vanalt entered into a contract with PKF-Mark III, Inc., agreeing to perform electrical work on a project for the Southeastern Pennsylvania Transportation Authority (“SEPTA“). Vanalt turned to Selco in June 2001 for a price quote on multi-outlet underground cable connectors for the SEPTA project. Selco sent the quote to Vanalt on June 20, 2001. By March 2002, SEPTA had approved the use of Selco‘s connectors, and, on March 12, 2002, Vanalt sent a purchase order to Selco for 73 connectors at a total price of $54,906. The purchase order confirmed that the parties had agreed on the specifications for the connectors, including the crucial specification that the connectors “shall be pre-insulated, watertight and submersible.” Selco started supplying the connectors in June 2002, and all the connectors were installed by Vanalt between June and November 2002.
Vanalt tested the system containing the installed connectors for the first time in November 2002. Essentially every segment of the system failed. Vanalt notified Selco of the test results on December 9, 2002, contending that pin-holes in the insulation caused the connectors to fail in a wet environment. Vanalt‘s efforts to have Selco take responsibility for resolving the problems with the connectors were not successful and, under pressure to meet its contractual obligations on the SEPTA project, Vanalt decided to fix the connectors itself. By August 2003, the connectors were satisfactory.
After Selco refused to pay Vanalt for the costs associated with fixing the connectors, Vanalt filed suit in the United States District Court for the Eastern District of Pennsylvania on December 16, 2003, claiming that Selco had breached its contract, its express warranty that the connectors would be watertight and submersible, and its implied warranty that the connectors would be fit for a particular purpose. At trial in October 2005, the jury found in favor of Vanalt on all three claims and awarded $300,000 in damages. The District Court thereafter denied Vanalt‘s request for prejudgment interest. Selco appeals from the judgment entered by the District Court pursuant to the jury‘s verdict. Vanalt cross-appeals on the order denying prejudgment interest.
The District Court had subject matter jurisdiction over this case pursuant to
II.
Selco argues that the District Court erred during the trial by ruling as a matter of law that the contract between Selco and Vanalt did not include terms that limited Selco‘s liability for consequential damages arising from the connectors. Selco argues, and we agree, that the District Court‘s ruling was in effect a judgment as a matter of law against Selco on the affirmative defense that it had limited its liability by adding certain terms to the contract.1 Our review of the District
Selco presented evidence that its standard contract terms and conditions state that Selco “will not allow or be liable, under any circumstances, for any special, incidental, indirect or consequential damages of claims arising from the supply or use of any material furnished by it.” Vanalt presented evidence that it never received the document containing that language and so the limitation on liability was not part of its contract with Selco. In response, three Selco employees testified that it was Selco‘s standard policy to attach the document to every quote it submitted.
The District Court ruled that, even viewing the evidence in the light most favorable to Selco, no jury could conclude that the document was part of the contract. We must disagree. According to
Evidence of the habit of a person or of the routine practice of an organization, whether corroborated or not and regardless of the presence of eyewitnesses, is relevant to provе that the conduct of the person or organization on a particular occasion was in conformity with the habit or routine practice.
III.
Selco also argues that the District Court erred by instructing the jury that Selco bore the burden of proof as to whether Vanalt provided reasonable notice to Selco of the breach, as required by
Selco‘s sale of goods to Vanalt is governed by Pennsylvania‘s enactment of the Uniform Commercial Code (“UCC“),
The District Court‘s instructions set forth a requirement for the buyer to give the seller reasonable notice of a defect, as well as a requirement for the buyer to give the seller a reasonable time to cure the defect. One of the challenges in this case is finding the legal basis for requiring Vanalt to give Selco an opportunity to cure. The District Court was apparently guided by the parties’ proposed jury instructions, which stated that the seller must be given a reasonable time to cure.3 The parties supported that part of their proposed instructions4 with citations to
If the buyer rejects goods as nonconforming,
In this appeal, both Selco and Vanalt argue over the interpretation of
That does not end the inquiry, however, because even if notice is not necessary to a finding of breach, it may still be a prerequisite to recovery for breach, and, hence, the burden of proof would still be
Because we conclude that the Pennsylvania Supreme Court would place the burden of proving reasonable notice on the buyer, it follows that the District Court‘s instruction on this point was an incorrect statement of the law. Vanalt contends that, even if the District Court was in error, the error was harmless, but that is not so.8 Selco had argued that the
IV.
Selco also argues that the District Court erred in admitting particular exрert testimony and other evidence that Selco contends was unfairly prejudicial. As we write solely for the benefit of the parties, we need not dilate on these evidentiary rulings. Suffice it to say we have reviewed the rulings for abuse of discretion, Abrams v. Lightolier Inc., 50 F.3d 1204, 1213 (3d Cir.1995); In re Paoli R.R. Yard PCB Litig., 916 F.2d 829, 856 n. 33 (3d Cir.1990), and, in light of the record, have concluded that there was no abuse of discretion in admitting the evidence of which Selco complains.
As for Vanalt‘s cross-appeal regarding prejudgment interest, we agree with the District Court that Vanalt is not entitled to prejudgment interest as а matter of right under Pennsylvania law. See Black Gold Coal Corp. v. Shawville Coal Co., 730 F.2d 941, 943-44 (3d Cir.1984). We also conclude that, on this record, the District Court did not abuse its discretion in choosing not to award prejudgment interest. However, because we will vacate the judgment and remand for a new trial, we will also vacate the order denying prejudgment interest. While we do not imply that the result should be different after the new trial, we do not wish to tie the District Court‘s hands in its consideration of the issue in light of the record that develops on remand.
V.
The legal errors discussed above require us to vacate the damages award against
2002 describing problems with the connectors. However, Selco did contest whether that letter constituted reasonable notice, because delivery of the connectors began some six months earlier, in June 2002. At trial, Selco argued: “So, what kind of opportunity did SELCO have here? Was it a reasonable opportunity? Well, Vanalt notified SELCO in December of 2002, about a month after the problems arose and about six months after delivery. Then SELCO responded.” Later, while discussing mitigation of damagеs, Selco argued: “Does it make sense to you that an experienced electrical contractor [Vanalt] will wait months and months after he‘s installed these connectors to do any testing? Did Vanalt even test each section as it went in? ... No. They waited until everything was in and then they tested it and they found problems.” In our view, those arguments adequately set forth Selco‘s position that Vanalt was unreasonable in failing to give notice until several months after delivery began. Cf. Int‘l Union of Electronic, Electric, Salaried, Mach. & Furniture Workers v. Murata Erie N. Am., Inc., 980 F.2d 889, 902 n. 12 (3d Cir.1992) (concluding that the defendant‘s position was sufficiently сlear from its recitation of the facts to preserve that position). The District Court apparently agreed that reasonable notice was an issue at trial, because, significantly, it instructed the jury on that issue. See Murata, 980 F.2d at 898 n. 6 (concluding that the District Court‘s treatment of an issue as part of the case supported conclusion that the issue was adequately raised).
Thus, while Selco agreed that it received notice in December 2002, it argued, and a reasonable jury could have concluded, that such notice was not reasonable under the circumstances. The error in the jury instructions was therefore not harmless. Cf. Armstrong, 438 F.3d at 246 (concluding that an error was not harmless because “but for [the] error a reasonable jury could have found in favor of [the plaintiff]“).
FISHER, Circuit Judge, concurring.
Although I agree with the result reached by the majority, I write separately as I disagree with the harmless error analysis based on the parties’ arguments in this case. While the case law in this area is limited, I agree with the majоrity‘s determination that the buyer has the burden of proving breach and that it provided notice within a reasonable time to the seller that a breach occurred. The District Court‘s jury instructions treated notice and opportunity to cure as an affirmative defense thereby improperly placing the burden on Selco. Although the instruction was improper, I believe that it was harmless error.
As discussed by the majority, Vanalt had the burden of proving that it provided Selco with notice of the breach within a reasonable time. Such notiсe provides a seller with a reasonable time to cure. Although the focus is on notice, the parties mistakenly focus on whether there was a reasonable opportunity to cure. This improper focus is what leads me to depart from the majority‘s analysis.
Selco admitted at trial and in its briefs to this Court that Vanalt provided it with notice. Selco never argued that the timing of the notice was unreasonable, rather its argument was limited to a claim that Vanalt did not provide it with a reasonable opportunity to cure. As the majority points out, in its closing argument Selco stated: “So, what kind of opportunity did Selco have here? Was it a reasonable opportunity?” Opportunity refers to the opportunity to cure, not whether Vanalt provided reasonable notice. The argument regarding mitigation of damages similarly does not raise any issue regarding the reasonableness of the notice provided. Therefore, Selco admitted that Vanalt met its burden of proving notice.
Selco‘s admission makes the flawed jury instructions a harmless еrror. An error is harmless “only if it is highly probable that the error did not affect the outcome of the case.” Forrest v. Beloit Corp., 424 F.3d 344, 349 (3d Cir.2005). The admission of receipt of notice makes it highly probable that the improper jury instruction did not affect the outcome of the case. Although the error was harmless, on remand, the District Court‘s jury instruction should place the burden of proving notice on Vanalt. Therefore, I concur in the outcome of this case.
Notes
The Court‘s reasoning demonstrates that the ruling was indeed a judgment as a matter of law on Selco‘s defense. Vanalt‘s brief indicates that it also interpreted the District Court‘s ruling in this way. Vanalt Answering Brief at 26 (quoting Buczek v. Continental Cas. Ins. Co., 378 F.3d 284, 288 (3d Cir.2004), for this Court‘s standard of review for a judgment as a matter оf law).[The first of the] issues remaining that I told counsel I‘d discuss here is the issue the term and condition [sic] of the cоntract, which I find, as a matter of law, was not a part of this contract. The evidence doesn‘t support, in my opinion, a finding by the jury that these terms and conditions identified in the record ... were part of the contract and the jury would have to guess to reach such a conclusion.
[I]f you ... conclude that there‘s been a breach of ... warranties or the contract, before considering damages you must consider whether there was an opportunity given to SELCO to cure. It‘s called an opportunity to cure. And this simply means this. When a buyer purchases goods from a seller that are nonconforming, ... [t]he buyer must, within a reasonable time, provide the seller with notice of the problem and thereby provide the seller with a reasonable time and opportunity to cure the breach. Now, all of this is just сommon sense. You find a fault, you say, hey, guys, can you fix it up? That‘s what we‘re talking about. Now, a reasonable time to cure a breach depends on the nature and attending circumstances of the breach and the actions needed to effect the cure. Based upon the evidence, you must decide whether Vanalt in this case provided SELCO with reasonable notice and opportunity to cure prior to Vanalt having to remedy the problem at its own cost and whether SELCO ever notified Vanalt of any desire to insрect, test, or sample the multi-outlet connectors that Vanalt refused or failed to allow.... The question is, has defendant shown here that plaintiff did not give them an opportunity to cure? And, as I said, in determining that situation, you have to base it upon all the evidence that was presented with regard to that issue.
... I told you about the burden of proof, I told you that the defendant has the burden of proving whether or not sufficient time to cure was given here.
(a) General rule. —Where any tender or delivery by the seller is rejected because nonconforming and the time for performance has not yet expired, the seller may seаsonably notify the buyer of his intention to cure and may then within the contract time make a conforming delivery.
(b) Rejection of tender which seller believed acceptable. —Where the buyer rejects a nonconforming tender which the seller had reasonable grounds to believe would be acceptable with or without money allowance the seller may if he seasonably notifies the buyer have a further reasonable time to substitute a conforming tender.
It is true thаt Selco does not contest that it received a letter from Vanalt in December
