21 Neb. 36 | Neb. | 1887
On August 19, 1884, plaintiff filed a petition in court below, alleging in substance:
1st. That defendant is indebted to plaintiff for moving 20,000 cubic yards of dirt on section 25 of Kenesaw and Oxford branch of B. & M. R. R., at agreed price of 18 cents per cubic yard, amounting to $3,600.
2d. That on or,about February 1, 1884, plaintiff and defendant entered into contract by which plaintiff was to do the clearing, grubbing, and grading of section 25 of said railroad work, to be commenced on or before March 1, 1884, and done by July 1, 1884.
If in judgment of engineer plaintiff was not prosecuting work with such vigor as to insure it being done as contracted, defendant could serve notice to that effect on plaintiff, and if plaintiff fail for three days to put on enough force defendant could' either put on extra force and charge same to plaintiff, or could terminate contract. Plaintiff was at all times ready and willing to perform, and did so except when prevented by defendant. (See contract, exhibit A.)
3d. Plaintiff prays damages in sum of $9,900.
On October 29 defendant answered, making a general denial except as to those matters expressly admitted.
1st. Admits the contract as alleged.
2d. Alleges that plaintiff at no time prosecuted work so as to complete it in time contracted, and that defendant duly served notice to plaintiff to increase force. Plaintiff failing to increase force, defendant on 14th of May took possession of work, but not till plaintiff had abandoned it, and defendant then relet a small portion of work, and gave plaintiff benefit of profits. Defendant took possession of work May 14th, 1884.
That after notice was served, an'd plaintiff failed to increase force, defendant put on extra force and completed work, and charged costs of same to plaintiff. ■ Defendant admits that plaintiff removed and filled 20,000 cubic yards, but alleges full payment as work progressed, by virtue of terms of contract. That defendant was compelled to pay out more for completion of job than plaintiff was to have for all the work, and plaintiff owes defendant $1,469.53.
On December 29, 1884, plaintiff replies:
Denying that any complaint was made about the work, or that engineer ever made any complaint or decision that plaintiff was not vigorously prosecuting work, or that any notice thereof was given plaintiff. Alleges that engineer. was under influence and control of defendant, and colluded
On the 3d day of June, 1885, there was a trial to a jury, with verdict for plaintiff for $5.00.
The plaintiff's motion for a new trial having been overruled, and a judgment rendered on the verdict, the plaintiff brings the cause to this court on error.
There are thirty-three errors assigned; but as Ave were all of the opinion at the argument that there must be a new trial for error in the admission of the time books of the defendant in evidence on the trial, none of the other assignments Avill be considered. Our examination Avill accordingly be confined to number 29 of plaintiff's assignments, Avhich is as folloAvs:
“ 29. The court erred in admitting, over the plaintiff's objection, the book account and the account book marked on the back A\rith lead pencil, Uloldredge,' and given as a part of the answer 1126 of the witness John Muldoon.''
The book referred to as having been offered and received in cyidence in the above assignment of error is the time book of the defendant, used to keep the time of the work
Section 346 of the-civil code provides that “Books of account containing charges by one party against the other, made in the ordinary course of business, are receivable in evidence only under the following circumstances, subject to all just exceptions as to credibility: 1st. The books must show a continuous dealing with persons generally, or several items of charges at different times against the other party, in the same book. 2d. It must be shown by the party’s oath, or otherwise, that they are his books of original entries. 3d. It must be shown in like manner that the charges were made at or near the time of the transactions therein entered, unless satisfactory reasons appear for not making such proof. 4th. The charges must also be verified by the party or the clerk Avho made the entries,, to the effect that they believe them just and true, or a sufficient reason must be given Avhy the verification is not made.”
I knoAV of no authority outside of the aboAe section of statute for the admission of books of account or time-books
In the case of Mathes v. Robinson, 8 Met., 269, an account for labor performed by the. plaintiff and his apprentice for the defendant, was proven by a book kept in the same general manner as the book in the case at bar, except that there the page of the book ruled off the same as in this case is headed “ Mr. David Robinson, Dr: to,” then folloAvs the names of plaintiff and of his apprentice on separate lines, etc. Here the name of Van EArery does not appear anywhere on the book. There the account was evidently kept for the purpose of charging the work of the plaintiff in that case, and of his apprentice, to the defendant therein; here the account Avas evidently kept for the purpose of crediting each individual laborer with his time of labor and on the face of the book, its proprietor, the employer of the laborers, AAras charged in favor of each laborer with the number of days’ work, as there shown.
While I am quite clear that a book of account, to be admissible in evidence, as sucli must consist of charges by
For error in the admission of the said book in evidence, the judgment of the district court is reversed and the cause remanded for further proceedings in accordance with law.
Reversed and remanded.