76 Neb. 816 | Neb. | 1906
Tbe plaintiff was employed under *a verbal contract to dig a well for tbe defendant; and, on September 30, 1904, brought this suit to recover $65, tbe remainder alleged to be due upon tbe contract price. Plaintiff introduced evidence to tbe effect that said contract was entered into and. completed in May, 1901.. Defendant testified that the contract was entered into in the spring of 1900. Tbe main contention in tbe case is that tbe action is barred by tbe statute of limitations. Tbe jury returned a verdict for plaintiff for $65 and interest, and defendant prosecutes error to this court.
1. Upon tbe trial tbe court instructed tbe jury that, in order to sustain bis defense of tbe statute of limitations, tbe burden was upon tbe defendant to show that tbe well in question was dug more than four years prior to Septem
Again, the evidence in the case did not show when the action was begun, and the defendant argues that it was error for the court to recite that fact in the instruction complained of.. The case was brought to the district court-by appeal from a justice of the peace, and the trial judge had before him the original papers, and it was proper for-him to take judicial notice of' the time when the action was instituted and base his instruction as to the period of limitation upon the information contained in the justice’s transcript. The record before us does not show that the recitation in the instruction complained of, as to when the action was commenced before the justice, was a misstatement of fact, and we cannot presume error.
3. The other assignments of error pertain to the court’s rulings upon the rejection and reception of evidence. We have carefully examined all of the assignments of error, and are clearly of the opinion that no prejudicial error was committed by the trial court. We therefore recommend that the judgment of the district court be affirmed.
By the Court: For the reasons stated in the foregoing opinion, the judgment of the district court is
Affirmed.