Valley Metal Works, Inc. v. A. O. Smith-Inland, Inc.Valley Metal Works, Inc. v. A. O. Smith-Inland, Inc.
Appellant asserts, as a matter of law, that it is entitled to a mechanic’s and materialman’s lien against the property of appellee
The chancellor found there was no privity of contract between Valley and anyone except Aircon and that Valley, Aircon and Chempro were material suppliers and not subcontractors or contractors. Valley contends the chancellor erred inasmuch as it is entitled to its asserted lien as a matter of law. Appellant Valley argues the only issue is whether Valley, which delivered to Smith’s premises an item designed and fabricated specifically for installation there, is entitled to a mechanic’s and materialman’s lien. Valley contends that the provisions of our statute were intended to benefit one such as itself, which, as here, contracts with a subcontractor.
Appellant relies upon Ark. Stat. Ann. § 51-601 (Repl. 1971) asserting that it supplied the materials in issue “by virtue of [a] contract with the ...., subcontractor [Aircon] .... ” and therefore is entitled to a lien within the meaning of that statutory language. Appellant reinforces its argument by citing Ark. Stat. Ann. § 51-625 (Repl. 1975) which appellant says defines and manifests the legislative intent that a “subcontractor” includes “all persons furnishing things or doing work . . . . ”
Appellees cite Sweetser Const. Co. v. Newman Bros., Inc.,
We think the rationale of the case there is applicable to the case at bar. There, as here, the prime contractor contracted with a Fort Smith structural steel company, a materialman, to furnish certain items to be used in a building. Included was an item which was manufactured “by Newman Bros., Inc.” Fort Smith Steel then placed an order for this item with an Oklahoma steel company which in turn ordered the item from Newman Bros., which manufactured and shipped it to the job site. The prime contractor paid Fort Smith Steel for this item and all other items furnished by it. Fort Smith Steel paid the Oklahoma steel company for the specific item. That company did not pay Newman Brothers. There we held that Newman was a remote supplier, had no privity of contract with the prime contractor and was not entitled to recover on the prime contractor’s bond. There we further said:
It is contended by appellee that the Fort Smith Company was a subcontractor. Conceding, without deciding, this to be true, it avails appellee nothing because appellee did not deal with that company but with the Oklahoma Company which has been paid in full.....
The chancellor was correct in disallowing the asserted lien.
Affirmed.