UTILITY AIR REGULATORY GROUP, Petitioner v. ENVIRONMENTAL PROTECTION AGENCY, Respondent Edgecombe Genco, LLC, et al., Intervenors.
Nos. 12-1166, 12-1366, 12-1420
United States Court of Appeals, District of Columbia Circuit.
Argued Dec. 10, 2013. Decided March 11, 2014.
744 F.3d 741
David B. Rivkin, Jr., Lee A. Casey, Mark W. DeLaquil, Andrew M. Grossman, Lisa M. Jaeger, Eric A. Groten, and Jeremy C. Marwell were on the brief for intervenors Edgecombe Genco, LLC, et al. in support of petitioners.
Amanda Shafer Berman, Attorney, U.S. Department of Justice, argued the cause for respondent. On the brief were Robert G. Dreher, Acting Assistant Attorney General, and Norman L. Rave, Jr., Attorney. Eric G. Hosteller and Matthew R. Oakes, Attorneys, entered appearances.
Pamela A. Campos, argued the cause for Environmental Intervenors in support of respondent. With her on the briefs were Tomás E. Carbonell, Shannon Smyth, James S. Pew, Neil E. Gormley, Sean H. Donahue, Sanjay Narayan, John D. Walke, and John T. Suttles.
Before: GARLAND, Chief Judge, and ROGERS and KAVANAUGH, Circuit Judges.
Opinion for the Court filed by Chief Judge GARLAND.
Concurring opinion filed by Circuit Judge KAVANAUGH.
GARLAND, Chief Judge:
The Utility Air Regulatory Group and the State of Texas challenge 2009 and 2012 final rules issued by the Environmental
I
The
Fossil-fuel-fired steam generating units are boilers that produce electricity. In so doing, they emit particulate matter into the atmosphere. Because EPA determined that those emissions “may contribute significantly to air pollution which causes or contributes to the endangerment of public health or welfare,” List of Categories of Stationary Sources, 36 Fed.Reg. 5931, 5931 (Mar. 31, 1971), it promulgated new source performance standards for those units. The regulations are divided into four subparts within
To ensure that steam generating units comply with emission limits, EPA requires that they measure the particulate matter in their emissions. When EPA initially promulgated the regulations, the only way to measure such emissions was to perform a manual test. See Standards of Performance for New Stationary Sources, 36 Fed. Reg. 24,876, 24,888-90 (Dec. 23, 1971). To provide an alternative (and less expensive) way to assess compliance, EPA later added opacity standards to its boiler rules. See Standards of Performance for New Stationary Sources: Additions and Miscellaneous Amendments, 39 Fed.Reg. 9308,
A newer form of monitoring technology is a continuous emissions monitoring system (CEMS). A CEMS, like a COMS, requires the installation of monitoring equipment in the unit‘s stack. But a CEMS measures pollutants directly, rather than by measuring opacity as a proxy. Both a CEMS and a COMS measure only filterable particulate matter—which is emitted from the stack as a solid. They do not measure condensable particulate matter—which is emitted as a gas, but turns liquid or solid upon exiting the stack. Visual inspection, by contrast, can measure both. Historically, however, only filterable particulate matter has been subject to emission limitations.
In 2006 and 2007, EPA gave facilities the option of installing particulate matter CEMS as “an alternative method to demonstrate continuous compliance and as an alternative to opacity ... monitoring requirements.” Standards of Performance [for Subparts Da, Db, and Dc Units], 71 Fed.Reg. 9866, 9867-68 (Feb. 27, 2006); see Standards of Performance [for Subparts D, Da, Db, and Dc Units], 72 Fed. Reg. 32,710, 32,719 (June 13, 2007). The agency said that, because particulate matter CEMS “measure the pollutant of primary interest they provide adequate assurance of [particulate matter] control device performance, and continuous opacity monitoring is an unnecessary burden to affected sources using” CEMS. Standards of Performance [for Subparts D, Da, Db, and Dc Units]; Reconsideration and Amendments, 72 Fed.Reg. 6320, 6322 (proposed Feb. 9, 2007). EPA did not, however, eliminate the opacity standards themselves; it merely said that facilities using CEMS were no longer required to install and operate COMS. See Standards of Performance [for Subparts D, Da, Db, and Dc Units], 73 Fed.Reg. 33,642, 33,644 (proposed June 12, 2008) [hereinafter 2008 Proposal].
In 2008, EPA published a notice of proposed rulemaking, seeking comment on the possible elimination of opacity standards altogether for facilities using CEMS. See id. at 33,646. The agency said that elimination of such standards at those units might be appropriate, “[s]ince opacity data has been used as a surrogate for [particulate matter] emissions and since [particulate matter] CEMS give a more direct continuous measurement of the primary pollutant of interest causing opacity.” Id. (footnote omitted). EPA noted, however, that opacity is useful not only as a proxy for pollutants, but also “as an indicator of control device operation and proper maintenance.” Id. at 33,646 n. 1.
The 2009 final rule exempted all units using particulate matter CEMS from all opacity standards and monitoring requirements, but conditioned the exemption on their compliance with an emission standard for filterable particulate matter of 0.03 pounds per million British thermal units (lb/MMBtu) or less, rather than any otherwise applicable, higher limits. See Standards of Performance [for Subparts D, Da, Db, and Dc Units], 74 Fed.Reg. 5072, 5073-74 (Jan. 28, 2009) [hereinafter 2009 Rule]. For Subpart D units, for exam
If a unit that was using a particulate matter CEMS did not comply with the lower limit, the 2009 rule required it “to either use a COMS or perform periodic visual inspections to comply with the opacity standard.” Id. at 5074. The frequency of such inspections depended on the results of the most recent inspection. See id. In addition, the rule required all facilities to measure and report emissions of condensable particulate matter. See id. at 5073.
UARG filed a petition for reconsideration of the 2009 rule. Among other things, it asked EPA to reconsider its decision to limit the exemption from the opacity standard and monitoring requirements to units complying with the 0.03 lb/MMBtu emission standard. EPA granted the petition for reconsideration. At the same time, it published notice of a new proposed rule. In most respects, the proposal tracked the 2009 final rule. It contained only two differences relevant here: First, EPA proposed a total (that is, filterable plus condensable) particulate matter emission limit for certain Subpart Da units on which construction, reconstruction, or modification commenced after May 3, 2011. Second, EPA proposed to add an affirmative defense to civil penalties for exceedances of emission limits that are caused by malfunctions. See Standards of Performance [for Subparts D, Da, Db, and Dc Units], 76 Fed.Reg. 24,976, 25,061, 25,064, 25,071 (proposed May 3, 2011) [hereinafter 2011 Proposal].
Thereafter, UARG submitted a new round of comments. It argued that EPA should exempt all Subpart D units using CEMS from the opacity standard and monitoring requirements because CEMS are sufficiently accurate to ensure compliance with emission standards. The Texas Commission on Environmental Quality also submitted comments urging EPA to revise its rules to allow steam generating units to use state-law affirmative defenses in lieu of the federal affirmative defense the agency had proposed.
On February 16, 2012, EPA issued another final rule. Standards of Performance [for Subparts D, Da, Db, and Dc Units], 77 Fed Reg. 9304 (Feb. 16, 2012) [hereinafter 2012 Rule]. The 2012 rule did not expand the exemption from the opacity standard or monitoring requirements. Id. at 9424. Although it reduced the frequency of periodic visual opacity inspections for Subpart Da facilities not using COMS, see id. at 9457, it did not do so for Subparts D, Db, and Dc facilities, see id. at 9448, 9460, 9463. The 2012 rule also required certain Subpart Da units—those on which construction, reconstruction, or modification commenced after May 3, 2011—to test for condensable particulate matter. See id. at 9458. Finally, the rule did not allow the use of state-law affirmative defenses. Id. at 9433.
Thereafter, UARG and the State of Texas filed petitions for agency reconsideration as well as for judicial review. EPA has not yet acted on the petitions for reconsideration. The petitions for judicial review are now before us.
II
We begin with two issues regarding the scope of our review: the law that determines which of the petitioners’ challenges are properly before us, and the standards for reviewing those challenges that are.
A
This court‘s general view is that “a pending petition for [agency] rehearing ... render[s] the underlying agency action nonfinal (and hence unreviewable) with respect to the filing party.” United Transp. Union v. ICC, 871 F.2d 1114, 1116 (D.C.Cir.1989); see, e.g.,
Nonetheless, even under the
Only an objection to a rule or procedure which was raised with reasonable specificity during the period for public comment ... may be raised during judicial review. If the person raising an objection can demonstrate to the Administrator that it was impracticable to raise such objection within such time or if the grounds for such objection arose after the period for public comment ... and if such objection is of central relevance to the outcome of the rule, the Administrator shall convene a proceeding for reconsideration of the rule.... If the Administrator refuses to convene such a proceeding, such person may seek review of such refusal in the United States court of appeals for the appropriate circuit....
The first sentence of this subsection flatly states that “[o]nly an objection to a rule or procedure which was raised ... during the period for public comment ... may be raised during judicial review.” Standing alone, the sentence indicates that an objection raised for the first time in a petition for reconsideration may not be raised in court, because such an objection was, by definition, not raised “during the period for public comment.”
The second and third sentences create a limited exception to the bar imposed by the first. As the second sentence states, if it was impracticable to raise a particular objection during the comment period or the grounds for the objection arose after that period, and if the objection is of central relevance to the outcome of the rule, “the Administrator shall convene a proceeding for reconsideration of the rule.” Presumably, a party can seek judicial review of the outcome of such a reconsideration proceeding. But that sentence (together with the one that precedes it) would be pointless if a court could hear an objection raised for the first time in a petition for reconsideration before the proceeding was completed.
The third sentence indicates what a petitioner may do “if the Administrator refuses to convene” a reconsideration proceeding. In that circumstance, a peti
In sum, although the filing of a petition for reconsideration does not render a Clean Air Act rule nonfinal for purposes of judicial review, the only objections that may immediately be raised upon judicial review are those that were raised during the public comment period. Objections raised for the first time in a petition for reconsideration must await EPA‘s action on that petition. See Oklahoma v. EPA, 723 F.3d 1201, 1214-15 (10th Cir. 2013); see generally Appalachian Power Co. v. EPA, 249 F.3d 1032, 1055, 1065 (D.C.Cir.2001); North Dakota v. EPA, 730 F.3d 750, 770-71 (8th Cir.2013).
At oral argument, UARG maintained that, even if it cannot obtain judicial review of substantive challenges raised for the first time in a still-pending petition for reconsideration, it can obtain judicial review of procedural challenges raised for the first time in such a petition. But the language of the
Accordingly, because EPA has not yet resolved the petitioners’ petitions for reconsideration, the only objections that are properly before us are those the petitioners made during the public comment periods.
B
We may vacate a final rule promulgated under the
As under the APA, we may also vacate a rule under the
III
The petitioners raise several challenges that are not properly before us. They object to the following: the 2012 rule‘s condensable particulate matter testing requirement for Subpart Da units; the rule‘s establishment of a different frequency for periodic visual opacity inspections under Subparts D, Db, and Dc than under Subpart Da; and the agency‘s suggestion that it would permit the use of state-law affirmative defenses in the context of the mercury and air toxics (MATS) emission standards for coal- and oil-fired electric utility steam generating units (EGUs), issued pursuant to
The following subsections address the objections that the petitioners did raise during the comment period.
A
UARG challenges the requirement—included in the 2009 rule and reaffirmed in the 2012 rule—that Subparts D, Db, and Dc boilers emitting more than 0.03 lb/MMBtu of particulate matter remain subject to the opacity standard and must install COMS or perform periodic visual opacity inspections, even if they use particulate matter CEMS.
1. UARG contends that continuing to subject boilers emitting more than 0.03 lb/MMBtu of particulate matter to an opacity standard and opacity monitoring requirements, while exempting boilers emitting that amount or less, was arbitrary and capricious. We disagree. In its 2009 rule, EPA explained that sources emitting 0.03 lb/MMBtu or less of particulate matter “will operate with little or no visible emissions,” and thus “an opacity standard is no longer necessary for these sources.” 2009 Rule, 74 Fed.Reg. at 5073. “At this emission rate,” the agency said, the existence of any “visible emissions may indicate that the [particulate matter] control device is not operating properly.” Id. at 5074. Hence, for a source that is meeting this emission standard, no opacity standard is needed because any visible opacity will indicate improper operation.
By contrast, units emitting more than 0.03 lb/MMBtu of particulate matter “may have some visible emissions” even if their particulate matter control devices are op-
UARG also contends that EPA was unreasonable, not just in retaining an opacity standard for units emitting more than 0.03 lb/MMBtu of particulate matter, but also in requiring them to use a COMS or perform periodic visual opacity inspections. But as just explained, the purpose of retaining the opacity standard for such a unit is to provide a real-time check to ensure that its particulate matter control device is functioning properly. See 2009 Rule, 74 Fed.Reg. at 5073-74; 2008 Proposal, 73 Fed.Reg. at 33,646 n. 1. Using a COMS or performing periodic visual opacity inspections provides that check. See id. Because EPA has articulated a reasonable explanation for requiring opacity monitoring, petitioner‘s challenge to this requirement fails.
We also reject UARG‘s related contention that EPA‘s action was arbitrary and capricious because it failed to address “the impacts of the periodic visible emissions testing on the Subpart D units it had proposed to exempt from the standard, but did not exempt in the final rule.” Pet‘rs’ Br. 35. Whether or not a failure to consider the burden imposed on those units would have been arbitrary and capricious, the contention fails because EPA did consider the burden imposed by its visual opacity inspection requirement. See 2009 Rule, 74 Fed.Reg. at 5074; see also 2008 Proposal, 73 Fed.Reg. at 33,643 (noting that the proposal, which included visual opacity inspection requirements, “would not significantly change our original projections for the rule‘s compliance costs, ... burden on industry, or the number of affected facilities“); id. at 33,645 (noting that “the use of a digital camera system” to comply with the opacity monitoring requirements “would also reduce compliance costs“); 2012 Rule, 77 Fed.Reg. at 9425 (analyzing the power industry‘s compliance costs).
2. UARG further contends that, in promulgating the 2009 rule, EPA violated the
B
Texas’ petition for review challenges EPA‘s refusal to allow state-law affirmative defenses against the enforcement of new source performance standards.
As noted earlier, see supra Part I, EPA‘s 2011 notice proposed adding an affirmative defense to civil penalties when a facility exceeds emission limits as a result of a malfunction. See 2011 Proposal, 76 Fed.Reg. at 25,064. EPA proposed that the defense be available only “where the event that causes an exceedance of the emission limit” is “sudden, infrequent, not reasonably preventable and not caused by poor maintenance and or careless operation.” Id. In its comments during the rulemaking, Texas asked EPA to consider allowing states to use their own state-law affirmative defenses in lieu of the federal defense that EPA proposed. Specifically, Texas wanted to use the affirmative defense provisions in its State Implementation Plan (SIP), which EPA had previously approved under a different Clean Air Act provision,
Texas maintains that EPA did not explain why it declined to approve Texas’ use of a state-specific affirmative defense for the new source performance standards under
Texas protests that this explanation is arbitrary and capricious because EPA suggested, in responding to comments in a different rulemaking, that it would permit state-specific affirmative defenses with respect to different emission standards—the mercury and air toxics (MATS) emission standards for coal- and oil-fired EGUs, issued pursuant to
IV
For the foregoing reasons, the petitions for review are
Denied.
KAVANAUGH, Circuit Judge, concurring:
I join the Court‘s opinion. I note simply that the
To be sure, at least one case of ours has referred to the
