Lead Opinion
Appellant USCOC (U.S. Cellular) appeals from the district court’s sua sponte dismissal of U.S. Cellular’s complaint and denial of all outstanding motions. Because this matter was not moot at the time of the dismissal, we reverse the district court’s order and remand for further proceedings consistent with this decision.
I. BACKGROUND
U.S. Cellular desires to construct a cellular telephone tower in Franklin County, Missouri. To that end, U.S. Cellular filed an application for a conditional use permit (CUP) with the County in January 2007. On April 11, 2007, the Franklin County Planning and Zoning Commission (Commission) denied the application. U.S. Cellular appealed this decision and on July 11, 2007, the Franklin County Board of Zoning Adjustment (the BOZA) affirmed the Commission’s earlier denial of U.S. Cellular’s application.
U.S. Cellular filed this action in federal district court on August 10, 2007, challenging the BOZA’s July 11, 2007, decision, alleging claims arising under the Federal Telecommunications Act of 1996(TCA), as well as Missouri state law. In its complaint, U.S. Cellular prayed for three specific forms of relief in addition to certain monetary requests: 1) a declaration that Franklin County’s denial of the CUP violated TCA procedural and substantive requirements and the Franklin County Unified Land Regulation; 2) an injunction or writ compelling Franklin County to issue a CUP; and 3) an order reserving jurisdiction in the district court “to resolve any issues between the parties as to further site plan and building permit issues, to ensure the integrity of dealings between the parties” regarding the CUP application.
On August 20, 2008, the district court determined that the July 11, 2007, written decision did not satisfy TCA requirements because it did not contain any explanation of the reasons for the denial, i.e., it did not articulate the “substantial evidence” supporting the BOZA’s denial of the U.S.
Following the district court’s remand to the BOZA, the BOZA held rehearings and issued a new written decision on December 23, 2008. In that decision, instead of merely providing the requested written support for the initial denial of U.S. Cellular’s application, the BOZA granted U.S. Cellular’s CUP. U.S. Cellular notified the district court of the BOZA’s action by way of a status report filed on February 17, 2009. Also in that status report, U.S. Cellular notified the district court that Fritz Trust had filed suit in state court on January 21, 2009 (the Fritz Trust action), requesting that the December 23, 2008, BOZA approval be set aside.
The BOZA’s change of tune in its later grant of the CUP lends to the unique posture of this case. On April 3, 2009, the district court issued an order specifically requesting that the parties “file briefs addressing whether [U.S. Cellular’s] First Amended Complaint should be dismissed as moot.” In response, on May 8, 2009, U.S. Cellular filed a Motion for Judgment seeking an order from the district court requiring the County to issue the CUP along with any other required permits, and asking the court to otherwise dispose of all pending motions. U.S. Cellular further requested that the court grant Fritz Trust’s pending motion to consolidate, which would then allow the court to deny the then-pending motion to remand in the Fritz Trust action. U.S. Cellular explained that it moved for judgment because the pending Fritz Trust action prevented the County from issuing all permits necessary for the project to move forward. U.S. Cellular argued in its motion for judgment that “[n]ow, at the eleventh hour, Fritz seeks to undo the work of this Court, relitigate issues that have already been decided, and send this dispute back to square one.” On the issue of mootness, U.S. Cellular claimed that, because it was yet unable to begin construction, it had not yet been fully remedied and the case was thus not moot until work began.
On May 26, 2009, the district court held that because U.S. Cellular’s initial claims were directed at the July 11, 2007, denial of its CUP application — a decision superseded by the BOZA’s December 23, 2008, approval of the same application — the claims were directed at a decision no longer in force or effect. Accordingly, the district court dismissed the case as moot. On June 4, 2009, shortly after the district court’s dismissal in the instant action, the district court handling the Fritz Trust action, which was also in the Eastern District of Missouri but handled by a different judge, granted Fritz Trust’s motion to amend its complaint to remove all federal allegations and remanded the case back to state court. U.S. Cellular did not appeal
Currently before us is U.S. Cellular’s appeal from the district court’s sua sponte dismissal in the TCA action. Franklin County elected not to file a brief on appeal.
II. DISCUSSION
We review a district court’s dismissal for mootness de novo. Midwest Farmworker Emp’t and Training, Inc. v. U.S. Dep’t of Labor,
The TCA enactment in 1996 made substantial changes to the federal regulation of telecommunications as Congress sought “ ‘to accelerate rapidly private sector deployment of advanced telecommunications and information technologies and services to all Americans by opening all telecommunications markets to competition.’” New York SMSA Ltd. P’ship v. Town of Clarkstown,
In section 332(c)(7) of the TCA, Congress preserved the authority of state and local governments over zoning and land use issues, but imposed limitations on that authority. 47 U.S.C. § 332(c)(7). At the same time, however, section 332(c)(7)(B) provides that “[t]he regulation of the placement, construction, and modification of personal wireless service facilities by any State or local government or instrumentality thereof (I) shall not unreasonably discriminate among providers of functionally equivalent services; and (II) shall not prohibit or have the effect of prohibiting the provision of personal wireless services.” 47 U.S.C. § 332(c)(7)(B)®. To that end, “[a]ny person adversely affected by any final action or failure to act by a State or local government ... may ... commence an action.” Id. at 332(c)(7)(B)(v). Essentially, the TCA “strikes a balance between two competing aims — to facilitate nationally the growth of wireless telephone service and to maintain substantial local control over siting of towers.” Omnipoint Commc’ns, Inc. v. City of White Plains,
As plainly stated by U.S. Cellular, its TCA claims are not moot because U.S. Cellular still has not achieved the relief sought in its complaint — namely, its request that Franklin County remove the barriers standing in the way of erection of
The Third Circuit’s discussion in Ogden Fire Co. No. 1 v. Upper Chichester Township,
During the pendency of the summary judgment appeal, the local zoning board acted on the district court’s first directive and granted the special exceptions requested by Ogden and Sprint so the project could move forward. Id. at 377. But, the project was almost immediately halted at the next bureaucratic step when the township building inspector denied the needed building permit. Id. At that point, Ogden and Sprint filed a motion to compel the issuance of a building permit in the district court, which the district court granted — a filing similar to the motion for judgment filed by U.S. Cellular in this case that was pending before the district court at the time of dismissal. Id. To finally resolve the matter and avoid any further bureaucratic delays, the district court ordered the township to “issue all necessary approvals and permits for the building of [the telecommunications tower].” Id. The township appealed that order as well, arguing that the order impermissibly expanded the scope of the prior order, which had merely ordered the township to issue zoning permits for the tower. Id. at 395. The township claimed that the district court crossed the line and intruded into an area that was strictly a matter of local law and beyond the scope of the TCA. Id. The appeals were consolidated in the Third Circuit.
On appeal, the court noted how the TCA altered the traditional deference in very important ways insofar as local decisions interfere with, or impact upon, telecommunications facilities. Id. at 379. The court affirmed the district court’s order and supplemental remedy requiring the township to issue “all necessary approvals and permits,” thus confirming that the TCA encompasses all aspects of the wireless service facilities construction process when a party has been adversely affected by a local government’s final action or failure to act. Id. at 396. The court correctly noted that once the zoning board approved the application, if there was no assurance that approval could be had at every additional step in the administrative gauntlet that
The current situation in Franklin County highlights the very administrative quagmire that the TCA was enacted to avoid. Given the province of a federal court under the TCA to issue certain mandates when a party has been adversely affected by a local government’s failure to act, this matter was ripe for adjudication at the time of dismissal given the local authority’s failure to issue the necessary permits. Indeed, without power to mandate any and all permits contemplated by the federal claim, we would essentially perpetuate “an end run around the requirements of the TCA and thereby allow local regulatory agencies to subvert a federal policy by elevating zoning authority over congressional policy as enacted into law via the TCA.” Id. Fritz Trust argues that U.S. Cellular is unable to use the TCA as a vehicle to force the County to issue the needed building permit in this case. On this belief, Fritz Trust claims it has the green light to pursue its duplicative action in state court, in turn halting any forward motion toward the erection of the tower at issue until the state action is resolved. This erroneous argument sheds light on the very chicanery the TCA was put in place to halt. Disengaging the federal courts from such a suggested exercise frustrates the intent of the TCA.
Four years later, U.S. Cellular remains unable to erect the requested tower despite the BOZA’s approval of the CUP. The issuance of the requisite building permits is necessarily encompassed and specifically addressed in U.S. Cellular’s amended complaint and later motion for judgment, and arises under the TCA. The district court erred in finding U.S. Cellular’s claims moot. We therefore remand to the district court for further consideration of U.S. Cellular’s motion for judgment consistent with this opinion.
Finally, U.S. Cellular requests that the court enjoin any collateral attacks on the upcoming administrative and judicial proceedings, including the Fritz Trust pending state court claim. Under the All Writs Act federal courts have the inherent ability to protect our jurisdiction over pending disputes. 28 U.S.C. § 1651(a). Indeed, the All Writs Act authorizes federal courts to issue extraordinary writs to the extent that “the issuance of process [is] ‘in aid of the issuing court’s jurisdiction.” Clinton v. Goldsmith,
Given the procedural posture of this case we find it necessary that such a writ be issued so as to avoid any further unnecessary delays in the erection of the telecommunications tower, which delay we have held would only frustrate the congressional policies underpinning the TCA. Accordingly, although the district court’s actions should suffice in the instant case to complete the project at issue without incident, especially given the state court’s denial of a motion for new trial, we exercise the authority under the All Writs Act and direct the district court to enjoin any collateral attacks or any other such action that would frustrate the instant order.
III. CONCLUSION
For the reasons stated herein we reverse and remand this action to the district court for implementation of this judgment, including issuing all orders necessary to protect the jurisdiction of the federal courts.
Notes
. U.S. Cellular removed the Fritz Trust action to federal court in March 2009, case number 09-00372. Then, in April 2009, Fritz Trust moved to intervene as defendant in this action, case number 07-1426, and further moved to consolidate the two pending federal cases as well. However, these motions were denied as moot at the time the district court dismissed this action. On appeal, Fritz Trust again moved to intervene in this matter, which motion was granted.
. Our review of the state court docket sheet in the Fritz Trust action reveals that on December 31, 2009, the Franklin County Circuit Court held that the record contained substantial evidence to support the issuance of the CUP, but that the BOZA had not made certain required additional findings necessary to support the order. Accordingly, the court remanded the matter to the BOZA so that the BOZA could detail its findings in support of its grant of the CUP in accordance with the Unified Land Use Regulations of Franklin County (the “Zoning Code”). In April 2010, the county circuit court denied Fritz Trust’s motion for new trial in the Fritz Trust action. As the parties did not apprise this panel of any development in the state action, we presume the BOZA’s grant of the CUP remains intact and now complies with the Zoning Code.
Dissenting Opinion
dissenting.
I respectfully dissent. I would affirm the district court’s conclusion that U.S. Cellular’s original claim under the TCA is moot. The TCA ensures effective and hopefully efficient legal process in state and local zoning decisions affecting cellular tower placement. It does not guarantee approval. U.S. Cellular’s inability to erect its telecommunications tower in Franklin County after four years, while regrettable, is unrelated to its original claim that the BOZA violated the TCA’s procedural requirements when it originally denied U.S. Cellular’s application for a CUP.
The TCA allows federal courts to review the decisions of local authorities to ensure that those decisions comply with the TCA’s requirements. It does not create the trump card that U.S. Cellular seeks: namely, as the majority opinion describes it, to “remove the barriers standing in the way of erection of a telecommunications tower.” In enacting the TCA, “Congress did not give the courts authority to hear a zoning case anew or to take new evidence, but only to review the ‘written record’ for ‘substantial evidence’ supporting the decision of the local authority.” USCOC of Greater Iowa, Inc. v. Zoning Bd. of Adjustment of Des Moines,
Here, U.S. Cellular brought its original action in the district court to challenge the BOZA’s decision denying its CUP applica
The Third Circuit’s decision in Ogden does not change the analysis. In Ogden, the plaintiffs initially brought suit in the district court, alleging a violation of the TCA based on the local zoning board’s denial of a zoning permit.
These facts are distinguishable. Here, unlike Ogden, after the BOZA granted the CUP, Fritz Trust — not Franklin County— initiated legal action that halted U.S. Cellular’s tower construction. In addition, unlike Ogden, where the building inspector actually denied the building permit, it is impossible to discern from the record what steps, if any, U.S. Cellular has actually taken to get Franklin County to issue the CUP or the building permit and how Franklin County has responded.
Because there is no longer a BOZA decision that violates the TCA for this court to review, I would find that U.S. Cellular’s TCA claim is moot. Accordingly, I would affirm the district court.
. In a memorandum supporting its motion for judgment, U.S. Cellular merely asserted that “Franklin County refuses to issue the building permit because of, upon information and belief, [Intervenor] Fritz’s pending claims.” At oral argument, when asked whether U.S. Cellular had applied for a building permit, counsel responded, equivocally and somewhat cryptically:
We have asked that the building permit be issued. One of the concerns is that because of the ongoing litigation, any building permit is under the cloud of the ongoing challenges. So for those reasons, as a practical matter, it makes it difficult to build a tower without the security of knowing that the litigation is wound up.
U.S. Cellular has not identified which provisions of the TCA that Franklin County’s action (or inaction) would violate.
