UPROSE v. Power AuthorityUPROSE v. Power Authority
—In a proceeding pursuant to CPLR article 78, inter alia, to review
Ordered that the appeal from the judgment is dismissed, without costs or disbursements, as the judgment was superseded by the amended judgment; and it is further,
Ordered that the amended judgment is modified, on the law, by deleting the provision thereof denying those branches of the petition which were to annul the negative declaration issued by the Power Authority of the State of New York, and substituting therefor provisions (1) granting the petition to the extent of annulling the negative declaration issued by the Power Authority of State of New York, (2) directing the Power Authority of the State of New York to issue a positive declaration, (3) remitting the matter to the Power Authority of the State of New York to prepare a full Environmental Impact Statement, and (4) enjoining the Power Authority of the State of New York from further construction or operation of the subject generating facilities; as so modified, the amended judgment is affirmed insofar as appealed from, without costs or disbursements; and it is further,
Ordered that so much of the amended judgment as enjoined the Power Authority of the State of New York from further construction or operation of the subject generating facilities is stayed until January 31, 2002, to afford the Power Authority of the State of New York an opportunity to expeditiously comply with the requirements of the State Environmental Quality Review Act, without prejudice to an application in the Supreme Court, Kings County, for a further extension, if necessary; if no extension is requested or if an application for an extension is denied, upon application of the petitioners the Supreme Court, Kings County, shall vacate this stay.
Each of the turbines has a net generating capacity of 44 megawatts (hereinafter MW). Pursuant to Public Service Law § 160 (2), if a facility generates more than 80 MW it is characterized as a “major electric generating facility” subject to the requirements of Public Service Law article X.
After designating itself the lead agency pursuant to the State Environmental Quality Review Act (hereinafter SEQRA) (see, ECL art 8), NYPA, among other things, sought a ruling from the New York State Board on Electric Generation Siting and the Environment (hereinafter the Siting Board) that because NYPA would ensure that any two generator units on a common site would produce less than 80 MW of electricity, the site would not constitute a “major electric generating facility” thereby exempting it from the requirements of Public Service Law article X. After receiving public comments on the issue, the Siting Board ruled that if NYPA “makes a legally binding commitment * * * that the units will not be operated at a total net generating capacity of 80 MW or more * * * the generating facility so constructed and so operated will not be a major electric generating facility subject to * * * article X of the Public Service Law.”
Subsequently, NYPA prepared an Environmental Assessment Form (hereinafter EAF) for the Project. The EAF covered six of the seven facilities. A supplemental EAF was prepared for the Staten Island facility and is not at issue here. The EAF concluded that the Project would not have any potential significant environmental impacts, and NYPA, as lead agency, issued a negative declaration for the Project (see, 6 NYCRR 617.7).
The petitioners commenced this proceeding pursuant to
The Supreme Court properly concluded that the Siting Board did not act outside the scope of its legitimate power in interpreting Public Service Law § 160 (2). In reviewing a determination of a regulatory commission courts must “[engage] in ‘a realistic appraisal of the particular situation to determine whether the administrative action reasonably promotes or transgresses the pronounced legislative judgment’ ” (Matter of Niagara Mohawk Power Corp. v Public Serv. Commn.,
However, we find that the analysis by NYPA on the environmental impact of particulate matter was inadequate, and therefore, the Supreme Court erred in failing to annul the negative declaration. Pursuant to Clean Air Act § 108 (42 USC § 7408), “air quality criteria” for air pollutants are to be issued from time to time (see, Clean Air Act § 108 [a] [1]; 42 USC § 7408 [a] [1]). Once “air quality criteria” for a particular pollutant are issued, the Administrator of the United States Environmental Protection Agency (hereinafter the Administrator) is required to promulgate national primary ambient air
Particulate matter is the “ ‘generic term for a broad class of chemically and physically diverse substances that exist as discrete particles (liquid droplets or solids) over a wide range of sizes’ ” (Interim Decision, Commissioner, NYS Dept of Envtl Conservation, Matter of American Mar. Rail [Feb. 14, 2001], quoting Wooley, Clean Air Handbook, at 1-14, n 15 [9th ed]). Prior to 1997, standards for particulate matter were maintained for particulate matter of 10 microns in diameter (hereinafter PM 10). In 1997, the Administrator revised the NAAQS for particulate matter and added a new standard for PM 2.5 emissions (see, 40 CFR 50.7). Although the revised NAAQS were the subject of a legal challenge (see, American Trucking Assn. v United States Envtl. Protection Agency,
Particulate matter is a nonthreshold pollutant, which means that there is some possibility of an adverse health impact from particulate matter at any concentration (see, American Trucking v EPA: Unjustified Revival of the Nondelegation Doctrine, 23-SPG Environs Envtl L & Policy J 17, 26). The health effects associated with PM 2.5 emissions include: premature mortality and increased hospital admissions and emergency room visits, primarily in the elderly and individuals with cardiopulmonary disease; increased respiratory symptoms and disease in children and individuals with cardiopulmonary disease such as asthma; decreased lung function, particularly in children and individuals with asthma; and alterations in lung tissue structure and in respiratory tract defense mechanisms (see, 62 Fed Reg 38652).
Judicial review of the SEQRA process is limited to whether the determination of the lead agency was made in violation of lawful procedure, was affected by error of law, or was arbitrary and capricious or an abuse of discretion (see, Akpan v Koch,
SEQRA mandates the preparation of an EIS when the proposed project may include the potential for at least one significant environmental effect (see, Matter of Omni Partners v County of Nassau,
In light of the undisputed potential adverse health effects that can result from PM 2.5 emissions, we conclude that NYPA failed to take the requisite “hard look” at this area of environmental concern. An EIS is required if the proposed project “may include the potential for at least one significant adverse environmental impact” (6 NYCRR 617.7 [a] [1] [emphasis supplied]). The analysis undertaken by NYPA, in which it assumed that all PM 10 emissions are PM 2.5 emissions is not sufficiently detailed in the EAF and is not an adequate substitute for addressing the health impacts of PM 2.5 emissions. Thus, NYPA should have issued a positive declaration and prepared an EIS (see, Matter of Syrop v City Council,