History
  • No items yet
midpage
University System of Maryland v. Mooney
966 A.2d 418
Md.
2009
Check Treatment

*1 966A.2d 418 MARYLAND UNIVERSITY SYSTEM OF Mоoney. Kevin MOONEY and Teresa Term, Sept. No. 2008. Appeals Maryland.

Court 20, 2009.

Feb. *3 F. (Douglas Wherthey, Atty. E. Asst. General Kathleen General, Swann, Asst. Gansler, Sally Atty. Gener- Atty. L. al, Baltimore), brief, on for Petitioner. N. (Jeremy Friedberg and Steven Young S. S.

Gordon Fedder, PC, Leitess, Leitess, Leitess, Owings Friedberg brief, Mills), for Respondents. HARRELL, BATTAGLIA, BELL, C.J., Before:

Argued (Retired, MURPHY, GREENE, C. ELDRIDGE JOHN (Retired, Specially RAKER Assigned), IRMA S. Specially JJ. Assigned,)

BATTAGLIA, Judge. attempt by out Kevin and

The case before us arises Prince Mooney institute suit in the Circuit Court for Teresa County University System Maryland, George’s against assignment rights in a contract upon Mooneys’ based Cable, into Chesapeake entered between the LLC, money. to which had shall hold loaned We Mooneys’ must be of their suit dismissed because failure to exhaust the available administrative remedies.1

I. Introduction Mooney agreed In October Kevin and Teresa Cable, Chesapeake (“Chesapeаke”), LLC the sum lend *4 University’s following ques- presented for the 1. The Petition Certiorari tions, which we have renumbered: respondents may pursue against the 1. If a contract-based claim State, presented administratively agency must it be for review the Maryland required by Appeals, as Title 15 and the Board of Contract the State of Finance & Procurement Article? sovereign immunity respondents’ claim 2. Does the of bar doctrine assignee rights against of as contractual the State? question disposition of We shall not second because of our address the the first. $250,0002 in exchange promissory *5 $43,005.00 for services rendered cable for an account debtor the make to payment was to Chesapeake,6 University the by let- receiving that University although disputes the Mooneys, ter.7 a to 22, 2003, University check Chesa- the issued April

On 2003, Thereaftеr, on $43,005.00. June peake Cable for Payable” at in “Accounts employee emailed an Mooney Kevin check Chesapeake to requesting copy a University, the whom, by it cashed and of how was description as well a into bank Chesapeake’s not deposited “the cheek was because accounting pur- no record company and the has account Mooney July check was faxed to poses”; copy the 2003. against the complaint filed a Mooneys the

On June George’s County, for Prince University in the Court Circuit 9-406(a) of the University the violated Section alleging that (1975, Article, Repl. Maryland Code Law Commercial Vol.),8 Chesapeake Cable “by making payable the Check the Check to Cable instead only by mailing Chesapeake the amount Mooneys.” Damages sought the were Chеsapeake University specifically, to the 6. More an invoice sent from “Doppler Con- the billed for Radar Fiber reflects that was struction.” dispute involving of notice does not affect our conclu- 7. The the issue regarding Mooneys’ remedies. the to exhaust administrative sion failure 9-406(a) Maryland Code the Law 8. Section Commercial (1975, Repl.Vol.), states: (b) through Subject (j), an account debtor on to subsections account, may intangible discharge its paper, payment or chattel after, until, obligation by paying assignor the account but not notification, by assignor debtor receives a authenticated assigned assignee, been or to become due has that the amount due assignee. receipt of payment After is to made notification, by may discharge obligation debtor its the account obligаtion paying assignee discharge paying assignor. are to the Statutory Law Article herein references Commercial (1975, Repl.Vol.), noted. unless otherwise Code $43,005.00 attorneys’ fees, interest, reasonable “plus costs of action, expenses this and other incurred enforcing rights their under the Loan Documents.”

The University filed a Motion to Dismiss and Memorandum in Support, arguing Mooneys’ barred, that the complaint was the sovereign only because State “has waived as immunity to 12-201(a) written contracts” under Section of the State Gov- Article, (1984, ernment Maryland Code Repl.Vol.),9 Mooneys the not did have a written contract with the University. University also asserted that if sovereign waived, immunity had been the Mooneys also failed to file a claim with the appropriate year authorities within the one 12-106(b) provided by limitations period Sеctions 12-202 or of Article,10 the State which govern Government contract and actions, respectfully. tort In the to Motion Dismiss and in Support, University Memorandum the proffered also it Article, Maryland 9. Section 12-201 of State the Government Code (1984, Repl.Vol.), states: (a) general.—Except expressly provided by In as a otherwise law of State, State, officers, may the the its and its units not raise the action, sovereign immunity defense a contract in a court of State, the employee based on a written contract that an official or employee the or 1 executed for State of its units while the official or acting scope authority was within the the of the official or employee. Statutory throughout references to the State Government Article are (1984, Maryland Repl.Vol.), Code unless noted. otherwisе Article, 10. Section 12-202 of the State Government sets forth the time against frame within which a contract claim State the must be filed: A claim under this subtitle is barred unless the claimant files suit year within 1 after the later of: (1) arose; the date which the claim or (2) gives completion of the contract that rise to the claim. 12-106(b) turn, provides Section of the State Government against time frame which a tort claim the State filed: must be (b) required.—A Claim and denial claimant institute action under this subtitle unless: (1) the a claimant submits written claim to the or a Treasurer i designee year injury person of the Treasurer within 1 after the to or claim; property is the basis (2) designee finally; Treasurer denies the claim (3) years the action is filed after within the cause of action arises. defined in nor “person,” an “account debtor” was neither 9-102(a)(3) Article. the Commercial Law Section Dismiss, to Motion In to Defendant’s Opposition their was not barred complaint their argued that University sovereign waived because the immunity, sovereign Chesapeake, the contract when it entered into immunity Compli- was their assigned, nor properly which was thereafter contracts, because period limitations ant barred termination year they filed suit within one The Moo- Chesapeake University. and the contract between timely received although the neys argued that also by making notice, disregarded assignment” “willfully it Com- Maryland that the Uniform Chesapeake payment “per- University, which was apply did mercial Code Commercial 9 of the Uniform son” under Title *7 Code. was denied the Motion to Dismiss University’s

The in court, the that “the issues raised circuit which ordered re-raised in a Motion Motion to Dismiss be Defendant’s can for wherein more factual issues Summary Judgment thereafter, in Soon October of discussed and considered.” Mooney’s the com- filed Answer to University the an Mooneys’ April it the in which it admitted that received plaint, letter, that the asserted as affirmative defenses but sovereign immunity and the claims were barred Mooneys’ statute of limitations. applicable summary filed motions for subsequently cross parties

Both in to the made the Motion judgment echoing arguments thereto; summary both motions for Opposition Dismiss and 7, 2005, University the September were On judgment denied. Leave Amend Answer and an Amended filed a Motion for to letter; 14, 2003, the at

Answer, April it received denying that day, granted court the judge a that the circuit hearing motions request in to oral limine strike defendant’s Mooneys’ motion court neverthe- judge, for to amend answer. The circuit leave less, Dismiss,11 the granted University’s to concluding Motion no because there was written contract between the Moo- neys the University, the claim was in claim essence tort to requiring Mooneys go through the the procedures set forth in the Maryland Tort Act.12 Claims Mooneys

The appealed to the Court Special Appeals, arguing that the erred in judge determining that suit their was an action They argued tort. also were they University entitled to sue the based the contract between Chesapeake and The University. University, conversely, argued the Mooneys’ claim was barred failure to and, comply with Tort Act alternatively, Claims that the could not maintain a against contract action University the University because no had contract In Mooneys. unreported opinion, the intermediate that, appellate court concluded because suit was not an tort, action but “a brought instead suit under Maryland’s Mooneys’ alleged security UCC enforce the interest Chesapeake monies due under its contract with [the Universi- court, ty],” the judgment of the circuit based on the theory tort, that the suit was an action in could not stand. remand,

On University filed “Motion Dismiss or in for Summary Judgment Alternative In Response to the Ruling Special Appeals,” of Court of and Mooneys filed a Summary ‍‌‌‌‌‌‌‌​​​​​‌‌​​​​‌‌​​‌‌​​‌​‌‌‌‌‌​‌​‌‌‌‌‌‌‌‌​‌​​‍“Renewed Motion for Judgment.” that, argued because the “General Assembly Maryland has units[13] immunity not waived the sovereign State and its *8 Special Appeals recognized ruling, 11. The of Court later that "the dismissal, though grant summary couched as a [was] fact a of judgment.” Maryland The through Tort Claims Act is codified in Section 12-101 12. 12-110 of the State Government Article. entity 13. A "unit” is defined as "an officer or other that is the government Executive Branch of the State and is authorized law to enter into a contract.” Section State 11-101 of the Article, (1988, Maryland Repl. Finance and Procurement Code 2001

399 1 Article],” the Mooneys Law [Commercial 9 the under Title of Article, while the University under that not sue the could University violated Section 9- that the Mooneys reasserted 406(a) it the check Law Article when sent the Commercial assigned properly had been though they even Chesapeake, After another hear rights. receivable accounts Chesapeake’s motions, Univer judge granted court the the circuit ing the Dismiss, express that “there is no concluding sity’s Motion to Immunity Title 9 of the Sovereign [Commer under waiver of cial Law Article].” of Special Ap again appealed Court Mooneys

The the which, appropriate reported opinion, in a stated pеals, University waived sovereign had was not whether question but whether under the Commercial Law immunity default, was in debtor Mooneys, parties as secured whose Uni rights against the debtor’s contractual could enforce the University sovereign had waived and whether versity, rights. contractual respect to the debtor’s immunity 637, University Maryland, Md.App. Mooney System (2008). appellate The intermediate A.2d University waived sovereign that the had court then concluded Chesapeake’s enforce Mooneys and that the could immunity noted that the waiver of rights. opinion contractual also only year one under Section immunity existed sovereign Article and further that the Government 12-202 of State year of the to file the within one Mooneys “needed suit A.2d 113. In Id. contract.” at at termination terminated, as the contract was well order to determine whеn University notice to the gave proper whether judgment assignment, the court vacated Id. at proceedings. and remanded for further circuit court 113. 943 A.2d at VoL). System present case the State unit is the In Maryland. Statutory Article to the State Finance and Procurement references Code, (1988, Repl.Vol.). are to the herein

400 University certiorari, petitioned

The which granted, we University Systems v. 290, Mooney, 405 Md. 950 A.2d 828 (2008). We shall judgment reverse Court of Special Appeals Mooneys, assignees hold that the of accounts due under University, receivable a contract with the were required to exhaust the available administrative remedies relief, seeking judicial so, before they and because failed to do they pursue cannot action. present

II. Discussion The if asserts that even claim, they could pursue a were first to required exhaust their by submitting administrative remedies a contract claim to the procurement officer and the denial protesting Maryland Board”) State Board Appeals of Contract (“Appeals before judicial review, seeking they failed to do. The Moo neys, conversely, argue that we should not consider issue they required whether were first to exhaust their adminis trative remedies because the issue was raised for the first time in the Petition for Certiorari. The Mooneys allege also they are not a or person “contractor” “a who has been awarded a contract” under the State Finance and Procurement so that they required are not to proceed administratively before pursuing remedies.

With to the fact that respect exhaustion of administra tive remedies seminally us, was raised before ordinarily we will not consider an in this issue Court it plainly “unless appears by the record to have been raised in or decided by the 8-131(a)14; trial see also Maryland court.” Rule Robinson State, 456, 404 Burch v. (2008); Md. 946 A.2d 8-131(a) provides: Rule 14. jurisdiction subject The issues of of the trial court over the matter and, 2-322, person unless Rule may waived under over a raised by appellate and decided court whether not raised in and by Ordinarily, appellate decided the trial court. court will not any plainly appears decide other issue it unless the record to have court,

been raised in or decided the trial but the Court decide necessary guide such issue if or desirable to trial court or expense delay appeal. avoid the of another Cable, (2006); 687, 695, Md. 895 A.2d United State, 484, 505, 384 Md. 864 A.2d Fitzgerald v.

(2004). require Rule is “to counsel purpose *10 of lower to the attention of their client bring position and pass upon, court can the trial court at the trial so “to pre in proceedings” errors any correct possibly fashion, accelerating in thus piecemeal of cases a vent the trial Robinson, 216-17, 404 Md. at litigation.” of the termination 1018; 505, at Fitzgerald, 461; 384 at 864 A.2d at Md. 946 A.2d 1070, 1075 499, 509, 639 A.2d v. County Offen, Council 334 Md. (1994). that has usually will not consider an issue

Although we issues, of below, category there is “a limited not been raised ordinarily will jurisdiction, which an court appellate addition to Moats they by were raised a party.” even though address 972, 519, 525, 324 597 A.2d 975 City Hagerstown, v. Md. of (1991). administrative issues is the exhaustion of One of these remedies, the first time will when raised for we address South, See Furnitureland us, or our own before on initiative. State, 126,132, Treasury 771 Inc. Comptroller 364 Md. v. v. Broadcast (2001); Montgomery County 1061, A.2d 1065 Inc., 7, 452, 995, 758 438, 450-451 & A.2d Equities, 360 Md. n. Associates, (2000); Reclamation 7,n. 1003 1002 & 476, 10, 567, County, Inc. n. 677 A.2d v. Harford 342 Md. (1996). 574 n. 10 we will address ex

The determination whether remedies, for the when raised first haustion of administrative initiative, part depen time in this Court or on our own is the adminis statutory scheme in which dent on whether exclusive, primary is is deemed to be remedy trative included Co., Zappone Liberty v. Ins. or concurrent. See 349 Md. Life (1998). 1060, 45, 60-61, We have articulated 706 A.2d 1067-68 remedy primary, administrative is deemed where the in Board sponte; raised this Court sua issue can be Hubbard, 774, County Dorchester v. 305 Md. Education 625, (1986), 786-87, 506 A.2d we stated: Where ... the administrative is remedy deemed to primary, this Court has it generally held that must be pursued jurisdiction before a court exhausted exercises to decide controversy. Wash. Sub. San. Comm’n Mitchell & Best, supra, 303 Md. [544] at 553-554, 495 A.2d (1985)]; Co., [30 Md. Comm’n on Human Rel. v. B.G. & E. 46, 50, 205, (1983); 296 Md. 459 A.2d Md. Comm’n Steel, Human Rel. v. Beth. 295 Md. 457 A.2d (1983), Sec., there explained cases cited. As Dep’t Human Res. v. Wilson, supra, 286 Md. [639] at [1979], 409 A.2d 713 Legislature

“when the enacts comprehensive remedial scheme in which claim is to be determined agency administrativе and reviewed in an administrative available, appeal establishes, before review it *11 public policy, that a procedure produces such the most efficient and effective In results. order to effectuate this public ‍‌‌‌‌‌‌‌​​​​​‌‌​​​​‌‌​​‌‌​​‌​‌‌‌‌‌​‌​‌‌‌‌‌‌‌‌​‌​​‍trial policy, generally courts not should act until there has been compliance statutory comprehen- sive remedial scheme.”

While the failure to invoke and exhaust an administrative remedy not ordinarily does result in being a trial court’s nevertheless, of deprived jurisdiction, fundamental because of public involved, policy the matter is for pur- some poses jurisdictional question. treated like a Consequently, of primary jurisdiction issues and exhaustion of administra- tive will by remedies be sponte addressed this Court sua even though not any party. raised in (Emphasis original).15 The of primary, nоtion this con- text, is juxtaposed against concepts of “exclusive” adminis- State, 15. The reliance on Jones v. 379 Md. 778 A.2d Jones, (2004), misplaced. is In did we not consider the failure to remedies, rather, exhaust administrative but whether of Court Special Appeals properly exercised its discretion when it remanded consideration, post-conviction complaint to circuit court for of rule, exception coconspirator hearsay though was even that issue appeal. safeguard promulgated raised for the first time Jones, 714—15, 784, providing appellate 379 Md. at 843 A.2d at for remedies, remedy which the is administra under sole trative remedies, by which administrative tive, and concurrent to having remedies without first may pursue claimant Mary Atlantic See Bell remedies. exhaust administrative land, 1, 11-12, Systems Corp., Intercom Md. Inc. v. (2001). cases, in recent In one our more A.2d of adminis explore the exhaustion which we had occasion Maryland, Inc. v. Intercom Bell Atlantic remedies, trative (2001), 1, 11, we were Sys. Corp., 366 Md. 782 A.2d 796-97 Inter provider, internet service whether an asked decide rela com, interference with contractual alleged tortious its telecommu tions, against breach contract negligence and Atlantic, in the filed suit provider, appropriately Bell nications there George’s Prince Because County. for Circuit Court many available to address were administrative remedies claims, determining whether we were tasked with Intercom’s exclusive, In our primary concurrent. were those remedies Zappone on the extensively language relied analysis, we Liberty Company, Insurance Judge in which John C. Life Court, writing succinctly for this articulated Eldridge, exclusive, and concurrent admin primary between distinction istrative remedies: exclusive,

First, thus remedy may be the administrative remedy. Under this any resort to an alternative precluding scenario, no cause of action simply there alternative remedy. administrative statutory covered matters Second, remedy primary but the administrative situation, In invoke and this a claimant must exclusive. *12 judicial review remedy, exhaust the administrative and seek decision, can before a court of an adverse administrative judicial adjudicate the merits of the alternative properly remedy. prejudice a criminal consideration of an issue would not

review when would, instead, justice, promote is the administration defendant and inapplicable present the in case. Bell, State, 571, (2002) Conyers 15 State v. Md. 790 A.2d 367 178, (1994), Mooneys, by the are Md. 638 A.2d 107 also сited 334 inapposite well. * * * Third, the remedy judi- administrative the alternative concurrent, remedy cial bemay fully remedy with neither being primary, plaintiff at his or her option may pursue judicial remedy necessity without the of invoking and exhausting the administrative remedy. Atlantic, 11-12,

Bell 366 Md. at 782 A.2d at quoting (1998) (em- 60-61, at Zappone, Md. 706 A.2d at 1067-68 phasis original). in then We went to summarize the Zappone analysis, which provides general framework for determining exclusive, remedy whether administrative is primary, or concurrent:

We emphasized statutory “where neither the language legislative nor the history disclose an intent that the admin- exclusive, remedy istrative to be and where there is an judicial remedy alternative under another statute or under equitable common law or principles, presumption there is no that the remedy administrative was exclu- intended be sive.” Zaрpone, Instead, 349 Md. at 706 A.2d at 1069. we found rebuttable presumption that in the absence specific statutory indicating otherwise, language an adminis- trative remedy was intended to primary. be See id. at 63- evaluating 706 A.2d at 1069. In this we presumption, factors, are encouraged to including consider numerous “comprehensiveness of the remedy,” administrative agency’s view scope jurisdiction, of its and the “nature of the alternative cause of action pursued by plaintiff’ refuting presumption legisla- that the ture intended the administrative remedy primary. 64-65, See id. at A.2d at 1070. Atlantic,

Bell at at Md. A.2d 797. We applied Zappone analysis then statutory Atlantic, 3-102(a) scheme at issue Bell Section (1998), Public Utilities Code stated that “[a]ny person may complaint file a Commission.” We concluded that the was statutory scheme to be intended remedy the exclusive with complaints against consumers *13 “ex- the scheme was not because companies, services public of exhaustion administrative language requiring in its plicit Atlantic, 25-26, at 782 A.2d at 805- Bell 366 Md. remedies.” nonetheless, the Public because recognized, then 06. We exclusive, it was not intended to be Article was Utilities although “other further noted primary. We presumably compensatory puni- in and sounding tort cognizable claims Bell of contracts with out the service damages arising tive Service Commis- [Public cannot be resolved Atlantic the consumer could sion],” primary, the action was because file an and thereafter file a with the Commission first claim action, stayed until which would independent 27-28, Id. at were resolved. proceedings administrative at 806-07. A.2d in analysis statutory of our of the framework

At the outset general- case, University System we note that the present II of the State Finance ly governed by not Division is ll-203(e) Article Article because Section Procurement provides, part: pertinent

(e) University System Maryland.—(l)(i) In this subsec- following meanings words have the indicated. tion (ii) Regents of the Regents” “Board of means board Maryland. System of University

(iii) System Mary- “University” ‍‌‌‌‌‌‌‌​​​​​‌‌​​​​‌‌​​‌‌​​‌​‌‌‌‌‌​‌​‌‌‌‌‌‌‌‌​‌​​‍University means the land.

(2) subsection, in this this provided as otherwise Except University System II does apply Division Maryland.

(3)(i) comply A shall with the procurement by University procedures developed by University policies and the Board of Public Works and the Administra- approved by Executive, tive, Legislative Review Committee of § 12-112 of Edu- Assembly accordance General cation Article. added). Article, 12-112 of the Education

(Emphasis Section (1978, complementary: RepLVol.), Code (a)(1) ll-203(e) provided § Except Fi- State nancе and Procurement is exempt *14 from Division II of the State Finance and Procurement Article.

(2)(i) Subject to review and approval by the Board of Public Administrative, Executive, Works and the and Legislative Review Committee of the General the Board of Assembly, Regents shall develop policies procedures and governing procurements by the University.

(ii) policies The procedures developed under subpara- graph

(i) this paragraph promote of purposes shall procurement § State law set forth as 11-201 the State Finance and Procurement Article. result,

As a the Board of Regents, powers under delegated to it by Legislature, has developed Procurement Policies and Procedures the University System, for X Section of which governs protests in connection with the solicitation and award of contracts as well as contract provides claims and that “[a]n aggrieved party shall all exhaust administrative pro- remedies vided in this section before seeking judicial review.” Universi- ty of Maryland Policies Manual, and Procedures Section VIII-' 3.00, X, Subsection at http://www.president.umd.edu/ available policies/. The Procurement Policies and in- Procedures also clude an extensive protests scheme governing involving the contracts, award of but subject the University to the dispute procedures resolution in the State Finance and Procurement Article when contract claims are involved:

All claims shall be handled accordance with Title Subtitle of the State Article, Finance and Procurement Annotated of Maryland Code of Maryland Code Regula- tions, Title Subtitle 10—Administrative and Civil Reme- dies, 04, 05, Chapters as be may аmended from time to time. X(c). claim,

Id. at A contract defined Section 15-215 Article, State Finance and Procurement “includes a claim breach, modification, or termination performance, about the procurement contract.” and Procure- in the Finance framework State statutory The 15-217, “a Article, which provides includes Section ment contract procurement awarded a person who has been 15-220, officer,” Section a claim to the submit the final action “may appeal a contractor provides Board,” 15-223, which Appeals and Section unit “a of the Appeals review of final decision provides Board, turn, jurisdiction Appeals Board.” 15-211 of Finance and Procure- the State governed Section that, shall Appeals which states Board “[t]he ment from appeals аrising have to hear and decide all jurisdiction the final action of a unit.” *15 statutory the factors to the scheme

Application Zappone of Legislature of has indicated entails consideration whether “the that remedy that the administrative is exclusive.” We note jurisdiction appeals have over “all the Board does Appeals the Although from final of a unit....”16 arising the action “all,” is whole meaning of the word which defined “the plain of,” amount, Colle- quantity, or extent see Merriam-Webster’s (11th ed.2003), an intent on the giate Dictionary suggests the the of part Legislature jurisdiction of the to consider exclusive, in is no such indication Appeals Board as there 15-217(a)(2) of State Finance and Procurement Section Article, states, in that has pertinent part, “person which a who contract a contract procurement been awarded a submit 15-220, оfficer,” nor claim to the Section of a “may the final action provides appeal that a contractor we statutory provisions unit Like the Appeals to Board.” Atlantic, A.2d one in at at analyzed Md. Bell with “[a]ny person may complaint that file a which stated 3-102(a)(l) Commission,” see Section the Public Utilities Article, (1998), in 15- Sections language Code Article, 15-211(a)(2) State Procurement 16. Section Finance and note, jurisdiction Appeals except "a we does from the Board relating property.” of real contract claim a lease 217 and 15-220 of the State Finance and Procurement Article explicitly require does initial exhaustion administrative remedies to the of judicial exclusion the invocation reme- dies.

In the exclusivity, recognized absence of we have that there “a in presumptiоn specif- arises rebuttable the absence of otherwise, statutory language indicating ic an administrative Atlantic, Bell remedy was intended be primary,” 366 Md. at at presumption A.2d and this is not rebutted present statutory case. The scheme resolution of disputes occupies an entire subtitle Finance State is, indeed, Procurement Article and comprehensive, encom- passing the cause of action Mooneys’ sounding breach of Additionally, contract. the agency certainly jurisdic- views its primary, posited tion as “the having Appeals Board shall jurisdiction arising have to hear and decide all under disputes a contract with any agency, State as a result of a breach of a contract any agency....”17 State COMAR 21.02.02.02.

In deciding statutory that the scheme under consideration is primary, reject concurrеnt; we it obviously could be we statute, do so specifically because under the more Section 15- 211 of the State Finance and Procurement agency given authority is to entertain “all from appeals arising breach, final action of unit” on claim for the performance, termination or recognition modification of a contract. This statutory that the scheme a primary embodies administrative remedy our decision in SEFAC &Lift undergirded by *16 Admin., v. Mass Transit Equip. Corp. 374, 367 Md. 788 A.2d (2002), 192 in which we had occasion to consider the same statutory in issue framework and deemed it “either primary or SEFAC, Wilner, exclusive.” In Alan Judge writing M. then Court, this remarked: (§§ 15, 15-223) Title 2 through subtitle 15-201 of the State Finance and Procurement of the Maryland Article Code sets except jurisdiction Appeals 17. COMAR 21.02.02.02 does from the of the disputes relating Board labor claim[s] and "contract to a lease of real property.”

409 resolution of framework for the comprehensive forth a agencies between State disputes contract procurement framework is statutory The heart their contractors. § 15-205. an Board], excep- With created Appeals [the jurisdic- here, agency § 15-211 gives tion not relevant from the final arising “all appeals” to hear and decide tion concerning claim” “a contract agency action of a State modification, or of a breach, termination performance, contract. procurement confirmed, held, recently long and have

We have has or exclusive agency primary administrative “[w]here the controver controversy, parties over a jurisdiction await a final administrative decision sy ordinarily must courts for resolution оf contro resorting before Appeals, v. Board Contract 364 versy.” State State Md. (2001); Board License Comm. 446, 504, 457, A.2d 510 773 Wine, Inc., 418, 916, v. 761 A.2d Corridor Md. Admin., (2000). Aviation Driggs Corp. In (1998), 406-08, 442-43 we held that 704 A.2d Md. juris or has either exclusive primary Appeals [the Board] disputes encompassed by contract procurement diction over that, result, “any § 15-211 resolution as matter, Appeals Board] decision would [the before final Appeals, v. State Board Contract State premature.” 510-11; Driggs, supra, supra, Md. at 773 A.2d at 407-08, A.2d at 443. 348 Md. at Id. at 379-80, 195-96. 788 A.2d at nevertheless, ‍‌‌‌‌‌‌‌​​​​​‌‌​​​​‌‌​​‌‌​​‌​‌‌‌‌‌​‌​‌‌‌‌‌‌‌‌​‌​​‍that even were argue, exhaust its administrative remedies

Chesapeake required to relief, assignees, were not so seeking judicial they, before person who has been they “[a] were not required, because nor a “contractor” under awarded a contract” Finance and Procure 15-217 and 15-220 of the State Sections respectively, provided: ment protest contract 15-217. Section Submission claim.

(a)(1) general.—A offeror, In prospective bidder a or bid- der, may protest procurement or offeror submit a to the officer.

(2) A person who has been a procurement awarded contract may submit a contract claim to the procurement officer. (b) Time submission.—Except § in provided 15-219 for subtitle, of this a protest or contract claim shall submit required ted within time under regulations adopted by primary procurement responsible unit procuremen for the t.[18] Appeal

Section 15-220. gener- from unit’s decision—In al.

(a) Appeals action.—Except for a contract claim of final related to a for real offeror, lease a or property, bidder a offeror, unit, prospective bidder a or a contractor may appeаl final action of a unit to the Appeals Board. (b) Time under filing.—An appeal this section shall be for filed:

(1) a protest, for within 10 days after receipt of notice of action; a final

(2) claim, days contract within receipt after of the notice of a final action.

To assignee determine whether an comes within the meaning “person” Section 15-217 of the State Finance Article, normal, Procurement we look first plain statute, meaning language reading statute as word, clause, whole ensure that “no phrase sentence or surplusage, superfluous, rendered meaningless or nugatory.” Pope, (2007) Barbre v. 402 Md. 935 A.2d (internal omitted). quotations A “person” Section 15-217 of 15-217(a)(2) by Chapter 18. Section was amended 373 of Laws of to state: person procurement A unit or a who has been awarded a contract submit а contract claim to the officer. is defined Procurement Finance and the State *18 individual, receiver, as “an the same Article 11-101 of Section or fiduciary, repre- trustee, personal representative, guardian, firm, association, any partnership, kind and any sentative of “re- language the entity.” Clearly, or other corporation, fiduciary, or trustee, representative, ceiver, personal guardian, the only person include kind” does not any representative contract, parties repre- third but procurement awarded “receiver,” A contracting party. interests of the senting the furthermore, person appointed a “disinterested is defined as for the court, person, or other aby corporation or by a subject that is property collection of or protectiоn ed.2004). (8th claims,” Dictionary 1296 Black’s Law diverse of the same then, serves some third-party a who Obviously, another, receiver, due by collecting property functions of a statutory definition. by accommodated must also be are concomi- assignee of an rights that the recognized We 520, 256 Md. Goldberg, v. assignor of an James tant to those (1970), 753, wherein we stated: 527, 261 A.2d to transfer to operates assignment generally unqualified An of the title and interest right, all of the assignee and does not subject assignment in the of the assignor right than the greater right assignee any confer upon assignor. possessed Inc., 356 Md. Hyatt Agency, Ins. recently,

More Jones (1999), we 1106 n. 8 also n. 741 A.2d to the same limitations assignees are “bound recognized conclusion, furthermore, that a assignor.” as their Our period contract” has been awarded “person who rights, contractuаl is assignees includes the “contractor” 9-404(a) Law of the Commercial by Section buttressed assignee subject are to”: rights “the of an provides (1) between the account debtor agreement All terms recoupment or claim in aris- any and defense assignor contract; rise to the gave from the transaction ing (2) against or claim of the account debtor Any other defense debtor re- before the account assignor which accrues assignment

ceives notification of the authenticated assignor or the assignee. added).

(Emphasis If assignee subject to all agreement terms of the debtor, between the assignor the account including the complying burden of with the same period limitations as the assignor, they surely subject also must be any condition precedent to the invocation of remedies tо which the assignor subject. would be Exhaustion of administrative rem edies, case, in the present is such a condition precedent, and without satisfying such a condition “the action fatally itself is Montgomery Rios v. flawed.” County, 386 Md. 104, 127, (2005). A.2d To hold otherwise provide would Mooneys with greater rights than Chesapeake, which we will *19 not do. Mooneys, nevertheless,

The University also point to Maryland Architects, Inc., v. MFE Incorporated NCP / 86, (1997), Md. A.2d 676 to support their assertion that only primary contractor is required comply to with the remedy administrative governing procurement contract dis- putes. contrary, case, To the only we held State did not have the opportunity to utilize the administrative remedies under Section 15-217 of the State Finance and Procurement Article by appealing a unit decision against Board of Appeals. We noted that “the omission to authorize a Stаte unit is significant,” id. at 345 Md. at contract claims 93, 679, 691 A.2d at and since that Legislature time the has 15-217(a)(2) responded by amending Section of the State Finance and Procurement Article to allow a State unit to submit a contract claim to the See officer. Laws, 373. Chapter

Where, here, an administrative remedy primary, so that exhaustion of administrative remedies must prior occur to relief, seeking judicial we have suggested that: disputant] [A first must file a complaint adminis- [the trative agency] and then decide to file independent an Thereafter, judicial action. the trial court stay must party of either request judicial upon action independent proceeding. of the administrative final resolution until after 27, 806-07. See also Atlantic, 782 A.2d at Md. at Bell 646, 381 Md. County, Educ. Howard v. Board Arroyo (2004) (“[W]e that there is 576, perceive 584-85 851 A.2d action judicial filing indеpendent against prohibition no but, way, are under proceedings administrative primary while i.e., adjudicating, against deciding, prohibition there is a until a final adminis- judicial case independent in the the issue made.”) If (emphasis original). determination is trative administrative- proceed about whether to any there was doubt their courts, Mooneys could have filed through ly the circuit court action judicially; administratively claim the administrative deci- stayed pending could have been then sion. that the Mooneys alleged complaint,

In their Procure- Finance and under 9-405 of the State was breach Chesapeake April the check to Article when it issued ment denial of have this protested could 2003. days April within 30 after Appeals to the Board their claim 15-220 of the State of Section meaning within the so, do but chose Financе and Procurement we remedies. Because attempting to invoke instead reme- of administrative have that the exhaustion recognized sue, we affirm the right precedent dies is a condition Court, in the Circuit Mooneys complaint dismissal for further proceedings. rather than remand *20 THE OF SPECIAL APPEALS OF COURT JUDGMENT REVERSED; THAT REMANDED TO COURT CASE THE AFFIRM JUDGMENT TO WITH INSTRUCTIONS PRINCE GEORGE’S THE CIRCUIT COURT FOR OF IN THE COUNTY; IN AND COURT COSTS THIS COURT PAID BY BE RESPON- APPEALS TO OF SPECIAL DENT. MURPHY, J.

Dissenting Opinion by that to be dismissed on basis complaint never filed on June 2004. Petitioner majority opinion was that argued complaint to the Circuit Court should be that had failed to ground respondents dismissed “exhaust” their administrative remedies. Petitioner never argument this in the briefs it filed on the two presented when bar pending occasions the case at was the Court of Special Appeals. argument pre- Petitioner’s “exhaustion” was argument sented for the first time at the second oral in the Mooney University System, Special Court of Appeals. (2008). 647 n. 943 A.2d 108 Md.App. While this issue Court, may be raised for the first time in this ‍‌‌‌‌‌‌‌​​​​​‌‌​​​​‌‌​​‌‌​​‌​‌‌‌‌‌​‌​‌‌‌‌‌‌‌‌​‌​​‍I am persuaded Respondents’ complaint that should not be dismissed.

If disputed Chesapeake’s right Petitioner had to receive its unpaid $43,005.00 payment, Chesapeake assigned Respondents, Respondents claim to would have been required proceed administratively before the Board of Contract bar, however, The case at Appeals. dispute does not involve a between Petitioner I Chesapeake. agree While with the majority ‘person’ Section 15-217 of the State “[a] ... Finance and Procurement Article does not include only contract, the person awarded the but third par- representing contracting party[,]” ties the interests of the I do agree Respondents not should be included in the defini- “person” ground they tion of on the are involvеd in the process of “collecting property due to Because another[.]” Respondents are “representing not the interests of the con- tracting party,” attempting and are not to collect funds that Chesapeake, Petitioner had withheld from I would affirm the judgment Special of the Court of Appeals and order that this case be returned to the proceedings Circuit Court further opinion inconsistent the March of the Court of Special Appeals. for two notes a Securi- ty Agreement, assigned Chesapeake’s receiv- accounts Mooneys able to the in the event that Chesapeake were to Loan, default “in connection with the including but limited interest, fee, to any principal, deposit, penalty, charge, ad- vancement, assessment, escrow or or pre- taxes or insurance miums, Note, provided in Agreement, any as the the other Mooney, Loan Document.” Kevin whose affidavit states he was a of Chesapeake, signed Security “member”3 Agree- as a ment both lender and a borrower. as In a dated April Mooneys gave letter Chesa- peake Security written notice of under Agreement, default for to make timely payments failure on the loan. letter Mooneys further possession advised intended take notify of receivable Chesapeake’s accounts and to account payments make subsequent debtors to directly Moo- days later, 11, 2003, neys. Mooneys Two on April perfect- security ed their in Chesapeake’s interest accounts receivable financing a with the filing Maryland Department statement The Mooneys alleged Assessments Taxation.4 also their complaint they University System notified (the that, Maryland “University”)5 because the was undisputed Chesapeake promissory It is issued two notes to the 2. $200,000 $50,000, although Security amount of $200,000 Agreement only Agreement refers Line to Credit and a promissory unspecified note money for an amount. sum of The total nevertheless, Chesapeake, analysis. lent to is not relevant to our Article, Corporations 3. Under 4A-602 Section of the and Associations (1975, Maryland Repl.VoL), Code a member has an interest personal property liability company. of a limited security against is defined of a "[v]alidation Perfection interest as 4. creditors, usually by filing public other statement with some office or by taking possession Dictionary of the collateral.” Black’s Law ed.2004). (8th University Maryland, College 5. The Park is a constituent institution University System Maryland. Section 12-101 the Education (1978, Repl.VoL). Code

Case Details

Case Name: University System of Maryland v. Mooney
Court Name: Court of Appeals of Maryland
Date Published: Feb 20, 2009
Citation: 966 A.2d 418
Docket Number: 38, Sept. Term, 2008
Court Abbreviation: Md.
AI-generated responses must be verified and are not legal advice.
Log In