2004 Ohio 7133 | Ohio Ct. App. | 2004
{¶ 3} Almost immediately after work had begun, Universal and PAH identified defects in the architectural plans that required an expansion of the renovation project and an increase in the expenses involved. In August 1998, Universal's president wrote a letter to Aug at PAH outlining his concerns that PAH might lack the funds to complete the enlarged project. Because of federally imposed tax-credit funding restrictions, PAH could not then provide sufficient funding assurances to Universal. Universal threatened to exercise its contractual right to stop work if PAH could not provide additional assurances of funding. At a meeting in November 1998, Aug provided oral assurance that PAH had additional Housing and Urban Development ("HUD") funds and could adequately fund the project. Based upon that representation, Universal rescinded its work-stoppage notice and urged its subcontractors to return to work. But Universal continued to seek written confirmation that funding was available.
{¶ 4} PAH knew that the HUD funds were not forthcoming. PAH endeavored to obtain substitute HUD funding but was not successful. Universal continued working for five more months until April 1999. When PAH was unable to make several payments, Universal stopped work.
{¶ 5} Pursuant to the terms of the contract, in April 1999, Universal filed a claim with the American Arbitration Association alleging that PAH had breached its contractual duty to provide information that sufficient funds were available and seeking money damages. Universal raised no claims of negligent misrepresentation, and Aug was not made a party to the arbitration.
{¶ 6} On July 5, 2000, the arbitration panel awarded Universal and its subcontractors a $4,379,721.10 judgment against PAH. In its detailed arbitration award, the panel found "in favor of Universal against PAH for PAH's breach of contract for its own conduct and that of its representatives, including the conduct of [the project architects]." In the eight-page decision, the panel awarded Universal a total of $2,044,153 for the unpaid balance on work in progress, labor-escalation costs, extended general conditions, extended supervision, lost productivity, unabsorbed office overhead, and demobilization costs. The remaining amounts were awarded to subcontractors Geiler ($902,628), BJ Jacobs ($54,132), Zero-Breeze ($119,563), S/C Shaw ($5,157), Mayers Electric ($274,744), Ooten Interior Systems ($99,031), OK Interiors ($120,778), O'Rourke Construction ($17,380), and Wise Construction ($700,459). On September 22, 2000, in the consolidated cases numbered A-9905309 and A-0004161, the Hamilton County Common Pleas Court confirmed the arbitration award and entered a judgment against PAH subject to 10% interest per annum until payment was made in full.
{¶ 7} According to the affidavit filed in this case by Aug, PAH was unable to fully satisfy the judgment on the breach-of-contract claim. On May 31, 2001, Universal filed this action, alleging that Aug had negligently misrepresented PAH's ability to fund the project and that Universal had relied upon that representation to its detriment by returning to work. Universal sought $4,516,700 in compensatory damages from Aug. Following the denial of Aug's pretrial motions, a jury awarded Universal $467,154 in damages. Aug moved for judgment notwithstanding the verdict pursuant to Civ.R. 50(B). In its well-reasoned 11-page decision, the trial court granted the motion, ruling that while a corporate officer could generally be held liable for torts committed in the course of business, Universal could not proceed in a separate action against Aug for negligent misrepresentation when "[t]he contractual duty of PAH in the arbitration process and the claimed tortuous [sic] conduct of Aug * * * involve[d] the identical duty to provide [correct funding information]."
{¶ 8} When Universal filed this appeal, it was consolidated, for purposes of argument only, with the appeal of a declaratory-judgment action concerning whether Aug would be covered under PAH's directors-and-officers liability policy if Universal obtained a judgment against her.
{¶ 12} In Haddon View, the court reviewed the tort claims for economic damages brought by limited partners who had detrimentally relied upon representations an accounting firm had made to its client, their limited partnership. The individual partners were not in privity with the accounting firm. The court nonetheless held that the accounting firm could be liable to a third party for professional negligence when that third party was a member of a limited class of plaintiffs whose reliance on the firm's representation was specifically foreseen. See
{¶ 13} In resolving negligent-misrepresentation cases, Ohio courts have eschewed a bright-line rule on when to permit recovery. Plaintiffs, including those not in privity with the information provider, have most often raised negligent-misrepresentation claims where a fiduciary or fiduciary-like situation has existed between the information provider and the plaintiff, such as cases involving accountants, appraisers, architects, and bankers. See McCarthy, Lebit, Crystal Haiman Co.,L.P.A. v. First Union Management, Inc. (1993),
{¶ 15} In Textron Financial Corp. v. Nationwide Mutual Insurance Co.
(1996),
{¶ 17} At the other end of the spectrum are duties imposed in relationships involving business transactions negotiated at arms' length by sophisticated parties to further their own economic interests. Some jurisdictions that recognize the negligentmisrepresentation tort do not permit recovery when the negligently provided false information has been conveyed in the course of a contractual relationship. See Fireman's FundIns. Co. v. SEC Donohue, Inc. (1997),
{¶ 18} No Ohio court has denied the right of parties in privity to bring negligentmisrepresentation claims. See McCarthy, Lebit, Crystal Haiman Co., L.P.A. v. First Union Management, Inc.,
{¶ 19} In Floor Craft Floor Covering, Inc. v. Parma Community Gen.Hosp. Assn.,
{¶ 20} "The controlling policy consideration underlying the law of contracts is the protection of expectations bargained for." Floor CraftFloor Covering, Inc. v. Parma Community Gen. Hosp. Assn.,
{¶ 21} While by its terms the tort of negligent misrepresentation applies to "one who, in the course of his business, profession or employment, or in any other transaction in which he has a pecuniary interest, supplies false information," permitting a party who has a contractually defined right to recover economic damages to proceed in a separate action against a corporate officer who has provided false information would similarly undermine the ability of the parties to allocate risks and duties by contract. While an injured party may proceed in the alternative, raising breach of contract and negligent misrepresentation against both an officer and the corporation in an action naming both as defendants, the existence of a recovery for the breach of contract "excludes the opportunity to present the same case as a tort claim." Textron Financial Corp. v. Nationwide Mutual InsuranceCo.,
{¶ 23} Moreover, as the trial court noted, any damages that could have been awarded by the jury on Universal's negligent-misrepresentation claim would have duplicated those damages identified and awarded in the arbitration process. The complaint in this case specifically identified the economic-loss damages being sought as "several million dollars of material and labor provided to PAH for which [Universal] was never paid." This was precisely the injury — economic loss for PAH's breach of contract — that Universal had received compensation for in the arbitration proceeding.
{¶ 24} As reasonable minds could have only concluded in favor of Aug on her motion for JNOV, the assignment of error is overruled, and the judgment of the trial court is affirmed.
Judgment affirmed.
Winkler, P.J., and Hildebrandt, J., concur.