OPINION and ORDER
The Environmental Protection Agency and three similar state entities from Indiana, Michigan, and Illinois initiated this action against U.S. Steel in an 18-count complaint. (For simplicity’s sake, I will refer to the Plaintiffs in this case collectively as the EPA). The EPA alleges that three of U.S. Steel’s plants — one in each of the three states — are and have been violating the Clean Air Act. U.S. Steel says its done no such thing, but the merits of the case will be decided later. The only thing presently before me is whether Count 1 and parts of Count 3 are barred by the applicable statute of limitations and must therefore be immediately dismissed. As explained in detail below, I only buy half of that argument. U.S. Steel’s Motion to Dismiss will therefore be granted in part and denied in part.
BACKGROUND
In 1990, U.S. Steel performed a “reline” of its No. 4 furnace at its Gary Works facility in Gary, Indiana. A reline is the process whereby the furnace is completely shut down and the interior lining is updated. The legal issues raised in U.S. Steel’s motion to dismiss all really emanate from this 1990 relining. One might reasonably wonder why a court in the year 2013 is dealing with actions taken by a company some 23 years earlier; U.S. Steel is wondering the same thing. In all events, U.S. Steel believes it could do the relining of the furnace without a permit, but the EPA disagrees. To understand the parameters of this disagreement, we have to dive into obscure world of the Clean Air Act (“CAA”), its regulations, and the myriad of acronyms that flow from them.
Here’s a broad outline of the parts of the CAA applicable to this case. The CAA establishes two types of air permits: construction permits and operating permits. Both types of permits are at issue in this case. The construction permitting program emerged from the 1977 amendments to the CAA which required all new “sources” — factories, power plants, refineries, etc. — to undergo a “New Source Re
Under the NSR program, the new source must obtain a pre-construction permit from the EPA, demonstrate that the construction will not increase emissions above a certain threshold, and show that facility operations are in continuous compliance with the best available control technology (BACT). The NSR permit then specifies what construction is allowed, what emission limits must be met, and how often the emissions source must be operated.
In addition to these construction permits, most sources also have to obtain operating permits, which are known as Title V permits. A Title V permit grants a source permission to operate, and it includes all air pollution requirements that apply to the source, including emissions limits and monitoring, record keeping, and reporting requirements.
Most of this CAA permitting — both NSR and Title V — is actually done at the state level. The EPA establishes the basic requirements for the CAA, and states can then take those minimum thresholds and develop their own unique requirements and procedures in what is called a State Implementation Plan (“SIP”). Indiana has codified its SIP at Titles 326 and 327 of the Indiana Administrative Code. Indiana’s SIP generally seems to mirror the federal requirements, including requirements that new sources must obtain a pre-construction NSR permit and install BACT.
All of this applies to new sources, those built after 1977. The Gary Works plant, however, has a lot of dust on it; steel production began there in the early part of the last century. That doesn’t take the plant out of the regulatory woods, however, because the CAA says that even pre1977 plants must comply -with the NSR permitting program any time a “major modification” is made to them. Enter the 1990 relining project. U.S. Steel concluded that the reline wasn’t a major modification, so it didn’t bother seeking a preconstruction NSR permit. Then, in 1996, U.S. Steel applied for a Title V operating permit, which was eventually issued by the state of Indiana. The EPA now argues that the 1990 reline was a major modification, that U.S. Steel thus should have sought a preconstruction NSR permit, and that consequently the Title V permit was improperly granted and should be invalidated. More specifically, the EPA alleges in Count 1 that U.S. Steel performed a major modification, which violated the CAA and Indiana’s SIP by operating Gary Works without an NSR permit and without BACT. In Count 3, the EPA alleges that U.S. Steel is operating Gary Works in violation of the Title V permitting program under the CAA and Indiana’s SIP.
Whether or not the 1990 reline was a major modification is likely to be a difficult question to answer. See, e.g., U.S. v. Midwest Generation, LLC,
A motion to dismiss pursuant to Rule 12(b)(6) “challenges the sufficiency of the complaint to state a claim upon which relief may be granted.” Hollinan v. Fraternal Order of Police of Chi. Lodge No. 7,
The applicable statute of limitations here is 28 U.S.C. § 2462, which states:
Except as otherwise provided by Act of Congress, an action, suit or proceeding for the enforcement of any civil fíne, penalty, or forfeiture, pecuniary or otherwise, shall not be entertained unless commenced within five years from the date when the claim first accrued if, within the same period, the offender or the property is found within the United States in order that proper service may be made thereon.
Count 1 and Count 3 of the Complaint seek both injunctive relief and civil penalties. Section 2462 explicitly applies to the latter remedy, but it is less clear whether it applies to the former. As explained in detail below, I ultimately conclude that Section 2462 does not apply to claims for injunctive relief, but does apply to claims for civil penalties. I’ll start by analyzing the question of civil penalties, and then turn to the more difficult issue of injunctive relief.
Before moving to this analysis, however, I need to clear up one issue with respect to how Counts 1 and 3 are interrelated. The EPA argues that the Counts should be independently analyzed: “Regardless of how the Court decides the issue of whether NSR violations are ongoing, as Plaintiffs urge, or one-time past violations, as Defendant argues, the Court should deny Defendant’s Motion with regard to Plaintiffs’ Third Claim.” [DE 20 at 38.]
I disagree, and will instead analyze both Counts in the same way here. Here’s why. The main focus of the motion to dismiss really has to do with Count 1 of the Complaint, which is entirely centered on the NSR permitting process related to the 1990 reline. Count 3 deals with the Title V permitting process. The 1990 reline is only one part of Count 3, and U.S. Steel has only moved to dismiss the paragraphs in Count 3 that deal specifically with the 1990 reline (not all of Count 3). The central conceit of Count 3 is that U.S. Steel’s Title V permit has numerous deficiencies, one of which is that U.S. Steel’s application for the permit lacked information about the 1990 reline. More specifically, Count 3 asserts that since U.S. Steel did not have an NSR preconstruction permit for its 1990 reline, its 1996 application for its Title V permit was deficient.
I. Civil Penalties
The issue of whether the EPA is barred from bringing claims for civil penalties based on the 1990 reline is fairly straightforward. Section 2462 clearly applies to claims for civil penalties, which means all such claims must be brought within 5 years of their accrual. U.S. Steel argue that since the permitting violations are alleged to have occurred in 1990, the government had to bring any civil penalty claims by 1995. Any claims brought thereafter are barred by the statute of limitations.
The logic of this is simple and undoubtedly correct. The EPA, nevertheless, has grasped for various statute-of-limitations straws that would extend their time to file suit beyond five years. First, they argued that the discovery rule extends the limitations period, but they have now rightly abandoned that argument in the face of the Supreme Court’s recent decision in Gabelli et al. v. Securities and Exchange Commission, — U.S. —,
The EPA also argues that the statute of limitations was extended beyond 1995 because there was not just one violation in 1990, but rather a series of ongoing and continuous violations. The theory is that there is a new violation (and thus a new 5-year limitations period) every day since 1990 that U.S. Steel was out of compliance with the federal NSR permitting requirements and the Indiana SIP permitting requirements. This “continuing violation” argument is a somewhat more complicated question as various circuit and district courts have split on the issue. But the question got a whole lot easier to answer (for me, at least) a few weeks ago, as the Seventh Circuit addressed this very issue in U.S. v. Midwest Generation, LLC,
Given Midwest Generation, it is clear that the EPA’s civil penalty claims based on federal law (i.e., 42 U.S.C. § 7475) are barred by the statute of limitations. Nevertheless, Midwest Generation did leave one small door open — whether U.S. Steel violated Indiana’s state regulations (the aforementioned “SIP”). Midwest Generation explicitly left this question for the district court to figure out. Here’s how the Seventh Circuit explained the issue:
Plaintiffs stress that § 7475(a)(4) says that newly built or modified sources are “subject to” the need for the best available control technology. That obligation, they insist, continues after the construction work is done, which leads them to say that National Parks and Conservation Association Inc. v. Tennessee Valley Authority,480 F.3d 410 (6th Cir.2007), disagrees with the eighth and eleventh circuits .[and, now, the seventh circuit]. Yet the sixth circuit’s decision rests on Tennessee statutes and implementation plans that require certain sources to use the best available control technology, while § 7475 deals only with conditions precedent to construction or modification. Perhaps an Illinois statute, regulation, or implementation plan provides that any plant “subject to” BACT by virtue of § 7475(a)(4) must use it in operation, but any claim of that sort remains pending in the district court. What BACT entails is plant-specific. 40 C.F.R. § 52.21(b)(12). All we have for decision is a claim directly under § 7475. Plaintiffs maintain that 415 ILCS 5/9.1(d)(2) works the same way as the Tennessee requirements that the sixth circuit considered. To the extent that this contention is independent of § 7475, we leave it to the district judge in the first instance.
Id. at 647. Take this directive, substitute “Indiana” for “Illinois,” and it is now clearly left to me in this case to decide, “in the first instance,” whether the Indiana regulations at issue here work “the same way as the Tennessee requirements that the sixth circuit considered” in National Parks. Id.
With these marching orders, I have to comb the depths of Tennessee environmental law and see how it compares with Indiana. But before getting there it’s worth pointing out that the Sixth Circuit’s decision in National Parks is clearly an outlier.
So the Sixth Circuit’s decision in National Parks is now the one case where a circuit court upheld the continuing violation'theory. How did it get there? Under the Sixth Circuit’s reasoning, two provisions of Tennessee law dictated its result.
[U]nder the Tennessee SIP, the obligation to obtain an appropriate permit is ongoing, and applies even to those sources that did not obtain the appropriate permits before construction: “In the case where a source or modification was constructed without first obtaining a construction permit, a construction permit may be issued to the source or modification to establish as conditions of the permit, the necessary emissions limits and requirements to assure that these regulatory requirements are met.” Id. § 1200 — 3—9—.01(l)(e). In other words, while § 1200-3-9-.01(l)(a) contains the Tennessee SIP’s pre-construction permitting requirement, § 1200-3-9-.01(l)(e) establishes that the duty to obtain a construction permit containing the proper emissions limits is ongoing, even post-construction.
National Parks,
The Eighth and Eleventh Circuits agreed with this reading of Tennessee’s SIP, but also contrasted it to the other state SIPs that did not contain similar provisions. As the Eighth Circuit explained:
Because [Tenn. Comp. R. & Regs. § 1200-3-9-.01(l)(e) ] would allow a facility to obtain a determination of BACT limits through a postconstruction permitting process, the Sixth Circuit’s conclusion that in Tennessee there were ongoing duties both to obtain a permit and to employ BACT made sense. Sierra Club has pointed to no similar rule in South Dakota, and its contention that there is an independent ongoing duty to apply BACT is therefore not persuasive.
Sierra Club,
The Sixth Circuit believed it had another, independent reason for applying the continuing violation doctrine to Tennessee’s SIP, however. The court pointed to this provision: “A major modification shall apply best available control technology for any pollutant for which it would result in a significant net emissions increase at the source.” Tenn. Comp. R. & Regs. § 1200-3-9-.01(4)(j)(3). The Sixth Circuit found that “[t]his provision, by its own terms, creates an ongoing obligation to apply BACT, regardless of what terms a preconstruction permit may or may not contain.” National Parks,
Indiana’s SIP has a nearly identical “shall apply” provision. Indiana’s provision states: “A major modification shall apply best available control technology for each regulated NSR pollutant for which the modification would result in a significant net emissions increase at the source. This requirement applies to each proposed emissions unit at which a net emissions increase of the pollutant would occur as a result of a physical change or change in the method of operation in the unit.” 326
The Sixth’s Circuit’s reasoning on this point, however, was heavily criticized by both the Eighth and Eleventh Circuit. The Eighth Circuit, for instance, had this detailed analysis:
Emphasizing the imperative phrase “shall apply,” the Sixth Circuit interpreted ... Tennessee’s SIP as creating “an ongoing obligation to apply BACT, regardless of what terms a preconstruction permit may or may not contain.” Nat'l Parks 6th Cir.,480 F.3d at 418 . We cannot agree with this interpretation. The context of [40 C.F.R.] § 52.21(j)(3) shows that the command to apply BACT is not a freestanding requirement. Rather, it is tied specifically to the construction process. Subsection (j)(3) “applies to each proposed ... unit” (emphasis added); see Nat’l Parks 11th Cir.,502 F.3d at 1324-25 .... In light of these provisions, § 52.21(j)(3) is best understood as requiring that BACT limits be incorporated into a facility’s construction plans and [NSR] permits, not as establishing an ongoing duty to apply BACT independent of the permitting process.
This conclusion is bolstered by the practical nature of BACT. BACT limits are tailored to each facility “on a case-by-case basis” during the [NSR] permitting process. 42 U.S.C. § 7479(3); see also 40 C.F.R. § 52.21(b)(12). They are thus inextricably linked to the permitting process. Having determined that there is no ongoing duty to obtain [NSR] permits, it would make little sense to conclude that Otter Tail must nevertheless abide by the BACT limits which are a product of such permits____The duty to obtain a [NSR] permit and the duty to apply BACT are most sensibly construed as going hand in hand.
Sierra Club,
Similarly, the Eleventh Circuit also disagreed with the Sixth Circuit’s reasoning:
To the extent the Sixth Circuit interpreted the “shall apply” language by itself as creating an ongoing obligation to apply Best Available Control Technology every time the source operates ... we do not adopt that interpretation of the similarly worded Alabama regulations. Without a provision imposing an ongoing duty to meet preconstruction requirements that were not met at the time of construction, there is no basis for us to conclude that National Parks’ and the Sierra Club’s New Source Review allegations in this case are timely under the governing Alabama regulations.
National Parks,
I find the analysis of the Eighth and Eleventh Circuits much more persuasive than the Sixth Circuit approach. The “shall apply” language in Indiana’s SIP can only sensibly be read to be tied to the construction process because it applies to “each proposed emissions unit.” 326 IAC 2-2-3. What this means is that if a company is contemplating building a new facility or making a major modification to an existing facility — i e. a “proposed” emission unit — it must apply the best available control techniques. It doesn’t mean that there is an ongoing duty to apply the BACT limits independent of the permitting process. Sierra Club,
This conclusion is also consistent with the Seventh Circuit’s general holding that NSR permitting violations — including the failure to install BACT — all relate to the one-time construction (in this case, the modification) and not to the continuous operation:
The violation is complete when construction commences without a permit in hand.... [Operating a new or modified plant, despite failure to obtain a construction permit, is [not] a new violation of § 7475(a).... Although plaintiffs insist that the construction permit has “an operational component,” they mean only that under § 7475(a)(4) the operator must install the best available control technology. Section 7475(a)(4) specifies what must be built, not how the source operates after construction. If the owners ripped out or deactivated the best available control technology after finishing construction that would not violate § 7475 — though it might well violate some other statute, regulation, or implementation plan prescribing how polluters run their facilities.
Midwest Generation,
In sum, I find that the five-year statute of limitations bars any claims for damages under either federal law or Indiana state law for U.S. Steel’s alleged failure to obtain the proper NSR pre-construction permit and to install the best available control techniques. Consequently, Plaintiffs’ claims for damages in its Count 1, and the paragraphs in Count 3 related to the NSR permitting (¶¶ 122-127), are time-barred and will be dismissed.
II. Injunctive Relief
That leaves the issue of whether Section 2462’s five-year time limit applies to the EPA’s claim for injunctive relief. Just like the civil penalties analysis above, the analysis here would seem to be relatively straightforward: Section 2462 only explicitly applies to fines and penalties, so its five-year limitations period does not apply to equitable claims.
Of course, since every successful claim for injunctive relief penalizes the defendant in some way by forcing it to do what it otherwise wouldn’t have done, it can always be argued that an injunction functions as some sort of “penalty” and should thus be subject to Section 2462’s limitations period. Numerous courts have addressed this issue, and they have converged on a relatively simple analysis. Section 2462’s limitations period does not apply to injunctive relief if the injunction is actually remedial — ie., if it “seeks to undo prior damage or protect the public from future harm.” S.E.C. v. Wyly,
This structure of analysis makes some intuitive sense. If a defendant is simply not complying with a law, perhaps the government should always have the right to at least bring a suit demanding that it come into compliance. It would make little sense if a- defendant could strategically comply with some CAA regulations for five years and then immediately stop doing so on the theory that it would be immune from suit. On the other hand, it also makes sense that the government can’t get
So is the injunctive relief sought by the EPA here really a remedial injunction or a penalty? The Tenth Circuit’s analysis of the Clean Water Act in United States v. Telluride Co.,
The same is true here: the government is attempting to remedy the damage that U.S. Steel is alleged to have caused by being out of compliance with the Clean Air Act. It is thus clear that the EPA is not barred by Section 2462 from bringing its claim for injunctive relief. U.S. Steel has two arguments as to why the claims for injunctive relief are barred: 1) it says that this case is different and the injunction is actually a penalty/forfeiture; and 2) the concurrent-remedy doctrine applies. I will consider each of these arguments in turn.
A. Injunction vs. Penalty/Forfeiture
First, U.S. Steel argues that the injunction is, in truth, a penalty or a forfeiture and thus subject to the five-year limitations period. If an injunction were to be entered it would force U.S. Steel to apply for an NSR permit, install and operate BACT, and demonstrate compliance with the CAA. U.S. Steel says this amounts to a penalty:
The injunctive relief sought by the Government is undoubtedly unjustified and would be unreasonably severe. It asks this Court to undo, and require U.S. Steel and IDEM to redo, an operating permit that took the parties 10 years to develop in the first place. In addition, the Government requests an injunction requiring U.S. Steel to undergo a preconstruction permitting review for a project that was completed 22 years ago. Most relevant, however ... the Complaint simply does not seek to address the “injury caused by the defendant” and, therefore, cannot be remedial in nature. Since there is nothing remedial in its requested relief, by asking this Court to allow the Government to void Gary Works’ operating permit and enjoin U.S. Steel to obtain new permits with new (and, as is undoubtedly the Government’s intent, more onerous) limits, the Government is seeking a penalty.
[DE 14-1 at 14.]
I disagree that the injunctive relief sought here functions solely as a penalty. If a factual determination is made in the course of this case that the 1990 reline was a major modification such that U.S. Steel should have gone through the NSR permitting process and installed BACT, then it may very well be that the proper remedy would be an order forcing U.S. Steel to install BACT and/or to reapply for a new Title V operating permit. Any such order would be “remedial” in that its effect
U.S. Steel similarly argues that the injunctive relief is actually a forfeiture because it could involve the revocation of its Title V operating permit. U.S. Steel points to Article II Gun Shop, Inc. v. Gonzales,
I disagree that Article II Gun Shop is applicable here. First, the “holding” U. S Steel teases out of that case is actually just very weak dicta. The true holding of that case was that the government’s revocation of the gun shop’s license was timely because it was brought within five years of violations that-occurred in 2000. Article II Gun Shop,
Thus, I find that the injunctive relief sought here is neither a penalty nor a forfeiture, and it is therefore not barred by Section 2462’s five-year limitations period.
B. Concurrent Remedy Doctrine
U.S. Steel also argues that the injunctive relief claims must be dismissed because the “concurrent remedy doctrine” applies. The concurrent remedy rule provides that when legal and equitable relief are available “concurrently” (ie., when an action at law or equity could be brought on the same facts), “equity will withhold its relief in such a case where the applicable statute of limitations would bar the concurrent legal remedy.” Cope v. Anderson,
The problem with this argument, however, is that courts have uniformly held that the “concurrent remedy rule” does not apply to “a suit by the United States in its governmental capacity.” Telluride,
Let me explain. First, the idea that the concurrent remedy rule doesn’t apply to the government comes initially from the Eleventh Circuit’s decision in Banks and its analysis of E.I. du Pont. The district court cases cited above generally just cite to Banks and/or E.I. du Pont, as does the Tenth Circuit’s decision in Telluride. Most of these cases more or less just cite Banks without actually engaging in any independent analysis of the issue, which is understandable, given how decisive Banks is on the topic.
Nevertheless, on a close read, I think the analysis in Banks is deeply flawed. I’ll get to those flaws in a moment, but first let’s get a better handle on what the concurrent remedy doctrine actually is. Here’s the basic principle: “when the jurisdiction of the federal court is concurrent with that at law, or the suit is brought in aid of a legal right, equity will withhold its remedy if the legal right is barred by the local statute of limitations.” Russell v. Todd,
Thus, an important distinction to keep at the forefront here is that the concurrent remedy doctrine is not a statute of limitations rule; rather, it’s a general rule about the scope of equity’s reach. The doctrine has nothing to do with whether the applicable statute of limitations (here, Section 2642) applies to equitable remedies, which is a question I’ve already addressed above. Rather, the question here is whether a separate principle of equity — the concurrent remedy doctrine — independently bars the EPA’s equitable claims for relief here.
But what does it actually mean for legal and equitable remedies to be “concurrent”? In the context of litigation like this, where the EPA seeks to enforce alleged NSR violations under the CAA, one might argue that the remedies here are not really “concurrent” at all: the civil penalties sought here would likely serve a completely different purpose than the injunctive relief being sought. Indeed, that was the conclusion of at least one district court in this circuit:
[Rjegardless of a government exception to the concurrent remedy doctrine, thecivil fines and the equitable remedies the Plaintiffs seek are not concurrent, because they have different goals and effects. For example, the citizen suit provisions of the Act create an equitable remedy to stop threats to the environment. Civil fines collected through a citizen suit must be paid to the United States, not to the citizens; thus, “the primary purpose of civil penalties is deterrence, not reward to the Plaintiffs.” As a result of this distinction, the concurrent remedy doctrine does not operate to bar the Citizens’ suit for injunctive relief.
Cinergy,
As superficially intuitive as that reasoning might seem, however, it’s hard to square it with the Seventh Circuit’s decision in Nemkov v. O’Hare Chicago Corp.,
In fact, when concerned citizen groups (rather than the government) have alleged NSR violations just like in this case, courts have not hesitated to find that legal and equitable claims are concurrent such that the concurrent remedy doctrine bars the plaintiffs’ claims for injunctive relief. See Otter Tail,
[Cinergy ] suggested that, even if the government exception to the concurrent remedy doctrine had not applied, the civil remedies and equitable relief at issue in that case were nonetheless not concurrent because “they have different goals and effects.” Id. We respectfully disagree with this part of his analysis. As discussed above, our understanding of the doctrine is that it is not the nature of the remedy that is determinative, but rather whether the equitable relief is available on the same set of facts as a time barred legal remedy that determines whether the concurrent remedy doctrine applies. See Nemkov,592 F.2d at 354-55 . Thus, we find that the doctrine acts to bar equitable relief here because legal remedies albeit time-barred were available to vindicate the same rights for which Plaintiff was seeking relief in equity.
Id.
It’s thus clear that claims for civil penalties and injunctive relief based on NSR violations are indeed “concurrent.” Therefore, for the concurrent remedy doctrine not to apply here, it has to be because there is something special about the government being the plaintiff. This is where we return to Banks, which concluded that there is in fact something special about that fact.
Banks definitively states that “the concurrent remedy rule cannot properly be
Banks, however, urges us to adopt the “concurrent remedy rule,” which provides that “equity will withhold its relief ... where the applicable statute of limitations would bar the concurrent legal remedy.” Cope v. Anderson,331 U.S. 461 , 464,67 S.Ct. 1340 ,91 L.Ed. 1602 (1947). Banks relies chiefly on United States v. Windward Properties, Inc.,821 F.Supp. 690 (N.D.Ga.1993) to support his position. In Windward, the government sought equitable relief and civil penalties under section 309 of the CWA against the defendant for unpermitted discharge of dredged or fill materials into streams and adjacent wetlands. There, the court applied the concurrent remedy rule to bar the government’s claims for equitable relief under similar facts to this case. Id. at 693.
The Windward court, however, did not address the well-established rule that “an action on behalf of the United States in its governmental capacity ... is subject to no time limitation, in the absence of congressional enactment clearly imposing it,” E.I. du Pont de Nemours & Co. v. Davis,264 U.S. 456 , 462,44 S.Ct. 364 ,68 L.Ed. 788 (1924); United States v. Alvarado,5 F.3d 1425 , 1427 (11th Cir.1993), or the canon of statutory construction that “any statute of limitations sought to be applied against the United States ‘must receive a strict construction in favor of the Government.’ ” Alvarado,5 F.3d at 1428 .
Incorporating these principles into the analysis, the properly constructed rule is that — absent a clear expression of Congress to the contrary — a statute of limitation does not apply to claims brought by the federal government in its sovereign capacity. The statute is enforced against the government only when the government is acting to vindicate private interests, not a sovereign or public interest. See United States v. Beebe,127 U.S. 338 , 347,8 S.Ct. 1083 ,32 L.Ed. 121 (1888).
We conclude, therefore, that the concurrent remedy rule cannot properly be invoked against the government when it seeks equitable relief in its official enforcement capacity. Because Congress did not expressly indicate otherwise in the statutory language of section 2462, its provisions apply only to civil penalties; the government’s equitable claims against Banks are not barred.
Id. (footnotes omitted).
On a close read of this analysis, its flaws become manifest: what starts out as ostensibly an analysis of the concurrent remedy doctrine quickly changes into an assessment of how the statute of limitations applies to equitable claims — an entirely separate (and already answered) question. Indeed, Banks’ citation to E.I. du Pont belies its flaws and underscores my point. E.I. du Pont has nothing to do with the
Nevertheless, while Banks and the other courts that have parroted its analysis leave me wanting for logic, I am still reluctant to find that the concurrent remedy doctrine bars governmental action. This hesitancy derives from two sources. First, I have not been able to uncover a single instance where the concurrent remedy doctrine has been used to bar governmental action. U.S. Steel points me to Federal Election Commission v. Williams,
My second source of reluctance is this: Can some creaky, esoteric doctrine of equity really prevent the government from enforcing basic public policy? At a minimum, shouldn’t the government always be able to bring an equitable action to bring a defendant into compliance with the law? Counseling in favor of this intuition is the fact that the most prominent equitable doctrine related to limitations periods-— laches — does not apply to government action for this very reason. As the Supreme Court has explained:
The rule quod nullum tempus oceurrit regi — that the sovereign is exempt from the consequences of its laches, and from the operation of statutes of limitations— appears to be a vestigial survival of the prerogative of the Crown. But whether or not that alone accounts for its origin, the source of its continuing vitality where the royal privilege no longer exists is to be found in the public policy now underlying the rule even though it may in the beginning have had a different policy basis. The true reason is to be found in the great public policy of preserving the public rights, revenues, and property from injury and loss, by the negligence of public officers. And though this is sometimes called a prerogative right, it is in fact nothing more than a reservation, or exception, introduced for the public benefit, and equally applicable to all governments. Regardless of the form of government and independently of the royal prerogative once thought sufficient to justify it, the rule is supportable now because its benefit and advantage extend to every citizen, including the defendant, whose plea of laches or limitation it precludes; and its uniform survival in the United States has been generally accounted for and justified on grounds of policy rather than upon any inherited notions of the personal privilege of the king. So complete has been its acceptance that the implied immunity of the domestic ‘sovereign,’ state or national, has been universally deemed to be an exception to local statutes of limitations where the government, state or national, is not expressly included....
Guaranty Trust Co. of N.Y. v. United States,
What is animating all of these cases in the end is the fundamental public policy principle expressed by the Supreme Court — that “the sovereign is exempt from the consequences of its laches” — because the government has to have enforcement power to enjoin violations of the law. Guaranty Trust,
CONCLUSION
For the reasons explained above, U.S. Steel’s Motion to Dismiss [DE 14] is GRANTED in part and DENIED in part, consistent with this opinion. Furthermore, Plaintiffs’ Motion to Correct and/or Clarify Transcript of Oral Argument Held on 1/24/2013 [DE 34] is unopposed and is thus GRANTED.
SO ORDERED.
Notes
. After Midwest Generation came out, the United States filed a motion [DE 49] that sought to defer ruling on U.S. Steel’s motion to dismiss on the theory that it might appeal the Seventh Circuit's ruling. Magistrate Judge Rodovich rightly denied that motion. If the United States decides to appeal and if the ruling in Midwest Generation is altered as a result, then I will obviously revisit my holding here. In the meantime, U.S. Steel has waited long enough for a ruling on its motion, which I purposely put on hold pending the Seventh Circuit's ruling in Midwest Generation.
. And not to be confused with the Eleventh Circuit’s decision in a case of the same name.
. I did turn up Bank of U.S. v. Daniel,
