delivered the opinion of the Court.
The Interstate Commerce Commission instituted the proceedings leading to the orders here involved as its Seventy-fifth and Seventy-sixth Supplemental Reports to Ex parte 10/+, Practices of Carriers Affecting Operating Revenues or Expenses, Part II, Terminal Services, 209 I. C. C. 11. The proceedings concerned the switching and spotting services rendered by appellee-carriers at the Garfield and Murray, Utah, and Leadville, Colorado, plants of the American Smelting Company, and the Mid-vale, Utah, plant of the United States Smelting Company. Extensive hearings were held in these supplemental proceedings for the purpose of determining the respective points at which the carriers’ line-haul transportation service ended and the extent of the service the carriers might render in the discharge of their obligation to deliver the freight at these four plants.
It will not be necessary to detail the physical characteristics of each of the plants involved here. Each has a receiving yard or interchange tracks upon which incoming and outgoing freight is switched. Beyond the interchange tracks switching services are numerous and extensive within the plants. The Garfield plant may be described as indicative of the situation at all the plants. 1 There, frozen ore is handled in six distinct movements. A large amount of intraplant switching is done by the carriers. To perform these switching services.at Garfield requires three train-crew shifts daily. In one twelvemonth period at this plant, 22,982 carloads of inbound and 6,960 carloads of outbound freight were handled.
The Commission undertook its general investigation,
Ex parte 104,
in the interest of establishing a uniform and equal service for shippers. The Commission concluded that carrier obligation for transportation service ends customarily when delivery is made at a convenient point on the siding inside or outside a consignee’s plant. This delivery is such as may be accomplished in one continuous movement without “interruption” occasioned for the convenience of the industry, and is only the equivalent of team track or simple placement switching. In the Commission’s view as developed in
Ex parte 104,
such a con
As stated, the purpose of these proceedings before the Commission was to determine the beginning and end of
“The question of the reasonableness of published rates or of charges that are or may be fixed for performing industrial services can be decided only in a proceeding brought, or investigation instituted, under different provisions of the act. It is our purpose to make it entirely clear here that our order herein is based solely upon our findings herein, which in turn are based solely upon the principles and authority established with the approval of the Supreme. Court in our original and supplemental reports in Ex Parte No. 104, Part II, and that said order is not based in whole or in part upon any conclusions or findings in connection with tariff provisions or testimony as to whether the published rates are reasonable and do or do not include compensation for switching within the plant areas. We hereby repudiate any reference or conclusion to the contrary conveyed by our discussion or evidence relative to such questions and the conclusions based thereon in our prior supplemental report herein.” 270 I. C. C. at 362.
With that clear and distinct statement of what it was doing and what it was not doing, the Commission made its findings of fact which appear in the margin.
4
The essen
That the Commission is authorized to establish the point where line-haul service begins and ends is not to be doubted. The question, in reviewing the Commission’s determination of the convenient points at which line-haul or carrier transportation service begins and ends, is whether such determination is supported by substantial evidence,
5
as this Court said in
United States
v.
Wabash R. Co.,
“In sustaining the Commission’s findings in these proceedings, as in related cases, this Court has held that the point in time and space at which the carrier’s transportation service ends is a question of fact to be determined by the Commission and not the courts, and that its findings on that question will not be disturbed by the courts if supported by evidence.”
The contention of appellees is that there are now in effect tariffs that compensate for line-haul and plant services. These tariffs will be separately discussed below. Appellees urge that the carriers cannot be guilty of violating § 6 (7) when they are fully compensated for carrier services in line-haul and plant services beyond that, since the smelters do not then receive a preferential service not accorded to shippers generally. The corollary of this contention is that to require payment for the plant services in addition to the line-haul rates, in accordance with the Commission’s orders, would be to require the smelters to pay twice for the services.
This Court has emphasized that the preference involved in these proceedings is based upon an application of the standards derived from
Ex parte 104
to the unique conditions at particular plants, a preference necessarily resulting when a service is rendered “in excess
A tariff, effective June 25,1938, is considered applicable only to the Midvale, Garfield, and Murray plants. By this tariff the “line-haul rate includes movement of loaded cars to track scales and subsequent delivery to any designated track within the plant which can be accomplished by one uninterrupted movement . . . from the road-haul point of delivery to the switching line.” 6 266 I. C. C. at 353-354. There are additional charges for other services in the plants.
If the Commission has the authority to fix the point at which line-haul begins and ends, and we have held that it has, and it designates Point X, obviously the carriers cannot by tariff fix line-haul at Point Y, a further point, and even add one subsequent movement. That would deprive the Commission of its right to determine the point. In the Commission’s judgment, which is supported by the evidence, delivery to Point X is the equivalent of team track and simple placement service — the service other shippers receive under a line-haul rate. For the carriers to give the appellee-smelters service to Point
The tariff which is considered by appellee-carriers as applicable only to the Leadville plant is set forth in the margin. 7 It may be noted that this tariff does not provide, as does the 1938 tariff applicable to the other plants, that the line-haul rate includes the intraplant services. Further, the “movement” specified in delivery of a line-haul shipment includes not just one, as provided by the 1938 tariff, but several switching operations which the Commission has classified as “interrupted” terminal switching services, performed for the convenience of the industry only.
The Commission has fixed the point at which line-haul or transportation service ends as the “flat yard” at Leadville and finds there are services performed beyond this point. These industry services must be so com
“Since the Commission finds that the carriers’ service of transportation is complete upon delivery to the industries’ interchange tracks, and that spotting within the plants is not included in the service for which the line-haul rates were fixed, there is power to enjoin the performance of that additional service or the making of an allowance to the industry which performs it.” United States v. American Sheet & Tin Plate Co.,301 U. S. 402 , 408.
Obviously the plant services at Leadville are different from those at Midvale, Garfield, and Murray under the 1938 tariff, which only emphasizes the wisdom of Congress in empowering the Commission to fix the point where line-haul begins and ends with a view to giving all shippers equivalent service. The Commission has standardized such service as team track or simple placement switching. What we now hold is that the Commission has the power to fix the point at which line-haul or carrier service begins and ends. This is necessary because the need for switching varies from plant to plant; indeed, some plants may need no intraplant switching service. Thus, unless the Commission can fix the beginning and ending point of the line-haul, some shippers would pay an identical line-haul rate for less service than that required by other industrial plants. See
Baltimore & Ohio R. Co.
v.
United States,
As to the argument that to require the carriers to conform to the Commission’s orders would require the appellee-smelters to pay twice for their service, the short
Finally it is contended that the District Court judgment should be affirmed because there was no appeal from the judgment and mandate when the case was sent back to the Commission, the court having found that there was no evidence to sustain a Commission finding that the line-haul rates were not compensatory for the services rendered. Appellees argue that that decision became the law of the case.
The rule of the law of the case is a rule of practice, based upon sound policy that when an issue is once litigated and decided, that should be the end of the matter.
Messenger
v.
Anderson,
Judgment reversed.
Notes
The plants are described in detail by the Commission in its reports, 263 I. C. C. 749, 266 I. C. C. 476, 270 I. C. C. 385; 263 I. C. C. 719, 2661. C. C. 349, 2701. C. C. 359.
Corn Products Refining Co.
v.
United States,
“No carrier, unless otherwise provided by this chapter, shall engage or participate in the transportation of passengers or property, as defined in this chapter, unless the rates, fares, and charges upon which the same are transported by said carrier have been filed and published in accordance with the provisions of this chapter; nor shall any carrier charge or demand or collect or receive a greater or less or different compensation for such transportation of passengers or property, or for any service in connection therewith, between the points named in such tariffs than the rates, fares, and charges which are specified in the tariff filed and in effect at the time; nor shall any carrier refund or remit in any manner or by any device any portion of the rates, fares, and charges so specified, nor extend to any shipper or person any privileges or facilities in the transportation of passengers or property, except such as are specified in such tariffs.” 24 Stat. 379, as amended, 49 U. S. C. § 6 (7).
The following were the findings of fact relating to the Garfield, Murray and Leadville plants of American Smelting. The findings with respect to the Midvale plant of United States Smelting were substantially identical.
“(1) That it is the duty and obligation of the smelters to obtainand certify to the carriers the values of ores for the purpose of ascertaining freight charges, and that the carriers are not under any obligation or duty to perform any switching or other services for the purpose of ascertaining, or assisting the smelters in ascertaining, such values.
“(2) That the ‘plant yard’ at the Garfield plant, the ‘hold tracks’ at the Murray plant, and the ‘flat yard’ at the Leadville plant, hereinafter referred to collectively as the ‘convenient points’ as described in the prior supplemental reports herein, are reasonably convenient points for the delivery and receipt of carload traffic moving to and from the plants of the American Smelting & Refining Company.
“(3) That the several respondents serving said plants move loaded and empty freight cars from said convenient points to points within the plant areas, from such points within the plant areas to the convenient points, and between points within the plant areas.
“(4) That the said services rendered within the plant areas to and from the convenient points are in excess of those rendered shippers generally in the receipt and delivery of traffic on team tracks or industrial sidings or spurs.
“(5) That the said services rendered between points within the plant areas are in excess of those rendered shippers generally in the receipt and delivery of traffic on team tracks or industrial sidings or spurs.
“(6) That the services from and to the convenient points and between points within the plant areas are not and cannot be performed in a continuous movement without interruption or interference at respondents’ operating convenience because of the disabilities of the plants, including the manner in which the industrial operations are conducted, all as explained in the prior supplemental reports.
“(7) That the said services rendered between the convenient points and points in the plant areas and between points within the plant areas are in excess of those performed in simple switching and team-track delivery and are industrial or plant services which respondents are not obligated to and should not perform at the line-haul rates.
“(8) That the common-carrier transportation which respondents are obligated to perform begins and ends at the convenient points,and that all services beyond those points in the plant areas are industrial or plant services for which respondents should make reasonably compensatory charges.
“(9) That the performance by respondents without reasonably compensatory charges in addition to the line-haul rates of the described services within the plant areas beyond the convenient points at any and all of the said plants results in the American Smelting & Refining Company receiving a preferential service not accorded shippers generally and results in the refunding or remitting of a portion of the rates and charges collected in violation of section 6 (7) of the act.” Id., at 367-368.
See
Interstate Commerce Commission
v.
Hoboken Manufacturers’ R. Co.,
An “uninterrupted movement” is defined in the tariff as "one continuous movement of switching locomotive and crew without interruption, resulting from orders from, or requirements of, the smelter.”
This tariff is almost identical with that which was applicable to all of the plants in 1920. The smelters, we are informed, pay the 1938 tariff under protest, and insist upon the 1920 tariff.
“Delivery op Line-Haul Carload Shipment Destined to Smelter at Leadville, Colo.
“Delivery of a line-haul carload shipment destined to smelter at Leadville, Colo., will include movement within smelter plant over track scales, to and from thaw-house, to and from a smelter sampler or to and from a combination sampler and concentrator to a designated unloading point indicated by the sampling company.”