Lead Opinion
The United States, on behalf of the Department of the Navy, brought an ejectment action against the appellant, Triple A, under 28 U.S.C. § 1345, seeking possession of property the government had leased to Triple A, and damages.
The district court granted the government’s motion for partial summary judgment, declaring that the Navy was entitled to immediate possession of the property and permanently enjoining Triple A from remaining on it. Triple A moved to vacate the ordеr on two grounds: (1) the district court lacked subject matter jurisdiction, and (2) alternatively, the district court improperly applied the parol evidence rule.
FACTS AND PROCEDURAL HISTORY
The Hunters Point Naval Shipyard consists of approximately 965 acres of land located on San Francisco Bay. The United States Navy operated it until 1973. In 1975, the Navy decided to lease a substantial portion of the property, and thus issued a Request for Proposals (RFP) pursuant to 10 U.S.C. § 2667 (1983). After negotiations, the Navy awarded the lease to the defendant, Triple A Machine Shop, Inc., to begin July 1, 1976.
Proposed Article 4 of the Navy’s RFP, entitled “TERM OF LEASE,” provided for a five-year lease term and stated that the lessee would have the right to elect to extend the lease for additional five-year terms. During negotiations, Triple A proposed a different Article 4, which provided that the government would have the option to extend the lease for additional five year terms, with the lessee having a right of first refusal. Triple A explains that it proposed this change because the San Francisco City Assessor told it that the tax consequences for Triple A would be more favorable if the government held the right to elect to renew the lease, rather than Triple A.
The article Triple A proposed was incorporated into the lease signed between the Navy and Triple A as Article 3, “TERM.” Article 3 of the lease stated:
TERM — The term of the lease shall be for a period of five (5) years, commencing on [July 1, 1976]. In the event that the Government elects to lease the Property ... for one or more additional five (5) year terms, at least one hundred twenty (120) days before the expiration of the then current term of the lease the [Navy] will notify the Lessee in writing that the Government so elects.... [I]n the event that the Lessee desires to lease said property for a further five (5) year term, at least ninety (90) days before the expiration of the then current term of the lease the Lessee will give the Government written notice that the Lessee desires to lease the property for such an additional term. Thereafter, the Lessee will negotiate with the [Navy] all the terms and conditions of the leasе for the additional term, including the rent to be paid.
The lease contract thus established a series of possible five-year terms, each succeeding term requiring a separate election and notice by the Navy.
The lease also included a provision for surrender of the property to the Navy at the expiration of the lease term. Article 25 stated:
SURRENDER — At the expiration of the lease, or upon its prior termination, the Lessee shall surrender the leased property and each item thereof in the same condition as when received or in such improved condition as may result from any improvements made by the Government or by the Lessee, with the exception of ordinary wear and tear and loss or damage for which the Lessee is relieved of liability under the lease.
Approximately one year before the first five-year term was due to expire, the Navy and Triple A entered into negotiations fоr a second five-year term. These culminated in the parties entering into a supplemental lease for a second five-year term, to begin July 1, 1981. The supplemental lease added a sentence to Article 3 providing that “[t]he total duration of the lease, including the exercise of all options to renew, shall not extend beyond 30 June 1996.”
Due to changes in the Navy’s requirements, it decided not to extend the lease beyond June 30, 1986. The Navy relied on the lease tеrm entitling it to not elect to renew the lease. Instead, in December 1985, the Navy offered Triple A a new lease for a portion of the originally leased property. Both parties acknowledged that the government’s offer of a new lease was not a notification of its election under the existing lease to continue leasing the entire property for an additional five-year term.
The government filed a “Complaint for Ejectment and Writ of Possession” in the district court. The action was brought in ejectment for possession of the Shipyard in the absence of a lease agreement beyond June 30, 1986, and for damages for the period of Triple A’s use and possession of the Shipyard beyond that date. The government’s complaint asserted, and Triple A’s answer admitted, that (1) the government owns the Shipyard; (2) Triple A and the Navy agreed that the Navy had not elected to lease the property for an additional term beginning July 1, 1986, as was the Navy’s right under Article 3 of the lease; and (3) the parties have not enterеd into a lease agreement governing any period after June 30, 1986.
The government moved for partial summary judgment, seeking an order declaring it entitled to immediate possession of the Shipyard and a permanent injunction barring Triple A from remaining on the property; it reserved the damages question for later.
Triple A made two arguments in response to the government’s motion. First, Triple A contended that what it characterized as a “collateral” agreement existed which created a genuine issue of material fact concerning whether the parties intended Article 3 to constitute their complete and exclusive agreement regarding renewal. In support of this argument, Triple A submitted the affidavits of several persons who had participated in the original lease negotiations on behalf of Triple A or the Navy. In the affidavits, these persons testified that the Navy accepted Triple A’s Article 3 language with bоth parties’ understanding that Triple A would remain at the Shipyard for three additional five-year terms, for a total lease term of twenty years. These persons testified that the Navy did so knowing the favorable tax consequences to Triple A if the government held the exclusive right of election to renew. Triple A asserted that this demonstrated the existence of a collateral agreement that the Navy would elect to renew the lease for three additionаl five-year terms.
Second, Triple A asserted that the court lacked jurisdiction. It contended that the lease renewal issue was subject to the Disputes Clause of the lease, and therefore the government was required to exhaust the administrative procedures established by that clause before bringing suit. The Disputes Clause, Article 33, provides:
[A]ny dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Cоntracting Officer, who shall reduce his decision to writing.... The decision of the Contracting Officer shall be final ... unless, within 30 days ... the Lessee ... furnishes to the Contracting Officer a written appeal addressed to the Secretary [of the Navy]. The decision of the Secretary ... shall be final ... unless determined by a court of competent jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.
On November 19, 1986, the district court granted the government’s motion, holding that there was no dispute about renewal and the parol evidence rule precluded the factual contention concerning the “collateral” agreement. The court found that “[u]nder the plain language of Article 3, the Navy may elect ... not to lease the Shipyard for a further term.... In fact, the Navy did not elect to lease the Shipyard for a further term.” The court also rejected Triple A’s contention that the government was required to exhaust the administrative procedures of the lease’s Disputes Clause prior to bringing suit.
On January 30, 1987, Triple A moved the court to vacate the November 1986 order and to dismiss the government’s complaint
On the same date, Triple A also filed an alternative motion to vacate the November 1986 order on the ground the court erred in applying the California, not federal, parol evidence rule. Triple A asserted that under the federal rule, the evidence offered by Triple A was admissible to show that Article 3 did not represent the complete agreement of the parties regarding leasе renewal.
The district court held a hearing and denied Triple A’s motion. The court found that neither the Disputes Clause of the lease nor the Contract Disputes Act applied and therefore the court had jurisdiction. Concerning the parol evidence rule, the court found: “Following either California or federal law, this court was correct in finding that the lease between Triple ‘A’ and the Government was the complete and full embodiment of their agreement.” Triplе A appeals.
The government and Triple A subsequently entered into a stipulation by which Triple A was obligated to vacate the Shipyard by July 1, 1987, which Triple A has done.
The issue before this court on appeal is whether the dispute as characterized in the government’s complaint arises under the contract, and if it does not, whether Triple A can reshape the dispute in such a way that the district court was required to conclude that the dispute arose under the contract.
STANDARD OF REVIEW
This court reviews de novo questions of subject matter jurisdiction. Charley’s Taxi Radio Dispatch Corp. v. Sida of Hawaii, Inc.,
DISCUSSION
A. Does the Disputes Clause Deprive the District Court of Jurisdiction?
The Disputes Clause at issue here is a standard clause in government procurement contracts. It requires that certain аdministrative review procedures be followed only for a “question of fact arising under this contract.”
Not all disputes between these parties are subject to the contractual requirement that administrative remedies be exhausted; exhaustion is required only for disputes “arising under the contract.” Kyle Eng’g Co. v. Kleppe,
The test to be employed in distinguishing claims within the disputes clause procedure from those outside that procedure “is whether the controversy is fully re-dressable under a provision of the contract other than the disputes clause itself.” Bethlehem Steel Corp. v. Grace Line, Inc.,135 U.S.App.D.C. 81 , 86,416 F.2d 1096 , 1101 (D.C.Cir.1969). In other words, a fact-dispute “arises under the contract” only when the disputed fact is capable of complete resolution by a procedure specified in the contract.
Id. See also United States v. Reisman,
The standаrd disputes clause presupposes an ongoing contractual relationship and applies to disputes for which specific contractual provisions contemplate a remedy. Such clauses do not apply to a dispute that is inconsistent with an ongoing contractual relationship and that is not contemplated by a contract provision. See,
The dispute between Triple A and the government does not arise under the lease contract. No clause in the lease, including the Surrender Clause, governs the situation herе, in which the government has failed to renew the lease. No clause in the lease grants the government a remedy for unauthorized use and possession of the Shipyard beyond the expiration of the lease. The government’s position is that by the plain language of Article 3, the lease has simply expired, it had no obligation to renew the lease, and it is entitled to eject its former lessee. Indeed, the government has clearly and unequivocally taken a pоsition inconsistent with a continuing relationship with Triple A.
Because the dispute is not of the sort contemplated under the Disputes Clause, the government was not required to exhaust administrative remedies prior to bringing this action. Therefore, the Disputes Clause did not deprive the district court of jurisdiction.
B. Does the Contracts Dispute Act Deprive the District Court of Jurisdiction?
The CDA requires administrative review of government claims against a contractor in four specified circumstаnces. 41 U.S.C. § 602, 605. The district court had jurisdiction to determine whether one of those circumstances applies here, and correctly determined none does.
The CDA applies to contracts for:
(1) the procurement of property, other than real property in being;
(2) the procurement of services;
(3) the procurement of construction, alteration, repair or maintenance of real property; or,
(4) the disposal of personal property.
41 U.S.C. § 602(a).
This court has already held that Triple A’s lease with the Navy is not a contract under (2), for the procurement of services. City & County of San Francisco v. United States,
Triple A’s second argument, that the lease should be construed as one for the disposal of personal property because it included various items of equipment, is similarly misguided. This court concluded in City and County of San Francisco, that “the purpose of the transaction was to lease the Hunters Point Naval Shipyard.” Id. at 504. Thus, the court found that “[i]t would distort the essential character of the lease transaction to treat it as a contract for the procurement of services” because
This dispute does not fall within the CDA, and thus the district court had jurisdiction.
C. Did the District Court Improperly Apply the Parol Evidence Rule?
Triple A contends the district court’s injunction was based on the erroneous conclusion that the lease contract constituted the complete and final agreement between the parties. Triple A argues that the district court erred in not admitting parol evidence offered by Triple A which allegedly would have shown the existence of a collateral agreement between the parties. Triple A alleges that under this collateral agreement, the Navy agreed, at the time the original contract was negotiated, to elect to renew the lease after each five-year term, for a total of twenty years.
Both parties agree that federal law governs the interpretation of a government lease contract, including issues of parol evidence. Contracts to which the federal government is a party, and into which the government enters pursuant to federal law, are generally governed by federal law. United States v. County of Allegheny,
In denying Triple A’s motion to vacate the injunction, the district court properly applied the parol evidence rule as it has been developed under federal common law. See, e.g., Sylvania Elec. Prod., Inc. v. United States,
The district court did not abuse its discretion in refusing to admit the parol evidence and issuing the injunction.
CONCLUSION
We hold that the dispute as presented by the government’s ejectment action does not arise under the contract. Neither contention of the defendant reshapes the dispute so that it does. The district court had
AFFIRMED.
Notes
. This is consistent with California case law on ejectment. In Paap v. Von Helmholt,
. The case of Forman v. United States,
Concurrence Opinion
concurring:
I concur in the majority’s opinion. I write separately, however, in order to clarify the basis for my concurrence in section A, the part of the opinion that discusses the disputes clause.
Notwithstanding the broad language of the standard disputes clause,
When a contracting party’s claim and the remedy it seeks are both covered by a substantive clause, the cases are clear: the party must exhaust the remedies set forth in the disputes clause before filing a suit. See, e.g., Crown Coat Front Co. v. United States,
The question the cases do not squarely answer is whether a party must exhaust its remedies under the disputes clause if its claim is covered by a substantive clause but the remedy the party seeks is not — for example, where the contrаct offers only adjustment in payment as a remedy for government delay, but the party argues that the delay was so severe that the appropriate remedy is rescission or termination. Cf. Reisman,
. See, e.g., United. States v. Reisman,
