Opinion for the Court filed by Circuit Judge ROGERS.
This case is before the court for a second time. In the first appeal, the court reversed in part the grant of summary judgment to TDC Management Corporation, Inc. and its president, Theodore Monts. The court held that the decision of the Department of Transportation Board of Contract Appeals (“the Board”) on TDC’s appeal from cost disallowances collaterally estopped the government from relitigating the accuracy of TDC’s monthly progress and expenditure reports, but did not estop the government from bringing False Claims Act charges based on information that was omitted from those reports. Un
ited States v. TDC Mgmt. Corp.,
I.
The background to this appeal appears in
TDC I.
Suffice it to say, the litigation arose in connection with a Demonstration Bonding Program (“Program”) of the Urban Mass Transit Authority (“UMTA”) of the Department of Transportation. The Program was designed to assist minority enterprises in securing bonding from sure
*423
ties when bidding on large transportation construction projects.
TDC I,
When the Program failed to progress as expected, UMTA terminated the contract for convenience and disallowed nearly half of TDC’s claimed contract-related expenses, which totaled $928,916.
Id.
at 296. TDC appealed to the Board. Before the Board rendered its decision, the United States in May 1989 sued TDC under the False Claims Act, 31 U.S.C. § 3729 (1982), for misrepresenting its actual progress in its monthly reports to UMTA and concealing deviations from the Program terms.
Id.
The Board ruled in TDC’s favor and reversed the disallowances, finding that TDC had not breached the contract for nonperformance and that its monthly reports had notified UMTA of the categories and types of expenses that UMTA sought to disallow.
Id.
Viewing its jurisdiction under the Contract Dispute Act, 41 U.S.C. § 605, as limited to the costs that had been disallowed by the contracting officer, the Board declined to consider UMTA’s claim that TDC was not entitled to any monies under the contract due to fraudulent omissions.
Id.
at 295. The Board’s decision was affirmed by the United States Court of Appeals for the Federal Circuit.
Skinner v. TDC Mgmt. Corp.,
Based on the collateral estoppel effect of the Board’s findings, TDC moved on April 19, 1991, for summary judgment on the False Claims Act charges.
TDC I,
II.
On appeal, TDC challenges the grant of summary judgment on several grounds, only one of which requires extended discussion. That contention is that the district court relied on an erroneous application of the doctrine of collateral estoppel.
A.
On remand, the district court ruled that collateral estoppel prevented TDC from relitigating factual issues decided by the Board with regard to omissions in TDC’s monthly reports because “the issue of omissions was squarely addressed by the Board in its prior review of the contract termination.” Remand Opinion at 7. Relying on the Board’s findings, the district court concluded there were no genuine issues of fact with regard to the alleged omissions. Id. at 14. The district court recited at length the Board’s findings that TDC had departed from the terms of the Program by, inter alia: (1) planning to use interest generated by short-term investment of the UMTA contribution to underwrite the costs of providing services to disadvantaged business enterprises; (2) *424 proposing to investors that such businesses be charged a 3% fee for management services; and (3) intentionally failing to disclose to UMTA its plans to hold a financial stake in Program operations in order to keep UMTA from learning of activities that it would insist be terminated; and that with such investment TDC could no longer act objectively as ombudsman for the Program. On the basis of the Board’s findings, the district court concluded that the omissions were either intentional or resulted from reckless disregard of the Program terms, causing the monthly reports submitted by TDC in support of its invoices for payment to be false. In granting summary judgment to the government on liability, the district court also relied on the unrebutted declarations of UMTA officials, including that of UMTA Administrator Ralph L. Stanley stating that had he known that TDC or Monts tried to obtain an equity stake or other financial interest in the Program, he would have directed that the contract be immediately terminated for cause. The district court thus found that the omissions were material because had UMTA known of the omitted information, it would have either required TDC to cease those activities or terminated the contract for cause. Id. at 15.
In
TDC I,
this court explained that a party is not collaterally estopped from relitigating a disputed issue of fact unless that issue “was actually litigated and necessarily decided by a final disposition on the merits.”
In
TDC I,
this court stated that the Board “expressly reserved for the district court the legal determination of whether TDC’s failure to report its financial stake in Program operations constituted fraud,” and that “[i]n disposing of TDC’s contract claim, the Board made no necessary findings about UMTA’s reliance on TDC’s reports.”
TDC I,
B.
The question remains whether this court should exercise its discretion to consider TDC’s contention notwithstanding its waiver. In
District of Columbia v. Air Florida,
This court thus acknowledged in
Air Florida
that in “exceptional circumstances,
*426
where injustice might otherwise result, we have the discretion to consider questions of law that were neither raised below nor passed upon by the District Court.”
TDC accordingly asserts in its brief that “[sjomething went horribly 'wrong here to turn this case upside down from [the] point” where TDC prevailed before the Board, and “it is up to this Court to correct that wrong.” Appellant’s Br. at 16. In support of its position, TDC makes two arguments why this court should address its collateral estoppel contention: first, the issue is purely a question of law subject to de novo review; and second, “the district court’s error was plain — if not egregious,” as the overwhelming weight of authority demonstrates that collateral estoppel operates in only one direction. Reply Br. at 14. However, these reasons sweep far too broadly and address only some of the relevant considerations. Neither of TDC’s arguments necessarily demonstrates that a manifest injustice will occur unless this court addresses the “necessity” of the Board’s findings to its holding and remands the case for a trial. Although TDC’s counsel may have failed to alert the district court to an obvious error, we decline to exercise our discretion for three reasons.
First, culpability. The False Claims Act complaint alleged that TDC’s reports overstated its progress and failed to disclose that, contrary to the Program terms, TDC sought to obtain a financial interest in Program operations.
See TDC I,
Second, prejudice to the government. The considerable delay in this litigation creates problems with regard to witnesses’ memories and document retention regarding events that occurred almost two decades ago. These problems would presumably affect both parties at a trial. But they are exacerbated for the government, for at oral argument the parties informed the court of the death of Ralph L. Stanley. Stanley’s term as UMTA Administrator, from November 21, 1983 to May 31, 1987, spanned the period just after the Program’s inception in July 1983 until its termination in April 1985. He was directly in charge of what he described in his April 1996 declaration as a “high priority project,” and he claimed in his declaration that he first learned at meetings with Monts and TDC’s legal consultant in December 1984 and January 1985 that TDC was deviating from the Program in significant ways. Although other UMTA officials were involved in the management of the Program, Stanley was the person in charge and, due to his death, there would be obvious prejudice to the government at a trial.
Third, TDC recovered its contract costs. Pursuant to the Board’s decision, TDC recovered $778,613 of the $928,916 that it claimed over the life of the contract as “allowable, allocable, and reasonable” costs associated with its work on the Program.
TDC I,
In sum, in light of the undisputed record evidence of TDC’s culpability, the prejudice to the government, and TDC’s recovery of its contract costs, remanding for a trial would simply prolong the closure date of this litigation without, in all likelihood, advancing the interests of either party. Accordingly, we decline to exercise our discretion to address the collateral estop-pel contention that TDC waived.
III.
We address briefly TDC’s two other contentions, regarding damages and Monts’ liability.
A.
TDC contends that in light of the Board’s ruling, the government’s net damages were zero because it “got what it paid for” under the “best efforts” agreement. TDC further contends that the government failed to prove that TDC proximately caused its damages because it may have *428 terminated the contract for reasons unrelated to the omissions in the progress reports, and that at the very least, an evi-dentiary hearing into the causation issue was required. These claims are meritless.
The Supreme Court pointed out long ago that “the chief purpose of the statutes [which formed the basis for the False Claims Act] ... was to provide for restitution to the government of the money taken from it by fraud, and that the device of double damages plus a specific sum was chosen to make sure that the government would be made completely whole.”
United States ex rel. Marcus v. Hess,
TDC’s contention that the government terminated the contract for convenience and failed to prove that TDC’s omissions proximately caused its damages is also unavailing. UMTA initially terminated the contract for convenience but changed this to a termination for cause after learning about the omissions in TDC’s progress reports. No court has ever found the termination for cause to be unwarranted. Further, TDC failed to rebut the declarations of UMTA officials that UMTA relied on TDC’s monthly reports and would not have continued to make payments on TDC’s vouchers but for the omissions. TDC’s alternative contention that the district court erroneously characterized the question of materiality by failing to ask whether UMTA officials would have acted differently if the omitted information had been included in the reports, as opposed to whether they knew of such information, was not raised in the district court and is not properly before this court.
See Air Florida,
B.
Finally, TDC’s contention that the district court improperly extended the judgment to include Monts as a defendant
*429
is frivolous. The government sued both TDC and Monts as named defendants.
TDC I,
Accordingly, we affirm the grant of summary judgment to the government.
