MEMORANDUM OPINION and ORDER
I. INTRODUCTION
This case traces its ultimate origins to the inauspicious beginnings of George Washington’s military command. Washington, then a twenty-two year old Lieutenant Colonel, led almost four hundred Colonials and British regulars in the Battle of the Great Meadows on July 3,1754. Sent at the behest of General Dinwiddie to clear a road through the forests around present-day Pittsburgh, thereby facilitating the movement of men and materiel to the Ohio River, the force came into contact with six hundred French troops commanded by Capt. Louis Coulon de Villiers. After inclement weather swamped his hastily prepared fortifications and rendered most of his powder useless, Washington negotiated a truce that allowed the peaceful withdrawal of his men. The French occupied and eventually razed the Colonials’ encampment, which had been christened with the somewhat baleful, if perhaps appropriate, name of Fort Necessity. The first significant engagеment of the French and Indian War was thus also Washington’s first and only surrender.
Today, the Fort Necessity National Battlefield is located outside Farmington, Pennsylvania. In 2003, the National Park Service entered into a contract with MCDS, Inc. (“MCDS,” “Movant,” or “Applicant”) for the construction of the Fort Necessity/Nationa! Road Interpretive and Education Center (“the Project”). Because the value of the contract exceeded $100,000, the Miller Act, 40 U.S.C. § 3131, et seq.,
As the general contractor on the Project, MCDS subsequently executed a subcontract (“the Subcontract”) with the Frank M. Sheeslеy Co. (“FMS” or “Plaintiff’), under which the latter agreed to perform various duties at the work site, including demolition, clearing and grubbing, paving excavation, and concrete construction. Under f 17 of the Subcontract, “[a]ll disputes between the Contractor and Subcontractor ... shall, at the contractor’s sole option, be resolved by arbitration in accordance with the rules of the American Arbitration Association.” Document 17, Exh. 1, p. 6.
According to MCDS, FMS “did not complete its work on the Project. In fact, in order to complete the Project, MCDS requested that [FMS] return to the site to finish its incomplete work.” Brief in Support of Motion to Intervene (Document No. 17), p. 2 n. 1. By not cooperating, Plaintiff allegedly forced MCDS to hire another firm for the work FMS contracted to perform. Id. For its part, FMS contends that “MCDS directed [it] to perform a substantial amount of additional work outside the scope of the Subcontract” and that it “successfully completed all of its work and additional work on the project.” Brief in Opposition to the Motion to Intervene (Document No. 22), p. 2. Though FMS submitted invoices to MCDS in the
On August 23, 2006, MCDS therefore filed two motions with this Court. In the first, it seeks to intervene in FMS’ suit under Fed. R. Civ. P. 24. Document No. 16. It asserts a right to do so under Rule 24(a), and, in the event the Court finds otherwise, asks for permissive intervention under Rule 24(b). Assuming the Court will allow intervention, MCDS requests in its second motion the enforcement of the Subcontract’s arbitration clause. Movant therefore asks for a stay in this litigation and for an order compelling FMS to arbitrate its grievances. Document No. 20. For the reasons set forth in this Memorandum Opinion, both motions are granted.
II. THE MOTIONS TO INTERVENE
A. Standards
An applicant for intervention must first comply with the рrocedural requirements set forth in Fed. R. Civ. P. 24(c), which provides: “A person desiring to intervene shall serve a motion to intervene ____ [that] state[s] the grounds therefor and [is] accompanied by a pleading setting forth the claim or defense for which intervention is sought.” Despite the compulsory language of the rule, some federal circuits have held that whether “to permit a procedurally defective motion to intervene is within the sound discretion of the district court.” Retired Chi. Police Ass’n v. City of Chicago,
Assuming no procedural deficiency fatally undermines an applicant’s motion, Fed. R. Civ. P. 24(a) provides for intervention as a matter of right in twо circumstances: first, when unconditionally permitted by a federal statute; or second, under Rule 24(a)(2), “when the applicant claims an interest relating to the property or transaction which is the subject of the action and he is so situated that the disposition of the action may as a practical matter impair or impede his ability to protect that interest____” In the latter case, however, an existing party’s representation of the purported interest can create an exception, and the applicant has no right to intervention where his proprietary interest is already being adequately defended. As MCDS makes no claim that a federal statute supports the motion sub judice, any right to intervene must arise under subsection (a)(2).
In the Third Circuit,
a non-party is permitted to intervene under Fed. R. Civ. P. 24(a)(2) only if: (1) the application for intervention is timely; (2) the applicant has a sufficient interest in the litigation; (3) the interest may be affected or impaired, as a practical matter by the disposition of the action; and (4) the interest is not adequately represented by an existing party in the litigation.
Mountain Top Condo. Ass’n v. Dave Stabbert Master Builder, Inc.,
The third prong requires that the Court surmise the practical effects on the lawsuit of the grant or denial of the applicant’s motion. Dev. Fin. Corp. v. Alpha Hous. & Health Care,
Finally, the “burden ... is on the applicant for intervention to show that his interests are not adequately represented by the existing parties.” Brody,
If unable to satisfy these four independent requirements, a proposed intervenor may instead petition for permissive intervention under Rule 24(b). Such a motion requires only that the Court find a sufficient commonality of law or facts between the applicant’s claim and the main action.
B. MCDS’ Procedural Deficiency
Plaintiff first requests summary dismissal of MCDS’ Motion to Intervene on the ground that Movant has not filed “a pleading setting forth the claim or defense for which intervention is sought.” Document No. 22, pp. 3-4. While MCDS did attach a copy of its Motion to Stay Proceedings and Compel Arbitration as Exhibit A to its Motion to Intervene, FMS cites the narrow definition of “pleading” found in Fed. R. Civ. P. 7(a)
In a subsequent case, the Third Circuit held that the unique circumstances of a particular lawsuit compelled reversal of the lower court’s dismissal of a motion to intervene as untimely. In remanding the case for consideration of other intervention factors, however, the court suggested alternative grounds for denying the motion: the applicant’s “failure to comply with the procedural requirements of Rule 24(c).” Bank of Am. Nat’l Trust & Sav. Ass’n v. Hotel Rittenhouse Assocs.,
Accordingly, trial courts in this circuit have generally not considered their discretionary powers before dismissing motions to intervene for procedural inadequacies. See, . e.g., Gaskin v. Pennsylvania,
However, even among courts adhering to this more strict reading of Rule 24, it is rare that only procedural grounds are proffered for denial. “In those cases in which a stern attitude has been taken toward procedural mistakes it is noteworthy that ... the court also has discussed reasons of substance why intervention should not be allowed.” Charles Alan Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure § 1914, p. 414-15 (2d ed.1986). Indeed, of the cases cited above, in only two—School District and Ryer—were the dismissals wholly stated on procedural grounds.
The Court also notes that the federal circuits have carved a nearly unanimous exception to the express requirements of Rule 24 in the context of confidentiality orders. In such cases, the proposed intervenors do not seek to become a party to the litigation, “but simply want[] access to materials gathered or prepared by the original parties in the course of their litigation.” EEOC v. Nat’l Children’s Ctr.,
Even on this issue, however, the Third Circuit has demonstrated less willingness to dispense with Rule 24’s express requirements. Rather than hold that intervenors wishing to attack confidentiality orders need not demonstrate the commonality of Rule 24(b), the court has instead decided as a matter of law that such circumstances legally satisfy the Rule’s commonality requirement: “By virtue of the fact that the [intervenors] challenge the validity of [an] Order of Confidentiality ... they meet the requirement of Fed. R. Civ. P. 24(b)(2) that their claim must have ‘a question of law or fact in common’ with the main action.” Pansy v. Borough of Stroudsburg,
It is this kind of flexibility that has prompted other circuits to review procedural dismissals of motions to intervene for abuse of discretion. The prevailing approach among the courts that have considered the question is reflected in the Seventh Circuit’s conclusion that “if no prejudice would result, a district court has the discretion to accept a procedurally defective motion.” Retired Chi. Police Ass’n v. City of Chicago,
This wealth of case law demonstrates that the waiver of procedural defects in intervention attempts is often prompted by the merits of the motion itself,
In respect to this last consideration, it is also noteworthy that MCDS does not seek to intervene for the purpose of advancing its own claims against an existing party, but to compel the arbitration to which it contends FMS is obliged to resort. Thus, to insist that Applicant accompany its Motion to Intervene with a proper pleading would be to command that MCDS needlessly expend resources. It would not help efficiently resolve the dispute sub judice to require that MCDS file a third-party complaint so that it may immediately seek a stay of its claims in favor of the arbitration proceedings for which it intervened in the first place. To the extent that judicial economy is a consideration in intervention analysis,
The Court thus finds that it has the authority to employ its discretion and consider a motion to intervene that contains no pleading, but instead includes a motion to compel arbitration and stay the proceedings. Accordingly, the procedural mandate of Rule 24(c) does not undercut MCDS’ Motion to Intervene, and the Court now proceeds to the merits of that motion.
C. MCDS’24(a) Claim
As discussed, MCDS has adеquately complied with Rule 24(c). Furthermore, the Bond that the Sureties issued represents the kind of specific fund that can ground a legitimate interest for Rule 24(a)(2) purposes. Mountain Top Condo. Ass’n v. Dave Stabbert Master Builder,
Few of MCDS’ arguments about Rule 24(a) intervention squarely address either of these questions. According to applicant, “Sheesley’s dispute is with MCDS, not the sureties,” “[discovery would certainly involve MCDS,” and “permitting intervention will promote judicial efficiency.” Document No. 17, pp. 4-5. MCDS also argues that intervention as of right is justified by both the possibility of a future indemnification action against MCDS and the federal policy favoring arbitration, which will be furthered if the Court grants both the Motion to Intervene and the Motion to Compel Arbitration. Id. at 5. These arguments seem more tailored to Applicant’s Rule 24(b) motion and do little to demonstrate the impairment or inadequate representation that denial of MCDS’ 24(a) motion will effect. Deciding Movant’s right to intervene, the Court need not address the potential impairment to MCDS’ interest, for
“The requirement of [Rule 24(a) ] is satisfied if the applicant shows that representation of his interest ‘may be’ inadequate; and the burden of making that showing should be treated as minimal.” Trbovich v. United Mine Workers,
when the party seeking intervention has the same ultimate objective as a party to the suit, a presumption arises that its interests are adequately represented. To overcome the presumption of adequate representation, the proposed intervenor must ordinarily demonstrate adversity of interest, collusion, or nonfeasance on the part of a party to the suit.
In re Cmty. Bank of N. Va. & Guar. Natl Bank of Tallahassee Second Mortgage Loan Litig.,
By asserting that Plaintiffs suit against the sureties is actually a suit against MCDS, Applicant concedes that its interests are aligned with those of Defendants; the Court finds that it would be disingenuous to conclude otherwise. It is not certain that the Sureties are entitled to indemnification from MCDS in the event that a Subcontractor recovers on the Bond,
In the Third Circuit, “complete identity of interest and legal representation between [a potential intervenor] and [an existing party] insures that the [former’s] interests will be аdequately represented.” McClune v. Shamah,
MCDS has made no contention that the Sureties’ interests are different from its own, that the Sureties are somehow in collusion with FMS, or that Defendants аre not vigorously litigating Applicant’s defenses. In short, Movant has made no effort to satisfy the requirements stipulated in Third Circuit caselaw. The Court therefore finds that the Sureties are adequately defending against any recovery that FMS might achieve against the Bond, and that MCDS cannot intervene as a matter of right.
This conclusion is buttressed by the findings of another district court, which addressed a factually similar case. The Southern District of New York held that when a surety is bound to defend against claims to a bonded amount by subcontractors under the Miller Act, then the general contractor to whom the bond was issued cannot claim that its interests are inadequately represented for Rule 24(a) purposes. Union Switch & Signal, Inc. v. St. Paul Fire & Marine Ins. Co.,
D. MCDS’24(b) Claim
As stated above, an applicant may intervene under Rule 24(b) at the Court’s discretion if a sufficient commonality of law or facts underlie the applicant’s claim and the main action. Harris v. Pernsley,
The Court first notes that MCDS’ arguments for rightful intervention possess considerably greater traction under Rule 24(b), which is expressly more concerned with consolidating common legal or factual issues than with protecting the implicated rights of a non-party. According to MCDS, its disputes with FMS “quite obviously share common questions of law and fact. In fact, the very same questions of law and faсt that would be litigated in this action on the bond would be involved in the ... arbitration” that Applicant hopes to compel. Document No. 17, p. 6. Permissive intervention would therefore “promote judicial efficiency, prevent multiple actions, and permit the Court to ... promot[e] the strong federal policy in favor of arbitration____” Id. In opposition, FMS reiterates that Applicant’s interests are identical to those of the Sureties and are being adequately represented by the counsel that the three entities share. Document No. 22, p. 9. Moreover, Plaintiff claims that “the dilatory intent of the sureties and MCDS is clear. The obvious intent of both the sureties and MCDS is to stay this matter pending arbitration____” Id.
The Court agrees with Applicant that a plethora of questions to be raised in a potential arbitration proceeding are common with the issues in the main breach-of-contract action. Both the breach-of-contract claim pleaded in FMS’ Complaint and any cross-claim MCDS could raise in arbitration share the same factual history. Identical questions will also ground the defenses available in this Court and the claims that Applicant may bring before an arbitrator: The extent to which FMS fulfilled its contractual
Rather than have different tribunals examine these issues at different times, notions of judicial economy suggest aggregating them in a single proceeding. Brody v. Spang,
While it is true that MCDS seeks to stay this proceeding altogether, it is not clear that the stay, if granted, would delay the resolution of FMS’ claims. Compelling the arbitration procedures that Plaintiff agreed to could have the opposite effect, since the “policy favoring arbitration ... [can] achieve the twin goals of ... settling disputes efficiently and avoiding long and expensive litigation.” Remmey v. PaineWebber, Inc.,
The Court notes that in a factually similar case, a court in the Southern District of New
III. The Motion to Stay and Compel
As a newly-intervened defendant in this case, MCDS’ first action is its Motion to Compel Arbitration and Stay Proceedings Pending Arbitration (Document No. 20), in support of which it argues that the arbitration clause in the Subcontract is valid, irrevocable, and enforceable under the Federal Arbitration Act (“FAA”), 9 U.S.C. § 1, et seq. Brief in Support of Motion to Compel Arbitration and Stay Action Pending Arbitrations (Document No. 19), p. 3. MCDS therefore asks the Court to stay these proceedings and compel the arbitral processes to which the parties are bound. Movant does not expressly seeks a stay of FMS’ claims against both it and the Sureties, but only requests that the Court stay “the current action.” Document No. 19, pp. 4-5. Though the Court surmises from the language of the Motion sub judice and from the precedent MCDS cites that Movant requests a stay in the entire case— including FMS’ claims against the Sureties— it notes that at least one federal court has allowed a Miller Act suit to proceed against a surety while simultaneously compelling the subcontractor to arbitrate its claims against the bond principal. United States ex rel. Pensacola Constr. Co. v. St. Paul Fire & Marine Ins. Co.,
FMS does not contend that the arbitration clause is invalid or that any dispute between it and MCDS is not subject to mandatory arbitration under the FAA. Plaintiff instead argues that its claims against the Sureties are not governed by any arbitration clause and that the Motion to Stay is merely an attempt to delay the proceedings and attrite FMS’ resources:
MCDS ignores the fact that the sureties are not signatories to the arbitration agreement and are, therefore, neither obligated to participate in, nor bound by the results of, any arbitration proceeding. Thus, if MCDS’ Motion is granted, FMS will have to expend cоnsiderable time and resources arbitrating its claim against MCDS, only to be faced with the prospect that even if successful, FMS will be unable to collect a judgment from MCDS. And certainly, when FMS turns to the surety with a copy of the arbitrator’s decision in hand, the sureties will disclaim liability arguing that as a non-signatory to the arbitration agreements, the sureties are not bound by the decision of the arbitrator. See AT & T Tech., Inc. v. Commc’ns Workers of Am.,475 U.S. 643 , 648[,106 S.Ct. 1415 ,89 L.Ed.2d 648 ] (1986).
Brief in Opposition to the Motion to Compel and Stay (Document No. 24), p 6. FMS therefore asks that the Court not stay its claims against the Sureties, even if FMS is compelled to arbitrate any dispute with Mov-ant. Id. at 4-8.
The Subcontract between FMS and MCDS states that “[a]ll disputes between the Contractor and Subcontractor ... shall, at the contractor’s sole option, be resolved by arbitration in accordance with the rules of the American Arbitration Association.” Exh. 1 to Document No. 20, p. 6, H17. According to the FAA, a “written provision ... to settle by arbitration a controversy thereafter arising out of such contract ... shall be valid, irrevocable, and enforceable.” 9 U.S.C. § 2. Furthermore,
If any suit or proceeding be brought ... upon any issue referable to arbitration under an agreement in writing for such arbi*417 tration, the court ... shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement. ...
9 U.S.C. § 3. “If one of the parties fails to comply with [an arbitration] agreement, a court may order ‘the parties to proceed to arbitration in accordance with the terms of the agreement.’ ” In re Mintze,
The Court finds, however, that the FAA does not compel FMS to arbitrate its claims against the Sureties, who never adopted the terms of the Subcontract and did not enter a separate arbitration agreement with Plaintiff. But regardless of whether MCDS also seeks a stay of FMS’ action against the Sureties, the Court may issue such a stay at its own discretion. Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp.,
Plaintiff is concerned that it will be forced to proceed in separate actions to secure its payment under the Bond. First it will have to arbitrate MCDS’ liability for the unpaid work FMS performed, then it will have to execute that judgment against the sureties, who will not be bound by any arbitral award against MCDS and who can be expected to assert all defenses already advanced by MCDS. Plaintiffs fear is justified by the Fifth Circuit’s holding that a surety is not bound to judgments against its principal “when the [subcontractor’s] recovery depends upon a Miller Act bond.” United States Fidelity & Guaranty Co. v. Hendry Corp.,
The Court finds, however, that Hendry has not enjoyed considerable influence over the circuits that subsequently addressed this issue. The Sixth Circuit reviewed de novo a subcontractor’s attempt to collect an arbitration award from a Miller Act surety and
The court relied in part on the Ninth Circuit’s holding that “a surety on a Miller Act subcontract was bound by an arbitration decision later ratified by a state court, even though it ‘was not a named party in the arbitration and made no appearances.’ ” Id. (quoting United States ex rel. Aurora Painting, Inc. v. Fireman’s Fund Ins. Co.,
Because [the surety’s] liability is merely derivative, its interests are nearly identical [to those of the general contractor]. [The surety] had actual notice of the state court action against [the general contractor], tendered its defense to [the general contractor], and used the same counsel as [the general contractor]. The surety cannot now complain that it was inadequately represented by [the general contractor’s] defense.
Aurora,
Similarly, the Eleventh Circuit bound a surety to a default judgment levied against the principal in a Miller Act suit in which both the surety and the principal were named as defendants. Drill South, Inc. v. Int’l Fid. Ins. Co.,
The Court can find no indication that the Third Circuit has addressed whether a surety is bound by an arbitrator’s decision against a principal. However, the caselaw suggests that courts in this circuit trend toward the majority view. The Third Circuit held that an arbitrator’s decision was binding against a non-party whose interests were “directly related, if not in fact congruent” to those of a party in the arbitration proceeding. Isidor Paiewonsky Assocs., Inc. v. Sharp Properties, Inc.,
Applying Isidor in an unpublished decision, the Middle District of Pennsylvania recently found that a Miller Act surety could move to vacate an arbitration award against its principal, even though the surety was not a party to the arbitration proceeding. Westra
The record in this case indicates both that FMS has attempted to include the Sureties in any arbitration with MCDS and that the Sureties have declined the offer. See Document No. 22, Exh. C. Additionally, the Sureties and MCDS share counsel. Id. That the Sureties have been served with Plaintiffs Complaint and Applicant’s motions also demonstrates their notice of the dispute. The Court is thus confident that a stay of FMS’ claim against the Sureties will not force Plaintiff to relitigate issues decided in the arbitration proceeding. For these reasons, judicial economy impels the discretion of this Court to find that this matter should be stayed in its entirety, pending the outcome of the arbitration proceeding that FMS is hereby compelled to initiate against MCDS.
IV. CONCLUSION
For the reasons stated in this Memorandum Opinion, the Court hereby grants MCDS’ motion to intervene pursuant to Fed. R. Civ. P. 24(b)(2). Finding that the Federal Arbitration Act requires the Court to stay FMS’ suit against MCDS and compel thе arbitration of those claims, the Court also concludes that a stay in FMS’ case against the Sureties will give the most effect to the principles behind the Federal Arbitration Act without prejudicing Plaintiff or winnowing the protection that the Miller Act affords subcontractors. An appropriate Order follows.
AND NOW, this 7th day of November, 2006, IT IS HEREBY ORDERED that MCDS, Inc.’s Motion to Intervene Pursuant to Federal Rule of Civil Procedure 24 (Document No. 16) is GRANTED. MCDS is therefore allowed to enter this lawsuit as an Intervening Defendant.
IT IS FURTHER ORDERED that Intervening-Defendant MCDS, Inc.’s Motion to Compel Arbitration and Stay Action Pending Arbitration (Document No. 20) is GRANTED. Accordingly, this lawsuit is STAYED in its entirety and Plaintiff must resort to the arbitration proceedings to which it agreed in its subcontract with MCDS, Inc. for resolution of the claims in this lawsuit.
Notes
. For more on the colonial military history of Western Pennsylvania, see Charles Morse Stotz, Outposts Of The War For Empire. The French And English In Western Pennsylvania. Their Armies, Their Forts, Their People 1749-1764 (2005). For more on the life of George Washington, please reference the work of Douglas S. Freeman.
. The Miller Act provides: "Before any contract of more than $ 100,000 is awarded for the construction ... of any public building ... a person must furnish to the Government .... [a] payment bond with a surety ... for the protection of all persons supplying labor and material in carrying out the work provided for in the contract. ...” 40 U.S.C. i 3131(b)(2).
. "Upon timely application anyone may be permitted to intervene in an action .... when an applicant's claim or defense and the main action have a question of law or fact in common.” Fed. R. Civ. P. 24(b)(2).
. Fed. R. Civ. P. states as follows:
Pleadings, (a) There shall be a complaint and an answer; a reply to a counterclaim denom-mated as such; an answer to a cross-claim, if the answer contains a cross-claim; a third-party complaint, if a person who was not an original party is summoned under the provisions of Rule 14; and a third-party answer, if a third-party complaint is sеrved. No other pleading shall be allowed, except that the court may order a reply to an answer or a third-party answer.
. See Retired Chi. Police Ass’n,
. See, e.g., Providence Baptist Church,
. Id.
. See infra Section II.D.
. There is no dispute regarding the timeliness of MCDS’ Motion to Intervene. "Timeliness of an intervention request is determined by the totality of the circumstances. Among the factors to be considered are: (1) the stage of the proceeding; (2) the prejudice that delay may cause the parties; and (3) the reason for the delay." In re Cmty. Bank of N. Va. & Guar. Nat’l Bank of Tallahassee Second Mortgage Loan Litig.,
. Though MCDS contends that there is an indemnity agreement. Document No. 17, p. 2, none has been put on the record. Moreover, even if there is such an agreement, MCDS could still refuse to indemnify the Sureties in certain situations. United States ex rel. MPA Constr., Inc. v. XL Specialty Ins. Co.,
. This section adopts the timeliness and procedural analyses already set forth.
. The court found that the “precedential effect of [Hendry] has been weakened” by Supreme Court caselaw not relevant here. Pensacola,
. According to 28 U.S.C. § 1738, "The records and judicial proceedings of any court .... shall have the same full faith and credit in every court within the United States."
. The Skip Kirchdorfer, Aurora Painting, and Drill South courts all cited the applicable state law regarding surety liability to support their conclusions. None held, however, that this was a state-law issue, and each court premised its result primarily on federal law. In this case, the Court has before it a Pennsylvania plaintiff, a Colorado intervenor, and defendant sureties from Virginia and Maryland. No party has raised the issue of the applicable state law, and the Court expresses no opinion in that regard.
. 9 U.S.C. § 11 (allowing a district court to "modify[] or correctf] the award upon the application of any party to the arbitration”) (emphasis added).
