UNITED STATES v. SECKINGER, TRADING AS M. O. SECKINGER CO.
No. 395
Supreme Court of the United States
March 9, 1970
Argued January 14, 1970
397 U.S. 203
John G. Kennedy argued the cause for respondent. With him on the brief was Frank S. Cheatham, Jr.
This case concerns the construction of a provision common to fixed-price government construction contracts that states that the private contractor “shall be responsible for all damages to persons or property that occur as a result of his fault or negligence....” The Court of Appeals for the Fifth Circuit held that the provision could not be construed to allow the Government to recover from the contractor damages suffered by the Government on account of its own negligence. 408 F. 2d 146 (1969). We granted certiorari because of the large amount of litigation that this contract clause has produced1 and because of the divergent results that the lower courts have reached in construing the same or similar provisions.2 396 U. S. 815 (1969). We reverse.
I
The United States had entered into a contract with the Seckinger Company for the performance of certain plumbing work at a United States Marine base in South Carolina. While working on this project, one of Seckinger‘s employees was directed by his foreman to assist a fellow employee on a particular section of pipe that had been partially constructed above a street. About four or five feet above the place where the employee was working, there was an electric wire that carried 2,400 volts of electricity. The employee accidentally
The injured employee recovered benefits under South Carolina‘s workmen‘s compensation law,
On the merits, the South Carolina District Court found that the United States had customarily de-energized its electric wires whenever Seckinger employees were required to work dangerously near them. The court therefore held that the United States had been grossly negligent in failing to de-energize the wire in this particular case. Alternatively, the Government was held to have been negligent in failing to advise Seckinger‘s employees that the electric wire had not been de-energized. Concluding also that the employee had in no way contributed to his injury, the District Judge orderеd that he recover a judgment against the United States in the amount of $45,000 plus costs. No appeal was taken from this judgment of the District Court.4
Thereafter, the United States proceeded to the District Court for the Southern District of Georgia and commenced the instant suit against Seckinger. The complaint alleged that Seckinger‘s negligence was solely responsible for its employee‘s injuries5 and that therefore the United States should be fully indemnified for the judgment which it had satisfied. In a second count, the Government alleged that Seckinger, having undertaken to perform its contract with the United States, was obligated “to perform the work properly and safely and to provide workmanlike service in the performance of said work.”
The District Court granted Seckinger‘s motion to dismiss the complaint on the alternative grounds, first, that the suit was barred by the prior litigation in South Carolina and, second, that the contractual language was not sufficiently broad to permit the Government to recover indemnification for its own negligence. The Court of Appeals rejected the first ground of decision,6 but sus-
In the Government‘s view, this construction of the clause renders it a nullity, for the United States can never be held liable in tort under the Tort Claims Act or otherwise in the absence of negligence on the part of its agents. Thus, so the argument goes, the contractual provision in question can have meaning only in a context in which both the United States and the contractor are jointly negligent.8 In that circumstance, the contractor would be obligated to sustain the full burden of ultimate liability for the injuries produced. Alternatively, the Government suggests that it is en-
II
In the posture in which this case reaches us, the historical background of the clause9 and evidence concerning the actual intention of these particular parties with respect to that provision are sparsely presented. We do know that the clause was required in government fixed-price construction contracts as early as 1938.10 This fact merely precipitates confusion, however, because it was not until the passage of the Tort Claims Act in 1946, §§ 401-424, 60 Stat. 842, as amended,
In American Stevedores, Inc. v. Porello, 330 U. S. 446 (1947), we had before us a contractual рrovision that was similar to that involved here. There we noted that
III
Preliminarily, we agree with the Court of Appeals that federal law controls the interpretation of the contract. See United States v. County of Allegheny, 322 U. S. 174, 183 (1944);12 Clearfield Trust Co. v. United States, 318 U. S. 363 (1943). This conclusion results from the fact that the contract was entered into pursuant to authority
In fashioning a federal rule we are, of course, guided by the general principles that have evolved concerning the interpretation of contractual provisions such as that involved here. Among thesе principles is the general maxim that a contract should be construed most strongly against the drafter, which in this case was the United States.14 The Government seeks to circumvent this principle by arguing that it is inapplicable unless there is ambiguity in the contractual provisions in dispute and there exists an alternative interpretation that is, “under all the circumstances, a reasonable and practical one.” Gelco Builders & Burjay Const. Co. v. United States, 177 Ct. Cl. 1025, 1035, 369 F. 2d 992, 999-1000 (1966). The Government itself, however, has proffered two mutually inconsistent interpretations of the contract clause. To be sure, one of them is pressed with considerably more enthusiasm than the other. The Government, nevertheless, must be taken implicitly to have
More specifically, we agree with the Court of Appeals that a contractual provision should not be construed to permit an indemnitee to recover for his own negligence unless the court is firmly convinced that such an interpretation reflects the intention of the parties. This principle, though variously articulated, is accepted with virtual unanimity among American jurisdictions.15 The
In short, if the United States expects to shift the ultimate responsibility for its negligence to its various contractors, the mutual intention of the parties to this effect should appear with clarity from the face of the contract. We can hardly say that this intention is manifested by the formulation incorporated into the present contract.17 By its terms Seckinger is clearly liable for its negligence, but the contractual language cannot readily
On the other hand, we must not fail to accord appropriate consideration to Seckinger‘s clear liability under the contract for “all damages” that resulted from its “fault or negligence.” (Emphasis added.) The view adopted by the Court of Appeals, and now urged by Seckinger, would drain this clause of any significant meaning or protection for the Government, and, indeed, would tend to insulate Seckinger from potential liability
Furthermore, in this latter situation, it is perfectly clear that, both before and after the passage of the Tort Claims Act, the United States could not, in any event, be charged with liability in the absence of negligence on its part. In short, the construction of the clause adopted by the Court of Appeals tends tо narrow Seckinger‘s potential liability and, also, limits its application to circumstances in which no doubt concerning Seckinger‘s sole liability existed. In the process, considerable violence is done to the plain language of the contract that Seckinger be responsible for all damages resulting from its negligence.
A synthesis of all of the foregoing considerations leads to the conclusion that the most reasonable construction of the clause is the alternative suggestion of the Government, that is, that liability be premised on the basis of comparative negligence.20 In the first place, this interpretation is consistent with the plain language of the clause, for Seckinger will be required tо indemnify the United States to the full extent that its negligence, if any, contributed to the injuries to the employee.
Secondly, the principle that indemnification for the indemnitee‘s own negligence must be clearly and unequivocally indicated as the intention of the parties is
Finally, our interpretation adheres to the principle that, as between two reasonable and practical cоnstructions of an ambiguous contractual provision, such as the two proffered by the Government, the provision should be construed less favorably to that party which selected the contractual language. This principle is appropriately accorded considerable emphasis in this case because of the Government‘s vast economic resources and stronger bargaining position in contract negotiations.21
For these reasons, we reverse the judgment of the Court of Appeals and remand this case to the District Court for further proceedings consistent with this opinion.22
Reversed and remanded.
MR. JUSTICE MARSHALL took no part in the consideration or decision of this case.
MR. JUSTICE STEWART, with whom THE CHIEF JUSTICE and MR. JUSTICE DOUGLAS join, dissenting.
The standard form that the Government uses for its fixed-price construction contracts has long contained a single sentence saying that the contractor “shall be re-
To be sure, the Court does not go quite so far as to hold that this obscure clause operates as a complete liability insurance policy. But the Court does hold that the clause requires the contractor to indemnify the Government “to the full extent that its negligence, if any, contributed to the injuries to the employee.” The magnitude of the burden the Court imposes is well illus-
Despite intimations in the Court‘s opinion to the contrary, we do not deal hеre with “common law or statutory rules of contribution or indemnity.”4 The only question the Court decides is the meaning of the words of a clause in a government contract.5 I think the
The clause first appeared in government contracts at least eight years before the enactment of the Federal Tort Claims Act in 1946. Before the passage of that Act the United States could not be sued in tort for personal injuries. Thus there was absolutely no reason for the Government to secure for itself a right to recovery over against an alleged joint tortfeasor. Yet we are asked to believe that the drafter of this clause was so prescient as to foresee the day of government tort liability nearly a decade in the future, and so ingenious as to smuggle a provision into a standard contract form that would, when that day arrived, allow the Government to shift its liability onto the backs of its contractors. This theory is nothing short of incredible.
In drafting its construction contracts the United States certainly has both the power and the resources to write contracts providing expressly that it will pass off onto its contractors, either in whole or in part, liability it incurs for damages caused by its own judicially determined negligence. The Government could require its contractors to hold it harmless without regard to fault on their part, or it could establish a prоration of liability arising from the joint negligence of the parties. But the contractual provision before us does neither. It no more says that the contractor shall reimburse the Government for his share of joint negligence than that he shall be a liability insurer for the Government‘s sole negligence.
The Court nonetheless manages to discover that the clause amounts to a contribution agreement, relying for its conclusion upon cases involving, not the simple responsibility clause before us, but express indemnification agreements with “hold harmless” clauses.6 This result is said to be desirable because it ensures a fair distribution of loss between those jointly responsible for the damage. But when Seckinger entered into this contract, it had every reason to expect that its liability for injuries to its employees would be limited to what is imposed by the South Carolina compensation law. That law relieved it of responsibility in tort in exchange for its guarantee that its employees would recover without regard to fault. Presumably its bid on the government project reflected its reasonable expectation that this would be the extent of its liability on account of employee accidents. Now the Court heaps an unforeseen federal contractual burden atop the requirement the State has already imposed.7
If the Government wants to impose additional liabilities upon those with whom it contracts to do its work, I would require it to do so openly, so that every bidder may clearly know the extent of his potential liability. Even in the domain of private contract law, the author of a standard-form agreement is required to state its terms with clarity and candor.8 Surely no less is required
Mr. Justice Holmes once said that “[m]en must turn square corners when they deal with the Government.”10 I had always supposed this was a two-way street. The Government knows how to write an indemnification or contribution clause when that is what it wants. It has not written one here.
I would affirm the judgment.
Notes
See Sternberger v. United States, 185 Ct. Cl. 528, 543, 401 F. 2d 1012, 1021; Jones v. United States, 304 F. Supp. 94, 101.11. PERMITS AND RESPONSIBILITY FOR WORK, ETC.
The Contractor shall, without additional expense to the Government, obtain all licenses and permits required for the prosecution of the work. He shall be responsible for all damages to persons or property that occur as a result of his fault or negligence in connection with the prosecution of the work. He shall also be responsible for all materials delivered and work performed until completion and final acceptance, except for any completed unit thereof which theretofore may have been finally accepted.
We specifically decline to hold that a clause that is intended to encompass indemnification for the indemnitee‘s negligence must include an “indemnify and hold harmless” clause or that it must explicitly state that indemnification extends to injuries occasioned by the indemnitee‘s negligence. Thus, contrary to the view apparently adopted in the dissenting opinion, we assign no talismanic significance to the absence of a “hold harmless” clause. Our approach is, in this respect, consistent with American Stevedores, Inc. v. Porello, 330 U. S., at 457-458. Contract interpretation is largely an individualized process, with the conclusion in a particular case turning on the particular language used against the background of other indicia of the parties’ intention. Consequently, we hold only that, in this case, the clause that provides that Seckinger will be responsible for all damages resulting from its negligence is insufficiently broad to encompass responsibility for injuries resulting from the negligence of the Government. And, of course, the Government is entitled to no recovery unless it establishes that Seckinger was negligent. Thus the dissenting opinion mischaracterizes the scope of our holding when it states that Seckinger must “reimburse the Government for losses it incurs resulting from its negligence.”“4.18. INDEMNIFICATION
“4.18.1. The Contractor shall indemnify and hold harmless the Owner and the Architect and their agents and employees from and against all claims, damages, losses and expenses including attorneys’ fees arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense (a) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting therefrom, and (b) is caused in whole or in part by any negligent act or omission of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder.” AIA Document A 201, Sept. 1967.
