United States v. O'BRIENUnited States v. O'BRIEN
delivered the opinion of the court.
This is a suit brought by the. United States to recover the extra expense incurred to complete some dredging in Rhode Island, by reason of the failure of the defendants Perkins and O’Brien diligently and faithfully to prosecute the work. The complaint was dismissed by the Circuit Court in accordance with the decision of the Circuit Court.of Appeals upon a previous'trial, 159 Fed. Rep.
Perkins and O’Brien made a contract with the United States to do the dredging required in improving Providence River and Narragansett Bay between certain points, to begin work on or before March 1, 1899, and to complete it on or before July 1, 1902. One term of the contract was that if they should fail to begin on time or should, “ in the judgment of the engineer in charge, fail to prosecute faithfully and diligently the work in accoi’dance with the specifications and requirements of this contract, then, in either case, the party of the first part, or his successor légally-appointed, shall have power, with the sanction'’of the Chief of Engineers, to annul this contract by giving notice in writing to that effect, . . . and, upon the giving of such notice all money or reserved percentage due or to become due to the party or parties of the second part by reason of this contract shall be and become forfeited to the United States; and the party of the first part shall be thereupon authorized, if an immediate performance of the work or delivery of the materials be, in his opinion, required by the public exigency, to proceed to provide for the same by open purchase or contract, as prescribed in § 3709 of the Revised Statutes of the United States: ” with a proviso that if the contractors should be prevented by violence of the elements from beginning or completing the work as agreed such additional time might be allowed them as in the judgment of the party of the first part should be just.
Toward the end of the contract, four paragraphs further on than the last, was the further agreement: “In case of failure on the’ part of the party of the second- part to complete this contract as specified and agreéd upon, that all sums due and percentage retained shall thereby be forfeited to the United States, and. that the said United
The work was begun but did not go on satisfactorily. On December 4, 1900, the major of engineers in charge wrote from Newport to the contractors and their surety, now represented by the other defendant, "that from present appearances it does not seem to be possible for the contractors to put on other dredges than the one now supposed to be at work,” stating what had been done and what would have to be done before the time allowed expired, and that to do the work, it would need three dredges upon it continuously. The letter proceeded to give the authorized warning that "unless the contractors have on work by January 1st, 1901, a sufficient plant to dredge at least 100,000 cubic yards per month the contract will be annulled.” On December 13 the contractors answered from New York, stating that they éxpected to make an arrangement to put on two more dredges within a few days. On December 29, 1900, the contractors telegraphed that their representative would call upon the major in charge on Tuesday morning, i. e., January 1. On December 31 he replied that the representative could accomplish nothing by coming, and on the same day wrote to the defendants informing them that the contract was annulled. The work afterwards was finished by other parties, at much increased cost. There was no substantial ground in the evidence to attribute the Government’s course to anything but the fault of the contractors, which was very plain, and the only question is what liability they incurred.
Again, the later paragraph that we have quoted, giving the right to recover expense of completing the work in excess of the original price, gives that right only “in case of failure ... to complete this contract as specified and agreed upon.” On their face these words mean failure
If the proviso for annulment be not construed' to import a promise on the defendants’ part, we are of opinion that there is no ground to charge them with a breach of contract. There were suggestions on the Government’s part of anticipatory breach, etc., that do not seem to us to need discussion..
We may add one further observation, although it hardly • is material, in the view that, we take. The ill chosen word ‘annul’ in the contract, repeated in the notice to- the contractors and in the complaint, cannot be taken literally in any of them. It means refuse to perform further, not rescind or avoid.
Philadelphia, Wilmington & Baltimore R. R. Co.
v.
Howard,
Judgment affirmed.