UNITED STATES of America for the Use of WELLMAN ENGINEERING COMPANY, Appellee,
v.
MSI CORPORATION and Fullerton Construction Co., Comprising a joint venture known as Zarpas-Fullerton Joint Venture, and
Aetna Casualty & Surety Company, Appellants.
No. 446.
Docket 29519.
United States Court of Appeals Second Circuit.
Argued May 6, 1965.
Decided July 29, 1965.
Richard E. Moot, Buffalo, N. Y. (William S. Easton and Ohlin, Damon, Morey, Sawyer & Moot, Buffalo, N. Y., on the brief), for appellee.
Marvin P. Sadur, Washington, D. C. (Francis J. Pelland, and Sussholz & Sadur, Washington, D. C., Lauren D. Rachlin, of Rachlin & Rachlin, Buffalo, N. Y., on the brief), for appellants.
Before MOORE, SMITH and HAYS, Circuit Judges.
J. JOSEPH SMITH, Circuit Judge:
The United States District Court for the Western District of New York, John O. Henderson, Judge, entered judgment on a Miller Act (40 U.S.C. §§ 270a, 270b) bond in favor of use-plaintiff Wellman Engineering Company, and the obligor and surety on the bond appeal. Affirmed.
Appellants MSI Corporation and Fullerton Construction Co., as a joint venture known as Zarpas-Fullerton Joint Venture (Zarpas), were successful bidders on a government project for construction of a Bomarc missile site near Niagara, New York. Appellant Aetna Casualty & Surety Company is surety on Zarpas' Miller Act bond on the contract.
Appellee, Wellman Engineering Company, contracted to furnish the Seneca Industrial Machine Corporation with certain hydraulic actuator and latch mechanisms needed by Seneca as part of a hydraulic system for opening and closing massive missile launcher roofs to be installed at a missile site then under construction by Zarpas, the general contractor for the Government project. Zarpas entered into a contract with Seneca entitled "Subcontract for Supply" whereunder Seneca was to manufacture and supply at the job-site the hydraulic system for opening and closing the roofs in accordance with contract specifications, sections 52 and 53 of the prime contract, including a designated change order, at a price of $85,000. Seneca did not have contractual responsibility for nor did it have anything to do with the installation of the system.
After Wellman had furnished all the mechanisms in accordance with the contract specifications, Seneca defaulted on its contract with Wellman and Wellman sought recourse against Zarpas. Timely notice of non-payment was given to Zarpas in accordance with the provisions of the Miller Act, and when Zarpas and its surety, the appellant Aetna Casualty & Surety Company refused payment, Wellman instituted this suit. The District Court, in finding for Wellman, held that Seneca was a subcontractor and that simply because Seneca did not perform any work on the job-site did not mean, as the court interpreted the Supreme Court decision in MacEvoy v. United States,
We think that the court was correct in looking at the total picture here. It has been held, properly, we believe, that MacEvoy does not confine the resolution of the issue to expert opinion in the trade. United States for the Use and Benefit of Gulfport, etc. v. Monaco & Sons,
The judgment is affirmed.
