The United States brought this replevin action to gain possession of certain tank gears in the possession of the defendant Lindberg Corporation (Lindberg). Lind-berg counterclaimed for the value of work performed in manufacturing the gears. Rejecting various defenses raised by the defendant, the district court granted summary judgment for the government and ordered Lindberg to relinquish its possession; it also dismissed the defendant’s counterclaim for lack of jurisdiction. Lind-berg now appeals the district court’s grant of summary judgment and its dismissal of the counterclaim. We affirm the judgment of the district court.
BACKGROUND
A. Facts
In March 1983, the United States Army Tank Automotive Command entered into a contract with MTC Gear Corporation (MTC) for the purchase of gears. 1 This government contract provided that the United States would purchase gears for use in military vehicles from MTC at the price of $604 per gear. R. 7 at 2. The contract incorporated Armed Services Procurement Regulation 7-104.35(b) (Procurement Regulation) — “Progress Payments for Small Business Concerns.” One of the provisions in that regulation is a title-vesting clause that grants title to the government in all “parts; materials; [and] inventories” allo-cable or chargeable to the contract upon production or acquisition by MTC. R. 10 at Ex. 5.
In the course of performing its work under the contract, MTC arranged for the gears to be heat “treated” or “enhanced” by Lindberg. This process was necessary to meet the specifications of the government contract. Thus, the unfinished gears were shipped from MTC to Lindberg, which, through its Harris Metals division, performed the treatment procedure. No formal subcontract was drawn up between MTC and Lindberg; MTC simply sent the gears, along with purchase orders explaining the proper specifications, to Lindberg for treatment. 2 Lindberg performed work on MTC-manufactured gears from April through October 1983.
In November, MTC closed active business and became insolvent. R.16A. At that time, MTC owed Lindberg $224,424.06 for its work; it also owed the government a substantial amount of money because, prior to MTC’s going out of business, the government had advanced $945,340 in progress payments. The government later recovered all but $273,420.20. MTC’s insolvency prompted both the government and Lindberg to seek some form of repayment.
Lindberg acted first. In May 1984, Lind-berg filed suit in the Circuit Court for Racine County, Wisconsin against MTC and the Chase Commercial Corporation (Chase). 3 It sought foreclosure of a common-law bailment lien against the gears for the value of the heat treatment performed by Lindberg. On July 25, 1984, the circuit court granted Lindberg a final default judgment foreclosing the lien. R. 7 at Ex. 1. At about this same time, the government, after having recovered as much of the cash progress payments as it could, took its first steps toward repossessing the gears. In December 1984, the government notified Lindberg of the government’s title to the gears and demanded that Lindberg relinquish possession. 4 Lindberg refused. Instead, in March 1985, Lindberg arranged a private foreclosure judgment sale of the gears to the Profile Gear Corporation (Profile) for $70,225. Notice of the private sale was provided to MTC, Chase, and the government. Upon receiving this notice, the government informed Profile of its claim of ownership, after which Profile refused to consummate the transaction.
On May 3, 1985, the government filed this replevin action seeking possession of the gears. Lindberg answered and filed an amended counterclaim, asserting that its common-law bailment lien was “superior to plaintiff’s claim of title.” R. 17 at 2, ¶ 7. Both parties moved for summary judgment.
B. Holding of the District Court
In two separate rulings, reported together as
United States v. Lindberg Corp.,
686
II.
ANALYSIS
A. Government’s Claim: Possession of the Gears
1. Title in the finished gears
At this point in the litigation, there appears to be no dispute between the parties with respect to the ownership of the gears prior to their shipment to Lindberg. By virtue of the government procurement contract between the United States and MTC, title clearly was vested in the United States. Nevertheless, Lindberg submits that title to the enhancement of the gears is vested in Lindberg. In a nutshell, Lind-berg argues that, although the government may have had title in the unfinished gears shipped from MTC to Lindberg, it does not have title in the heat treatment performed on the gears. It submits that, since the government did not make progress payments to MTC specifically directed at paying for the heat treatment, and, since neither MTC nor the government ever had possession of the heat-treated gears, the government never obtained title in the treatment of the gears. Appellant’s Br. at 13-18. Lindberg notes that it never received any payment from MTC. It then submits that, assuming the government followed its own regulations, “whatever progress payments were made by the Government to MTC did not include work which Lindberg performed. If the Government did not pay for the enhancement, and neither MTC nor the Government ever took possession of the enhancement, the title to the enhancement of the Gears never passed to the Government.” Appellant’s Br. at 17. Lindberg argues that MTC received progress payments from the government, but under Procurement Regulation paragraphs (a)(1) and (j), 6 it ought not have made those payments unless MTC paid Lindberg’s invoices in advance or after approval by the government.
(d) Title. Immediately upon the date of this contract, title to all parts; materials; inventories; work in process; ...; theretofore acquired or produced by the Contractor and allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices shall forthwith vest in the government; and title to all like property thereafter acquired or chargeable to this contract as aforesaid shall forthwith vest in the Government upon said acquisition, production, or allocation.
Procurement Regulation 11 (d) (emphasis supplied). The contract also provided, in relevant part, that:
All rights of the subcontractor with respect to all property to which the Government has title under the subcontract will be made subordinate to the rights of the Government to require delivery of such property to it in the event of default by the Contractor under this contract or in the event of the bankruptcy or insolvency of the subcontractor.
Procurement Regulation 1f (j)(2) (emphasis supplied).
When these provisions are given their plain meaning and are read in the context of the entire regulation, it is clear that title to the heat-treated gears — gears allocable to the MTC-government contract — is vested in the government. MTC entered into this contract to manufacture gears for the government; Lindberg was clearly a subcontractor to this arrangement.
7
Paragraph (d) of the Procurement Regulation, the key subsection, grants title in the unfinished gears to the government. No provision of the regulation supports the proposition that the heat treating of the gears altered this title. Moreover, under the provisions, there simply is no linkage between the government’s right to title and the making of progress payments to the subcontractor. The payment provisions nowhere qualify the government’s title in ma
2. Attachment of the Bailment Lien
Lindberg next submits that it held a valid bailment lien that precluded granting summary judgment for the government in its replevin action.
Under Wisconsin law, Lindberg well may have obtained a valid judgment foreclosing its bailment lien against MTC.
8
However, Lindberg’s satisfying state-law prerequisites for a bailment lien cannot end our inquiry. As the Supreme Court recently noted in
Boyle v. United Technologies,
— U.S.-,
Nor do we believe that Lindberg can avoid the supremacy of federal law by characterizing its claim as one for recoupment.
See
Fed.R.Civ.P. 13. Recoupment is merely “ ‘the right of the defendant to have the plaintiff’s monetary claim reduced by reason of some claim the defendant has against the plaintiff arising out of the very [matter] giving rise to the plaintiff’s claim.’ ”
United States v. 2,116 Boxes of Boned Beef,
3. Equitable defenses
The appellant finally submits that such extreme unfairness exists in this case that equity bars the government’s replevin action. Specifically, Lindberg notes that it (1) performed all the heat treating requested by MTC, (2) knew nothing about the MTC-government contract, and (3) upon learning of MTC’s insolvency, sought and obtained a proper bailment lien in state court. By contrast, Lindberg submits, the government never filed public notice of its title in the gears and did not notify Lind-berg of its interest in the gears until the eve of the private foreclosure sale. See Appellant’s Br. at 19-23. Thus, the appellant submits that the government ought to be prevented from suing for replevin by the doctrines of estoppel and laches. 10
We do not believe that either of these equitable concepts affords a basis for relief. In
Woodstock/Kenosha Health Center v. Schweiker,
“ ‘First, the party to be estopped must know the facts. Second, this party must intend that his conduct shall be acted upon, or must so act that the party asserting estoppel has a right to believe it is so intended. Third, the party asserting estoppel must have been ignorant of the facts. Finally, the party asserting estoppel must reasonably rely on the other’s conduct to his substantial injury.’ ”
Woodstock/Kenosha Health Center,
Similarly, Lindberg cannot resort to the equitable defense of laches. Regarding the application of laches against the government, this court has stated that “[ljaches bars the assertion of a claim ‘where deferment of action to enforce claimed rights is prolonged and inexcusable and operates to ... [a party’s] material prejudice.’ ”
Id.
(quoting
Advanced Hydraulics, Inc. v. Otis Elevator Co.,
The district court properly rejected the equitable defenses of estoppel and laches as bars to the government’s right to possess the gears. The record does not support the appellant’s contentions that the government acted in so unfair a manner as to prevent it from gaining possession to the property in which it holds vested title. Although a court may, under some circumstances, “apply equitable principles against the government in a case where extreme unfairness [is] shown,” those circumstances have not been established here.
American Pouch,
B. Lindberg’s Counterclaim: Compensation for the Heat Treating
The appellant also filed a counterclaim seeking compensation for the heat treatment performed on the gears, and now submits that the district court erred in dismissing that counterclaim for the unpaid heat treatment that Lindberg performed on the gears — $224,424.06.
We cannot reach the merits of this counterclaim, because, as the district court noted, it lacked jurisdiction to hear a claim against the United States for an amount greater than $10,000.
See
28 U.S.C. § 1346(a)(2). The appellant’s breaking down the total amount to a less-than-$10,-000 amount-per-gear is untenable. Any claim that Lindberg seeks to bring against the federal government must be brought in the United States Claims Court.
See
28 U.S.C. § 1491;
see also Marozsan v. United States,
CONCLUSION
Under the title-vesting clause of the government contract, the government held title to the gears both before and after Lindberg performed the heat treatment. Accordingly, the government is entitled to possession of the gears. Lindberg’s state-law bailment lien on the gears does not affect the government’s right to possession. The district court correctly held that it had no jurisdiction over the counterclaim. Accordingly, the judgment of the district court is affirmed.
Affirmed.
Notes
. The specific type of gears in Lindberg’s possession was described as "BullGears, Part No. 7364141.” R. 10 at Ex. 3.
. On its purchase orders, MTC requested that Lindberg perform the following treatment on the unfinished gears:
CARBURIZE, GLEASON HARDEN, TEMPER INDUCTION, TEMPER BORE, CLEAN AND 100% MAGNETIC PARTICLE INSPECTION PER MIL-I-6868 AND CLEAN
R. 10 at Ex. 1.
. The Chase Commercial Corporation was the only party that had filed a financing statement covering the gears.
. According to Lindberg, this letter was the first notice that it had "received of any claim of title to the aforesaid gears by the United States Government." R. 10 at 2, ¶ 5 (affidavit of Steven Pegg).
. The district courts have jurisdiction, concurrent with the United States Claims Court, of civil actions or claims “against the United States, not exceeding $10,000 in amount, founded either upon the Constitution, or any Act of Congress.” 28 U.S.C. § 1346(a)(2) (emphasis supplied).
. Those provisions state in relevant part that: (a) ... (1) Unless a smaller amount is requested, each progress payment shall be (i) ninety-five percent (95%) ... of the amount of the Contractor’s total costs incurred under this contract, except as provided herein with respect to costs of pension contributions, plus (ii) the amount of progress payments to subcontractors as provided in (j) below; ...
(j) Progress Payments to Subcontractors.
(1) The amount mentioned in item (a)(l)(ii) above shall be the sum of (i) all the progress payments made by the Contractor to his subcontractors and remaining unliquidated, and (ii) unpaid billings for progress payments to subcontractors which have been approved for current payment in the ordinary course of business, when under subcontracts which conform to (2) below.
(2) Subcontracts on which progress payments to subcontractors may be included in the base for progress payments pursuant to paragraph (a) of this clause are limited to those subcontracts in which there is expected to be a long "lead time”, between the begin-
ning of work and the first delivery, approximating four months or more for small business concerns and six months or more for firms which are not small business concerns, and in which the provisions regarding progress payments are substantially similar to and as favorable to the Government as this "Progress Payments” clause (except that in the case of those subcontractors which are small business concerns a "Progress Payment" clause substantially similar to 7-104.35(b) may be used). Progress payment rates for subcontractors shall be either the uniform, standard progress payment rate under Appendix E-503 or (if the subcontractor qualifies under Appendix E-530.3) the flexible progress payment rate under Appendix E-530, at the election of the subcontractor. All rights of the subcontractor with respect to all property to which the Government has title under the subcontract will be made subordinate to the rights of the Government to require delivery of such property to it in the event of default by the Contractor under this contract or in the event of the bankruptcy or insolvency of the subcontractor.
(3)The Government agrees that any proceeds received by it from property to which it has acquired title by virtue of such provisions in any subcontract shall be applied to reduce the amount of unliquidated progress payments made by the Government to the Contractor under this contract. In the event the
Contractor fully liquidates such progress payments made by the Government to him hereunder and there are progress payments to any subcontractors which are unliquidated, the Contractor shall be subrogated to all the Government’s rights by virtue of such provisions in the subcontract or subcontracts involved as if all such rights had been thereupon assigned and transferred to the Contractor.
(4) The billing described in (j)(l)(ii) above shall be paid promptly by the Contractor in the ordinary course of business, not later than a reasonable time after payment of equivalent amounts by the Government to the Contractor.
(5) To facilitate small business participation in subcontracting under this contract, the Contractor agrees to offer and provide progress payments to those subcontractors which are small business concerns, in conformity with the standards for customary progress payments stated in Appendix E of the Defense Acquisition Regulation, as in effect on the date of this contract. The Contractor further agrees that the need for such progress payments will not be considered as a handicap or adverse factor in the award of subcontracts.
R. 10 at Ex. 5 (footnote omitted) (emphasis supplied by appellant).
. See Appellant’s Br. at 17 (“Lindberg was clearly a subcontractor of MTC_”).
.
See Moynihan Assocs., Inc. v. Hanisch,
. See 6 C. Wright & A. Miller, Federal Practice and Procedure § 1427 (1971 & Supp.1988) (for court to entertain counterclaim against government, (1) the counterclaim must arise out of the same transaction or occurrence and (2) the relief must neither exceed nor differ in kind from that sought by the sovereign).
. In its answer to the government's complaint, Lindberg also pleaded waiver as an affirmative defense,
see
R. 2 at 3, and, in passing, mentions waiver in its appellate brief,
see
Appellant’s Br. at 21, but does not press that argument on appeal.
See Beard v. Whitley County REMC,
