United States v. Hugo Key and Son, Inc.United States v. Hugo Key and Son, Inc.
ORDER ON MOTION FOR SUMMARY JUDGMENT
This action was brought by the United States of America, on behalf of the United States Environmental Protection Agency (“EPA”), against Defendant Hugo Key and Son, Inc. (“Hugo Key”) for assessment of civil penalties and injunctive relief pursuant to the authority of Section 113(b) of the Clean Air Act (“Act”),
*1137
The United States has alleged in its complaint that Hugo Key violated Sections 112(c), 113(a)(3) and 114(a) of the Act,
The United States’ allegations are based on Hugo Key’s failure to follow certain work practices designed to prevent emissions of asbestos into the outside air. In particular, Defendant is charged with: (1) failure to adequately wet friable asbestos materials during stripping in violation of
The United States has also alleged that Hugo Key failed to timely respond to a reporting requirement issued by the United States Environmental Protection Agency (“EPA”) in violation of Section 114(a) of the Act,
On February 28, 1989, the Court heard the United States’ motion for summary judgment against Hugo Key on the issue of liability. After having considered the submissions of the parties and the arguments of counsel, 2 and reviewing the record in a light most favorable to the Defendant, the Court has determined that there are no issues of material fact as to the five claims alleged in the United States’ complaint and that summary judgment should be granted in the United States’ favor as to each of those claims.
I. STANDARD OF REVIEW
Summary judgment is appropriate when the pleadings and other submissions show that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law. Cia.
Petrolera Caribe, Inc. v. ARCO Caribbean, Inc.,
The “mere existence of
some
alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no
genuine
issue of
material
fact.”
Anderson v. Liberty Lobby, Inc.,
II.FINDINGS OF FACT
The Court finds that there is no genuine dispute as to the following facts. These facts are established for purposes of trial in this matter.
1. Pursuant to Section 112(b) of the Act,
2. Section 112(c)(1)(B) of the Act,
3. Hugo Key is and was at all relevant times a corporation incorporated under the laws of the State of Rhode Island with its principal place of business in Newport, Rhode Island.
4. Hugo Key is and was at all relevant times a construction and demolition contractor.
5. In September 1985, Hugo Key contracted with the United States Navy under Contract N62472-85-C-1830 (“Contract”) to conduct a demolition operation involving several buildings located on the Naval Base in Newport, Rhode Island.
6. The buildings to be demolished by Hugo Key under the Contract consisted of five quarters, identified as buildings B, C, D, E, and 131, and four garages.
7. Hugo Key was at all relevant times the contractor and superintendent responsible for the demolition operation.
8. The demolition operation involved a total of 420 linear feet of friable asbestos material on pipes, thereby triggering the asbestos NESHAP work practice standards.
9. The demolition operation was governed by the asbestos NESHAP, 40 C.F.R. Part 61, Subpart M.
10. Hugo Key hired Asbestos Removal and Consulting Company, Inc. (“ARCON”) to perform the asbestos removal work required under the Contract.
11. Pursuant to the Contract, ARCON developed an asbestos removal plan for Hugo Key, dated November 18, 1985, requiring that all asbestos removal take place within the sealed-off buildings which would be off-limits to all personnel not directly involved in the removal process until all asbestos was removed.
12. In a letter December 10,1985, Hugo Key notified the Navy that buildings B and E each contained an asbestos-covered boiler that had not been included in the Contract and requested that the Contract be amended to include additional compensation and contract time to remove the asbestos insulation from the two boilers.
13. On December 30, 1985, Hugo Key and the Navy negotiated an amendment to the Contract to include the removal by AR-CON of the asbestos insulation covering the two boilers located in buildings B and E.
*1139 14. On or about December 31, 1985, before ARCON had removed the asbestos insulation from the boilers, Hugo Key demolished buildings B and E and lifted the asbestos-covered boilers out of the rubble with a Koehring backhoe without wetting the boilers or taking any precautions to contain the asbestos material or prevent the release of asbestos fibers into the air as required by the asbestos NESHAP.
15. On December 31, 1985, the boiler which had been lifted from building E by Hugo Key, was pushed or dragged along the ground with the Koehring backhoe causing chunks of dry asbestos material to be stripped from the boiler, strewn onto the ground and emitted into 'the air.
16. On December 31, 1985, Navy Construction Representative Martin E. Kawa took samples of the dry asbestos material from the ground around building E to the Industrial Hygenist at the Navy Lab for analysis. The Navy Lab results confirmed that the samples were asbestos.
17. On or about January 3, 1986, David L. Hartshorn, Head Industrial Hygiene Officer for the Naval Hospital, accompanied Lt. William C. Taylor, II, the Navy Construction Project Engineer for the demolition operation, to the site. Mr. Hartshorn took six samples from the ground and boilers at the site of the demolition operation. The Navy Lab analyzed these samples and the results of the analysis established that five of the six samples were friable asbestos.
18. On January 17, 1986, traces of asbestos still remained on the site where buildings B and E had been as a result of Hugo Key’s improper handling of the asbestos-covered boilers.
19. At no time during the demolition operation did Hugo Key wet the asbestos-covered boilers.
20. On January 22, 1986, EPA Environmental Engineer Bridget E. McGuiness and Lt. William C. Taylor, II, inspected the site of the demolition operation. During the inspection, Ms. McGuiness took a sample of insulation material from Boiler E.
21. The sample taken by Ms. McGuiness was analyzed by EPA microbiologist Howard Davis who determined that the material was friable asbestos as defined by the asbestos NESHAP,
22. Section 114(a) of the Act,
23. On May 15, 1986, EPA issued a Section 114(a) investigatory letter to Hugo Key (“reporting requirement”) in order to obtain information on the demolition operation. EPA required a response from Hugo Key within ten days from receipt.
24. Hugo Key received the Section 114(a) reporting requirement on May 19, 1986.
25. Hugo Key failed to respond to the Section 114(a) reporting requirement within the ten day period set for response.
26. If a person fails to respond to a Section 114(a) reporting requirement, Section 113(a)(3) of the Act,
27. On or about June 30, 1986, EPA issued an Immediate Compliance Order and Reporting Requirement (“compliance order”) to Hugo Key pursuant to Section 113(a)(3) of the Act, ordering Hugo Key to provide information regarding the demolition operation within seven days.
28. Hugo Key received the compliance order on July 3, 1986.
29. Hugo Key failed to respond to the compliance order within the seven day period set for response.
30. Hugo Key did not respond to the Section 114(a) reporting requirement or to the Section 113(a)(3) compliance order until August 12, 1986.
*1140 III. CONCLUSIONS OF LAW
A. Violations Of The Clean Air Act And The Asbestos NESHAP Result In Strict Liability
This action was brought pursuant to the authority of the Clean Air Act,
The deleterious effects of asbestos are well documented. Inhalation of asbestos fibers can result in various pulmonary and pleural changes and diseases in humans such as mesothelioma (a form of cancer) and asbestosis. See, 38 Fed.Reg. 8820. 5
Asbestos was one of the earliest substances listed as a hazardous air pollutant in 1971. 36 Fed.Reg. 5931. The NESHAP for asbestos was promulgated in 1973 after extensive evaluation and public comment (38 Fed.Reg. 8820), and is currently set forth at 40 C.F.R. Part 61, Subpart M. The emission standard for asbestos is prescribed by Section 112(c)(1)(B) of the Act,
Section 112(e)(1) of the Act,
The legislative history of the 1977 amendments to the Clean Air Act makes clear that Congress intended that the Act and the asbestos NESHAP provide strict liability for civil violations of their provisions. H.R.Rep. No. 94-1175, 94th Cong. 2d Sess. 52-53 (1976). Federal courts have consistently adhered to the legislative intent of the Act to provide for strict liability.
See, e.g., United States v. Ben’s Truck and Equipment, Inc.,
No. S-84-1672-MLS,
B. Hugo Key Was Subject To The Requirements Of The Asbestos NESHAP
A major source of airborne asbestos in the demolition or renovation of buildings occurs when asbestos is present in insula
*1141
tion. 38 Fed.Reg. 8821. Since no level of exposure to asbestos is deemed safe, the asbestos NESHAP for demolition and renovation operations is designed to prevent emissions of asbestos fibers to the outside air. The standards for controlling asbestos emissions are expressed in the form of work practice requirements.
See,
The asbestos NESHAP requires each owner or operator of a demolition operation to comply with the work practices set forth in
The terms “owner or operator” and “stationary source” are explained in the Federal Register notice promulgating the 1984 amendments to the asbestos NESHAP, 49 Fed.Reg 13658, 13659 (April 5, 1984), as follows:
The general provisions of 40 C.F.R. Part 61 define “owner or operator” as any person who owns, leases, operates, controls, or supervises a stationary source (40 C.F.R. § 61.02(1) ). The stationary source in this case is the demolition or renovation operation. The demolition or renovation contractor would clearly be considered an owner or operator by “operating” the stationary source.... Therefore, the standard applies to both the contractor and the facility owner or operator.
The stationary source of emissions in a demolition or renovation operation is, by definition, the operation itself. Therefore, the demolition of buildings conducted by Hugo Key at the Naval Base was a “demolition operation.” The “owner or operator” of a demolition operation is any person who “owns, leases, operates, controls or supervises” the demolition operation.
It is undisputed that the amount of friable asbestos in the buildings being demolished was at least 420 linear feet on pipes. This amount of friable asbestos was clearly in excess of the threshold quantity of 260 linear feet on pipes, thereby requiring compliance by Hugo Key with the asbestos NESHAP work practice standards. Therefore, this Court finds that all substantive requirements of the asbestos NESHAP at issue in this action were applicable to the demolition operation conducted by Hugo Key.
The work practice violations concern Hugo Key’s failure to adequately wet friable asbestos materials covering the boilers during stripping (
C. Hugo Key Failed To Adequately Wet Friable Asbestos Materials During Stripping
The United States claims in the third count of its complaint that Hugo Key failed to adequately wet friable asbestos materials during stripping in violation of
Hugo Key does not dispute that it removed the asbestos-covered boilers from buildings B and E with a backhoe during the demolition operation. There is also no dispute that some asbestos insulation was stripped from at least one of the boilers when it was removed from the building and pushed by the backhoe. Hugo Key admits that at no time during the demolition operation did it wet the asbestos-covered boilers. Nor does Hugo Key claim that it used a local exhaust or ventilation and collection system to capture particulate asbestos material. The boiler insulation was sampled by both the EPA and the Navy and their analyses establish that the material covering the boilers was friable asbestos. Thus, the elements for a one day violation of
D.Hugo Key Failed To Keep Friable Asbestos Materials Wet Until Collected For Disposal
The United States claims in the fourth count of its complaint that Hugo Key failed to adequately wet the friable asbestos materials stripped from the boilers to ensure that the friable asbestos materials remained wet until collected for disposal, in violation of
There is no dispute that two asbestos-covered boilers were removed from buildings B and E by Hugo Key with a backhoe and that some of the insulation from at least one of the boilers was stripped when it was pushed along the ground with the backhoe. Hugo Key also admits that at no time during the demolition operation did it wet the asbestos-covered boilers. The Navy took samples of the insulation material that was scattered on the ground on December 31, 1985, and those samples were dry. Six more samples of dry insulation were taken from the ground and the boilers at the site of the demolition operation by the Navy on January 3, 1986, and five of the samples proved to be friable asbestos. The sample taken from boiler E by EPA also proved to be friable asbestos. Thus, the elements for at least a one day violation of
E.Hugo Key Discharged Visible Emissions Into The Outside Air During The Handling Of Asbestos-Containing Waste Material
The United States claims in the fifth count of its complaint that Hugo Key discharged visible emissions into the outside air during the handling of asbestos-containing waste material, and did not use one of the disposal methods specified in
It is undisputed that the boilers were covered with friable asbestos material. Nor is it disputed that dry, friable asbestos insulation material fell to the ground from at least one of the boilers when it was removed from the building with a backhoe. Traces of asbestos remained on the ground until January 17, 1986. In addition, Hugo Key does not dispute that it did not take any precautions to contain the materials so exposed, or to prevent release of asbestos fibers into the air.
Since visible emissions were discharged uncontained to the outside air, one of the disposal methods specified in the regulations would have had to be used by Hugo Key to avoid liability under
F. Hugo Key Failed To Timely Respond To EPA’s Section 114(a) Reporting Requirement
The United States claims in the first count of its complaint that Hugo Key failed to respond in a timely manner to EPA’s reporting requirement seeking information on the demolition operation in violation of Section 114(a) of the Act,
In order to establish a violation of Section 114(a), the United States must demonstrate that Hugo Key is a person who owns *1144 or operates a stationary source, that EPA issued Hugo Key a Section 114(a) reporting requirement requesting information, and that Hugo Key failed to respond to the reporting requirement in a timely manner.
A “person” within the meaning of Section 302(e) of the Act,
The following facts are admitted by Hugo Key. On May 15, 1986, EPA issued a Section 114(a) reporting requirement to Hugo Key asking for information on the demolition operation. Hugo Key received the reporting requirement on May 19, 1986, but failed to respond within the required ten day period. Hugo Key did not respond to the reporting requirement until August 12, 1986. Thus, the elements of a 77 day violation of Section 114(a) of the Act,
G. Hugo Key Failed To Timely Respond To EPA’s Section 113(a)(3) Compliance Order
The United States claims in the second count of its complaint that Hugo Key failed to respond in a timely manner to EPA’s compliance order issued pursuant to Section 113(a)(3) of the Act,
In order to establish a violation of an order issued pursuant to Section 113(a)(3), the United States must demonstrate that Hugo Key is a person who has violated Section 114(a) of the Act, that EPA issued Hugo Key a Section 113(a)(3) compliance order, and that Hugo Key failed to respond with the compliance order in a timely manner.
As previously stated, Hugo Key is a person within the meaning of the Act who violated EPA’s Section 114(a) reporting requirement. The following facts are admitted by Hugo Key. On or about June 27, 1986, EPA issued an Immediate Compliance Order and Reporting Requirement (“compliance order”) to Hugo Key to enforce the Section 114(a) reporting requirement. Hugo Key received the compliance order on July 3, 1986, but failed to respond within the required seven day period. Hugo Key did not respond to the compliance order until August 12, 1986. Thus, the elements of a 33 day violation of Section 113(a)(3) of the Act,
Consistent with the foregoing:
1. Summary judgment on liability as to the alleged violation of40 C.F.R. § 61.147(d) , is GRANTED in favor of the Plaintiff United States;
2. Summary judgment on liability as to the alleged violation of40 C.F.R. § 61.147(e)(1) , is GRANTED in favor of the Plaintiff United States;
3. Summary judgment on liability as to the alleged violation of40 C.F.R. § 61.152(b) , is GRANTED in favor of the Plaintiff United States;
4. Summary judgment on liability as to the alleged violation of Section 114(a) of the Act,42 U.S.C. § 7414(a) , is GRANTED in favor of the Plaintiff United States; and,
*1145 5. Summary judgment on liability as to the alleged violation of Section 113(a)(3) of the Act,42 U.S.C. § 7413(a)(3) , is GRANTED in favor of the Plaintiff United States.
The remaining issues in this action concern the United States’ request for the assessment of civil penalties and injunctive relief against Hugo Key for its violations of the Act and asbestos NESHAP. These matters have been set down for trial commencing on March 27, 1989.
IT IS SO ORDERED.
Notes
. Section 113(b),
*1137 The Administrator shall, in the case of any person which is the owner or operator of a major stationary source, and may, in the case of any other person, commence a civil action for a permanent or temporary injunction, or to assess and recover a civil penalty of not more than $25,000 per day of violation, or both, whenever such person—
(1) violates or fails or refuses to comply with any order issued under subsection (a) of this section; or ...
(3) violates ...section 7412(c) of this title
(4) fails or refuses to comply with any requirement ofSection 7414 of this title....
. In support of its motion for summary judgment, the United States submitted to the Court affidavits, answers to interrogatories, admissions and depositions. Following oral argument, the Court permitted the United States to file supplemental affidavits in order to clarify certain points made in its motion for summary judgment.
.
. A hazardous air pollutant is defined as an air pollutant "which in the judgment of the Administrator causes, or contributes to, air pollution which may reasonably be anticipated to result in an increase in mortality or an increase in serious irreversible, or incapacitating reversible, illness.”
. Congress made a specific finding in regard to the hazardous nature of asbestos in Section 502(a) of the Asbestos School Hazard Abatement Act of 1984,
. The asbestos NESHAP defines friable asbestos,
. The disposal methods specified in
. Section 114(a) of the Act,
For the purpose (i) of developing or assisting in the development of ... any emission standard undersection 7412 of this title, (ii) of determining whether any person is in violation of any such standard ... or (iii) carrying out any provision of this chapter ...
(1) The Administrator may require any person who owns or operates any emission source ... to (A) establish and maintain such records, (B) make such reports, ... and (E) provide such other information as he may reasonably require....
.The First Circuit has recognized the importance of EPA’s ability to seek information from persons in order to enforce the federal environmental laws. The Court upheld a civil penalty of $20,000 per defendant for violation of the Resource Conservation and Recovery Act’s reporting requirements, stating that:
[UJnless the civil penalty provision of the RCRA is applicable to those who refuse to honor the EPA’s inquisitorial authority under § 6927(a), the agency will be severely — indeed, unduly — handicapped in its attempt to effectuate needed regulation....
United States v. Charles George Trucking Co.,
. Section 113(a)(3),
Whenever, on the basis of any information available to him, the Administrator finds that any person ... is in violation of any requirement ofsection 7414 of this title (relating to inspections, etc.), he may issue an order requiring such person to comply with such section or requirement, or he may bring a civil action in accordance with subsection (b) of this section.