204 Pa. 438 | Pa. | 1903
Opinion by
September, 1899, Hegeman & Company, consisting of Hegeman & Russell, contracted with the United States to build a dam at Herr’s island on the Allegheny river, and the same month gave bond to the United States with the American Surety Company as surety, having among others, a covenant to pay all persons for material and labor supplied in the work. Nicola Brothers supplied the timber necessary to the carrying out of the contract; the custom of dealing between them and the contractors, was for the latter to give their notes from time to time to Nicola Brothers for about the book account price of the timber payable at the date of the notes, 'which notes were indorsed by the payees and discounts procured by indorsers; as they fell due they were paid in whole or in part; for whatever balance was unpaid, renewal notes of the same bind were given by the contractors. Nicola Brothers kept a book account against the contractors, charging them up regularly as the timber was furnished.
On August 11, 1899, the firm of Hegeman & Company was dissolved by the retirement of Russell and the introduction of a new member Reilley, the firm name thereafter being Hegeman & Reilley. At the dissolution, there were three of the Nicola Brothers’ notes outstanding, one for $1,500, one for
The principal assignments of error raise but the single question, did the court err in not deciding as matter of law that the evidence showed an agreement for extension on part of Nicola Brothers without the consent of the surety? The facts, that the creditors did agree to an extension of time on the notes to the principal debtor and that they did accept the notes, without the consent of the surety are not disputed. Does it follow that the surety was thereby released? We think not from the bare facts. There is no implied promise
Justice Strong, in the case last cited, while noticing the English cases which seem to decide that taking a time note suspends action on the original debt, at least until maturity of the note, says : “ But the late Pennsylvania cases take different ground and follow the ruling in Pring v. Clarkson, 1 Barn. & Cress. 14, in which it was decided that the acceptance of a new bill from the acceptor of a former bill after it had became payable for the payment of the same debt at a future day, could only be considered taking collateral security, and therefore did not amount to nor imply giving time to the acceptor.” In the case before him, Shaw & Leigh contractors for building a church, filed a mechanic’s lien and issued a sci. fa. thereon; at the trial defendants offered a receipt from the contractors for three notes equaling the amount of the lien claimed, at sixty, ninety and one hundred and twenty days, for bricks delivered to the church and signed by the contractors. There was some evidence as to the understanding of the parties when the notes were given, and the court below left it to the jury to find whether they were received as payment, reserving the point as to whether they were in law a payment and thereby a re
If the acceptance of the notes of themselves implied a payment, notwithstanding the verdict of the jury, that they were not so intended, the lien was ipso facto relinquished; so here, if, as argued by appellant’s counsel, the notes themselves implied a payment of the original debt 'or an extension of it, notwithstanding the verdict of the jury, that it was in fact not intended as a payment but was only the taking of a collateral security, then the judgment ought to be reversed; but the court below in the case cited was reversed for deciding the point in the very way appellant now asks us to decide it. We will not do so, not only because such decision would be flatly against precedent, but also because the precedents are founded on sound reasons.
As to the fourth assignment which complains of the refusal of the court to withdraw from the jury the charges for freight and demurrage on the timber, .we think these were properly a ■ part of the cost of the timber furnished by Nicola Brothers to defendants in the prosecution of the work. The expenses of transportation entered into the cost of the timber as much so as the cost of the chopping and hewing it in the woods.
All the assignments of error are overruled and the judgment is affirmed.