United States v. Essential Construction Co., Inc.United States v. Essential Construction Co., Inc.
MEMORANDUM
This is a suit under the Miller Act (40 U.S.C. § 270a et seq) by which use *682 plaintiff, Air Stream Products Co., Inc., seeks to recover on a payment bond for materials delivered to a subcontractor of a joint venture contractor composed of defendants, Essential Construction Co., Inc., and Himount Constructors, Ltd. The contractor and its surety, the Aetna Casualty & Surety Co., have moved for summary judgment on the ground that use plaintiff did not give them ninety days notice of its claim as required by 40 U.S.C. § 270b(a).
It is undisputed that use plaintiff is seeking recovery for three orders for louvers valued at $6,388, $120 and $25 and shipped on March 24, 1970, March 30, 1970, and September 29, 1970, respectively. Notice of claim was given by letter dated October 26,1970.
The Miller Act provides that a materialman can recover from a contractor for goods supplied a subcontractor only if he gives “written notice to said contractor within ninety days from the date on which [he] . . . furnished or sup-
plied the last of the material for which such claim is made.” 40 U.S.C. § 270b(a). Defendants argue that although notice was apparently given within ninety days of the shipping date of the last order, it is ineffective for one of two reasons: 1) The last.shipment was lost in transit and, therefore, cannot be the triggering event since it was not “furnished or supplied”; or 2) even if the last shipment was received, it represents too inconsequential an amount to revive liability as to the prior shipments.
With regard to defendants’ first ground, summary judgment is clearly inappropriate, inasmuch as use plaintiff contests the asserted nondelivery of the third shipment and has produced an invoice on which receipt of the item was acknowledged by the subcontractor. .
As to the second point, our research (unassisted by use plaintiff’s counsel who failed to submit an opposing memorandum as required by Rule 9(b) of the General Rules of this Court) has revealed that the law is less favorable to defendants’ position than they would have us believe. It is true that the case on which they rely, United States for use and benefit of J. A. Edwards & Co. v. Peter Reiss Construction Co.,
Therefore, the legal test is “whether the work was performed and the material supplied as a ‘part of the original contract’ or for the ‘purpose of correcting defects, or making repairs following inspection of the project.’ ” United States for Use and Benefit of Austin v. Western Electric Co., Inc.,
*683 Accordingly, since a genuine issue of material fact exists, the granting of summary judgment would be improper and the motion is denied.
It is so ordered.