215 F. 209 | E.D. Pa. | 1914
This is a suit in assumpsit for money bad and received, brought to recover the sum of $10,331.65, alleged to have been paid through a mistake of fact, with interest from May 1, 1910. The statement recites that the United States, through the isthmian Canal Commission, had a contract with the D’Olier Engineering Company, dated November 17, 1908, for the erection of two boiler plants, one at Gatun and the other at Miraflores, in the Isthmus of Panama, at a price of $60,335 for each plant. The price of the boilers, according to the contract, was based upon an efficiency of 65 per cent, developed by a certain test provided in the contract. In case the efficiency fell short of 65 per cent., the price of the plant was to be reduced $1,000 for each 1 per cent, below the efficiency percentage, and should the test demonstrate that the efficiency exceeded 65 per
“There shall be conducted, on at least one boiler of said plant an official test made by the engineer of the commission in charge or his deputy designated for the purpose and an official representative of the contractor, * * * and the same to be conducted under the conditions described in paragraph 4 of the specifications given under item 1 of circular No. 444.”
There were subsequent amendments of the contract, but there was no amendment of the provision in relation to the payment of $1,000 for each 1 per cent, of efficiency above 65. The statement avers that the plant at Gatun was tested in accordance with the contract, and from the record of the test the engineers having, charge of the matter, as provided in the contract, made computations and found that the boiler had attained an efficiency of 79.72 per cent., an excess of 14.72 over the efficiency prescribed by the contract. Thereafter the plant at Miraflores was similarly tested, and from the record of the test the engineers made computations and found that the boiler had attained an efficiency of 82.59, an excess of 17.59 over the efficiency prescribed in the contract. It is averred that, after these tests were, made, supplemental agreements were entered into February 28,' 1910, and May 10, 1910, by which the government, inter alia, agreed to pay the contractor' the $14,720 due for excess efficiency in the boilers of the Gatun plant and the $Í7,590 due for excess efficiency in the boilers in the Miraflores plant. In these supplemental agreements, arrangement was made for payment of other items under the contracts. It is then averred that:
“Thereafter, In January, 1911, the plaintiff discovered that a mistake had been made by the engineers having the computation in charge in calculating the figures of efficiency already referred to, to wit, of 79.72 per cent, on the boiler at Gatun and of 82.59 per cent, on the boiler at Miraflores. By a recalculation it appeared that the original figures had been arrived at by an erroneous method of computation; the error being based on the fact that the factor of evaporation had been determined by using the total heat in superheated steam instead of the total heat in saturated steam. A new computation was thereupon made, and it then appeared that the correct efficiency of the boiler at Gatun was 74.26 per cent, and of the boiler at Miraflores was 75.71 p.er cent. Instead of being entitled to a bonus of fourteen thousand seven hundred twenty dollars ($14,720) on the Gatun boiler the defendant was entitled only to nine thousand two hundred sixty dollars ($9,260), and instead of being entitled to a bonus of seventeen thousand five hundred ninety dollars ($17,590) on the Miraflores boiler the defendant was entitled to only ten thousand seven hundred ten dollars ($10,710), and had consequently been awarded-an excess allowance on these two items to the extent of twelve thousand three hundred forty dollars ($12,340), of which amount ten thousand three hundred thirty-one dollars and sixty-five cents ($10,331.65) had actually been paid to the said defendant by the plaintiff. Immediately on the discovery of this mistake, the plaintiff notified the defendant and demanded the return of the excess payment, amounting to ten thousand three hundred thirty-one dollars and sixty-five cents ($10,331.65) as aforesaid, and payment was refused. No part of this sum has ever been paid by the defendant, to the plaintiff, and the whole thereof is now justly due and payable.”
The defendant demurs to the statement of claim, and assigns as the special grounds of demurrer required under rule 20, § 3, of the rules of this court, that the agreements of February 28, 1910, and May 10,
“It lies for money which exsequo et bono the defendant ought to refund; * * * it lies for money paid by mistake; or upon a consideration which happens to fail. * * * In one word, the gist of this kind of action is that the defendant upon the circumstances of the case is obliged by the ties of natural justice and -equity to refund the money.” Per Lord Mansfield in Moses v. MacPerlan, 2 Burr. 1005.
The action must be based upon a mutual mistake of fact. Ege v. Koontz, 3 Pa. 109; Kingston Bank v. Eltinge, 40 N. Y. 391, 100 Am. Dec. 516. Under such circumstances money paid by mistake may be recovered back. In re F. & M. Mech. Bank (D. C.) 13 Fed. 361; Brown v. District of Columbia, 17 Ct. Cl. 402; Behring v. Somerville, 63 N. J. Law, 568, 44 Atl. 641, 49 L. R. A. 578; Walker v. Conant, 65 Mich. 194, 31 N. W. 786; Hudson River Water Power Co. v. Glen Falls Cement Co., 186 N. Y. 597, 79 N. E. 1107; U. S. v. Charles et al., 74 Fed. 142, 20 C. C. A. 346; Allen v. Hammond, 36 U. S. (11 Pet.) 63, 9 L. Ed. 633; Scriba v. Insurance Co., 21 Fed. Cas. 874; Wilson v. Insurance Co. (C. C.) 5 Fed. 674.
The contract between the parties is no longer. executory, except in so far as the payment of money by the plaintiff is concerned. There is no question involving the rights of other parties, or any involved method of accounting, which requires the suit to be in equity rather than at law. There is no question of restoration of the parties to their prior status, for the item in the contract under which the plaintiff agrees to pay for the excess efficiency is merely a carrying out of the express terms of the original contract, and everything else to be done has been done by the parties. The suit clearly comes within section 267 of the Judicial Code of March 3, 1911, providing;
“Suits in equity shall not be sustained in any court of the United States in any case where a plain, adequate, and complete remedy may be had at law.”
Both parties, relying upon the report of the engineers, agreed to the item- liquidating the amount to be paid for excess efficiency, which amount was subsequently set out in the supplemental agreements, and, in pursuance of that liquidation, the defendant has received the money claimed in this suit, without giving any consideration therefor. The defendant is liable for repayment of the money erroneously paid by the plaintiff, and erroneously accepted by the defendant under such a mutual mistake of fact, and the form of action selected in-this case is a proper one.
The demurrer is overruled, with leave to the defendant to file an affidavit of defense within 15 days.