MEMORANDUM, DECISION & ORDER
1. FACTS
This action concerns a construction project performed by defendant Chilstead Building Co., Inc. (“Chilstead” or “defendant”) involving the replacement of a roof at the United States Army Reserve Center in Plattsburgh, New York. 1 See PI. Rule 7.1(f) Stat. ¶¶ 1-4. The United Statеs Army issued a “Solicitation, Offer, and Award” (hereinafter “the contract”) on or about July 24, 1992, and Chilstead was awarded the contract on or about September 10, 1992. 2 Id. ¶¶ 1,4. The contract provided specific guidelines regarding any deviations from the original specifications. Paragraph 23 of the Statement of Work, attached to the contract, reads as follows:
SW-23 IMPORTANT NOTICE: The contractor will not accept instructions issued by any person other than the Contracting Officеr or his/her authorized representative acting within the limits of his/her authority. No information other than that which may be contained in any authorized amendment to this solicitation or any authorized modification to any resulting contract issued by thе Contracting Officer, which may be received from any person employed by the U.S. Government or otherwise, shall be considered as grounds for deviation from any provisions, conditions or other terms of this solicitation or any resulting cоntract.
Furthermore, Paragraph 24(b) reads as follows:
No oral statements of any person, whomsoever, will in any manner or degree modify or otherwise effect the terms or conditions of this contract. The Contracting Officer shall be the only person authorized to approve changes in any of the requirements under this contract, and notwithstanding any provisions contained elsewhere in this contract, said authority shall remain solely with the Contracting Officer. CORs shall be limited to the authority specified in their lettеr of appointment.
PI. Rule 7.1(f) Stat. ¶¶ 6-7.
A pre-construction meeting was held on November 5,' 1992 and work began shortly afterwards. On February 26,1993, Chilstead formally requested approval to make three major changes on the roof project. In partiсular, Chilstead proposed to eliminate the additional wood blocking as shown on Detail “D” Sheet A-l and configure a truss heavier than that called for in the specifications. Def. Exhibit H. The proposed changes were disapрroved by plaintiff by letter dated April 15, 1993. Pl. Rule 7.1(f) Stat. ¶10. Chil-stead never received an approved, signed submittal for the heavier trusses that it installed. Id. ¶ 11. Nevertheless, Chilstead began installation of the deviant trusses sometime after April 15,1993, and half of the trusses were erected by April 28,1993. Def. Mem. at 8. Plaintiff certified that the project was 100% completed on August 16, 1993. Def. Exhibit D.
Both parties agree that while defendant performed the work pursuant to the contract, the work failed to meet the contract specifications. Specifically, the project completed by defendant did not align truss panel points with the concrete masonry unit walls below, and defendant did not receive an “approved signed submittal” for the type of trusses which were installed. PI. Rule 7.1(f) Stat. ¶¶ 9-12. Chilstead maintains that it received verbal approval to install the deviant trusses from plaintiffs consulting engineer, N.K. Bhandari, Inc., provided that extra support blocking be installed to bring the trusses into conformance with the original plans. Def. Mem. at 1. Chilstead further maintains that verbal acceptance of the truss system and further lack of action by plaintiff after installation induced a belief by Chilstead that the truss design as specifiеd in the contract had been waived by plaintiff.
After a number of bi-weekly cite inspections, inspector Thomas Shaw wrote in an October 8, 1993 report that Chilstead “had fulfilled his obligation to the contract”. Def. Exhibit C. Plaintiff payed all but 1% of the final contract price on July 26, 1993. PL Exhibit E. Oh December 13, 1994, the Directorate of Contracting, Gordon Reynolds, sent a letter revoking final acceptance of the project to Chilstead, citing the installation of the disapproved trussеs and subsequent deviations from the original contract specifications caused by the installation of the deviant trusses. Def. Exhibit E.
II. PROCEDURAL HISTORY
Plaintiff filed an action for treble damages and civil penalties under the False Claims Act, 31 U.S.C. §§ 3729-3731, and in the alternative, for damages for fraud, breach of contract, and unjust enrichment on April 22, 1996. Defendant brought counterclaims alleging malicious prosecution, abuse/misuse of legal process, bad faith, fraud, negligence, conspiracy and сollusion. Plaintiff now moves for partial summary judgement on the False Claims Act and breach of contract claims, and for dismissal of defendant’s counterclaims.
III. DISCUSSION
A. Summary Judgment
Summary judgment shall be granted if there is no genuine issue of material fact and the moving party is entitled to a judgment as a matter of law. Fed.R.Civ.P. 56(c). The moving party has the initial burden of. demonstrating the absence of a genuine issue of material fact.
Thompson v. Gjivoje,
When the
moving
party has
met its
burden, the non-moving party must do more than “simply show that there is some metaphysical doubt as to the material facts.”
B. Breach of Contract Claim
Plaintiff argues that it is entitled to summary judgment on its breach of contract claim because there is no dispute that defendant did not perform the work as specified under the contract. Specifically, plaintiff maintains that defendant’s installation of the deviant truss system constitutes a breach of contract.
New York law provides that “[i]f a performance differing from that required by the contract is approved or accepted, such action may constitute a waiver of performance in accordance with the contract. Waiver requires a knowing acceptance of defective performance.” 22A N.Y. Jur.2d
Contracts,
§ 372 (1996). In
Mississippi Shipbuilding Corp. v. Lever Bros. Co.,
Based on the evidence in the record, a factual issue remains as to whether plaintiff, through project inspector Shaw, knowingly accepted the work as completed by Chilstead and therefore waived the original truss specifications. Specifically, defendant offers an affidavit from plaintiffs facilities manager, Frank E. McGrath, who claims that Shaw spoke with him personally about the truss issue. McGrath further notes that at the time of truss installation, the uninstalled deviant trusses were on the ground and readily accessible for Shaw’s observation, and that the roof wаs uncovered and the trusses were over 50% erected. Def. Exhibit R. McGrath assumed that there was no problem with the trusses because if there had been, Shaw would not have allowed them to be further installed. Id. It is undisputed that Shaw indicated in an April 28, 1993 rеport that about half the trusses had been installed with sheathing covering two-thirds of the trusses. Def. Exhibit Q. Neither in that report nor in following reports did Shaw mention that the installed trusses were not those which were specified by the contract. Shaw agаin commented on the trusses in a May 7, 1993 report, noting “[cjontractor set ting trusses on corridor from (illegible term) to drill hall.” Def. Exhibit H. Again, there was no mention of the deviant trusses.
Chilstead further asserts that Shaw acknowledged in writing on July 21, 1993, subsequent to the complete installation of the deviant trusses, that “we inspected the complete work cite and I could find no deficiencies other than those that were noted previously and corrected.” He further acknowledged that defеndant had “therefore fulfilled [its] obligation to the contract.” Def. Exhibit C. Finally, defendant points to the sixteen month period between full payment and the December 13, 1994 letter from Gordon Reynolds revoking acceptance of the сompleted work. Def. Exhibit E.
See Lever Bros.,
This evidence raises fact issues as to whether plaintiff knowingly accepted the deviant trusses, thus, waiving the right to assert such deviations as a breach of the contract.
See Lever Bros.,
C. False Claims Act Claim
The False Claims Act is applicable to any person who knowingly:
(1) presents, or causes to be presented, a false or fraudulent claim for money or property against the United States; (2) makes or causes to be made a false statement to get a false claim paid or approved; (8) conspires to defraud the government by getting a false claim paid; or (4) knowingly makes, uses, or causes to be used, a false statement to conceal, avoid or decrease an obligation ... to the government.
31 U.S.C. § 3729(a).
As Chilstead was performing the work, it submitted periodic “progress payment” claims. These claims certified that the work had been performed “in accordance with the specifications, terms, and conditions of thе contract.” Pl. Mem. at 2. Plaintiff asserts that Chilstead violated the False Claims Act in submitting five sworn claims that it had performed the work in accordance with the contract, when it had not.
The Second Circuit has long held that the False Claims Act is aрplicable only to claims which are “‘false, fictitious, or fraudulent’ and there must be clear and convincing proof.”
United States v. Foster Wheeler Corp.,
D. Counterclaims
Plaintiff contends that the counterclaims should be dismissed for lack of jurisdiction and as barred by sovereign immunity. Defendant’s counterclaims alleging a breach of contract are barred by the Tucker Act, because breach of contract claims seeking more than $10,000 can only be brought in the Court of Claims.
See United States v. Buiges,
Second, plaintiff contends that insofar as these counterclaims allege malicious prosecution and torts related to fraud and deceit, they are barred by sovereign immunity. The Federal Tort Claims Act’s waiver of sovereign immunity does not apply to “[a]ny claim arising out of ... malicious prosecution, misrepresentation, deceit, or interference with contract rights.”
See
28 U.S.C. § 2680(h);
Compton v. Ide,
IV. Conclusion
For the reasons stated herein, the Court hereby DENIES plaintiffs partial summary judgment motion on the False Claims Act and breach of contract claims, and GRANTS plaintiffs motion seeking dismissal of defendants counterclaims.
IT IS SO ORDERED.
Notes
. This suit was filed against Chilstead Building Cо., Inc., Terry Chilton, President, and Leo W. Smith, a Chilstead employee. Plaintiff requests the Court to dismiss this action against defendants Chilton and Smith. The Court grants the motion with prejudice, and thus Chilstead Building Co., Inc. remains sole defendant in this action.
. Paragraph 29 of the "Solicitation, Offer and Award” reads in part: "[Y]our offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) [t]he government solicitation and your offer, and (b) the contract award. No further contractual document is necessary.” PI. Mem. Exhibit A.
