United States of America Ex Rel. Charles R. Riley v. The Diran Company and Reliance Insurance CompanyUnited States of America Ex Rel. Charles R. Riley v. The Diran Company and Reliance Insurance Company
Charles R. Riley brought this suit under the Miller Act, 40 U.S.C. §§ 270a-270d (1976), to recover the balance due on his contract with The Dirán Company (Dirán), the general contractor on a project to expand the United States Army Reserve Center at Hammond, Louisiana. The Reliance Insurance Company (Reliance), also named as a defendant, is the surety on Dirán’s payment bond. Dirán appeals from a judgment awarding Riley damages and dismissing Diran’s counterclaim. We affirm.
Riley began work in late September 1973. He was to build brick walls with doorways through them. Dirán was to install the metal doorframes before Riley began the walls, but the frames were not at the job site when Riley was ready to start. He was nevertheless ordered to begin laying the walls while awaiting the arrival of the frames. This entailed additional difficulty and expense for Riley in later completing the wall sections around the doors.
Dirán was paid approximately every thirty days by the government as the work progressed. The subcontract provided that Riley was to be paid no later than 10 days after Dirán received payment. Despite the fact that Dirán was being paid for the masonry work even before Riley started work, Riley did not get his first payment until November 30, 1973. He was paid only once more, on December 14, 1973, for a total of $11,720.22.
The prime contract made Dirán responsible for quality control of all work on the project. Diran’s project manager, Johnny Hernandez, was the designated Quality Control Officer charged with ensuring that all work, including that of subcontractors, met the specifications in the contract. Hernandez supervised the work on a daily basis. He testified that he pointed out defects in Riley’s work as they were discovered and repeatedly asked Riley to remove excess mortar and wash the brick so that the true condition of the work could be assessed. Riley procrastinated, however, and never washed the walls.
Dirán gave Riley formal notice of default on January 22, 1974, and replaced him with another contractor on February 12, 1974. At that point the masonry work was 90% complete, although it was defective in certain respects, including: bricks were laid with the wrong face turned out, courses did not line up, control joints had been left out, and the walls had not been cleaned. The new contractor, who was hired on a cost plus basis, completed and corrected some of the work; it was finished by a third contractor brought in by Reliance after Dirán was defaulted by the Army on the prime contract.
Riley sued for the $23,300 due on the contract plus interest. Dirán counterclaimed for $23,000 as the cost of completing and correcting Riley’s work and damages incurred because of delay caused by Riley. The district court found that under the applicable Louisiana law 1 Riley had substantially completed the contract and was due the full contract price with deductions for the payments received, the cost of the brick purchased by Dirán for Riley’s account, and the cost of completing the work and correcting certain of the defects. Deductions were disallowed for other defects because the court found that Dirán had waived or was estopped from having Riley bear the cost of their repair. Diran’s counterclaim was dismissed.
On this appeal, Dirán first argues that no finding of waiver or estoppel is permissible on the record in this case. We disagree. Hernandez was Diran’s project manager on the job and the person responsible for overseeing the quality of Riley’s work. He testified that he made complaints to Riley almost daily about defects
I could have stopped the work, sir, but I’m after a finished product. Now, if he can run that brick and it’s a satisfactory job, well, whatever method he used to wash it down, or, whatever method he used to correct it, if it’s a satisfactory job, if it satisfies the Corps of Engineers or whatever, then, that’s fine. But, after it’s washed down and everything’s exposed and it’s not right, then the finished product is not any good.
Now, if he can get it up there where it’s satisfactory to everybody, if he can sell the thing, that’s fine. That’s good. He has a set of plans and specifications just like I got. He’s a mason contractor. He knows just exactly what he can sell and what he can’t sell. I shouldn’t have to point out everything to him and do his work for him.
First Supp. Record, vol. II, at 198-99. This testimony supports the court’s conclusion that Dirán, through Hernandez, intentionally permitted Riley to continue working despite the presence of known defects until it was too late to correct them without great cost. Hernandez took the attitude that if the Army accepted the work, that was fine; if the Army rejected it, that was Riley’s problem. But Riley’s contract was with Dirán, not the Army, and having permitted him to continue without correcting work it knew did not conform to the specifications, Dirán may not now be heard to object.
See Keating v. Miller,
Diran’s second argument is that the finding of substantial completion is demonstrably erroneous in view of the district court’s computation of the cost of completion and repair at $10,600. This amounts to 30% of the total contract price. Dirán contends that this compels the conclusion that the work was, in effect, only 70% finished, and this cannot be considered substantial completion under any circumstances. If Riley did not substantially perform, the argument continues, his only recovery is quantum meruit, but he offered no proof of the value of the work he completed and should recover nothing.
Dirán concedes that the question whether Riley substantially performed is one of fact. The detailed reasons for judgment filed by the district court in this case disclose a careful consideration of this issue and a conscientious balancing of the factors required by Louisiana law to be weighed in making such a decision. The district court was very familiar with the applicable rules,
see C. H. Leavell & Co. v. Board of Commissioners,
309 P.Supp. 626 (E.D.La.),
aff’d,
Dirán objects in passing to the court’s failure to credit it for the overhead and profit of the contractor brought in to complete the work. Dirán must bear this cost, however, since it prevented Riley from completing the work himself by ordering him off the job. The district court found that Dirán had intentionally breached the contract and by its breach precluded Riley’s full performance. The measure of damages on these facts is the contract price less the cost saved to Riley, which is the direct cost of completion, not the indirect costs occasioned solely by Diran’s breach. See 5 A. Corbin, Contracts § 1094 at 509 (1964); Restatement of Contracts § 346(2), Comment g (1932). This is the measure applied by the court here.
The judgment of the district court is AFFIRMED.
Notes
. Although this suit arises under the Miller Act, ordinary contract issues are governed by state law; inasmuch as a construction of the statute is not required here, no federal law questions are presented. See
United States ex rel. Au-coin Elec. Supply Co. v. Safeco Ins. Co. of America,
. On February 6, 1974, just before Riley was replaced on the job, Hernandez noted that the gable ends on one wall were too low and that the masonry contractor did not correct them.
. These cases are not distinguishable, as Dirán urges, on the basis that they did not involve defective work. In Keating, a cement slab was laid two feet shorter than called for by the plans. In Elite Homes, a slab was laid a foot lower than required by the contract. Thus, in both cases, known variances from the specifications were allowed to remain in the structures, and later complaints were held barred by the failure to object at the time. That is precisely the case here.