This is a petition for the assessment of land damages alleged to have been sustained by the petitioner by the construction of a high level toll bridge by the respondent over the Mystic Biver connecting Chelsea and the Charlestown district of Boston. The jury awarded damages in the sum of $262,950, of which they found $50,550 was due to damages resulting from the taking of an easement in the form of an air space over a part of the petitioner’s land and $212,400 was on account of dаmages resulting from the location of one of the piers of the bridge. The case is herb on various exceptions of the respondent.
The petitioner has owned and occupied since 1928 a parcel of land on the Mystic Biver in the Charlestown district of Boston which contains 232,770 square feet and borders for 434.53 feet along the pierhead and bulkhead line on the southerly side of the north channel of the river. The upper part of this area consists of the Beading dock or slip of 97,900 square feet and an area of 10,300 square feet covered by wooden wharves. The petitioner is engaged in the manufacture of plaster board or sheet rock and rock lath, a plaster base which is used largely as a substitute for wood or metal lath in constructing buildings. Bock gypsum, *132 the raw material for these products, is mined in Nova Scotia, and down to 1947 was transported by water to the Charles-town plant and other Atlаntic coast plants of the petitioner in bulk cargo vessels, with holds for the cargo, which were owned or chartered by the petitioner. These vessels owned by the petitioner measured a little over 361 feet in length and 52 feet 6 inches in breadth, and when loaded had a draft of 21 feet 6 inches. Their capacity was about 7,000 tons. The chartered vessels did not differ materially in type or dimensions from the petitioner’s vessels. These vessels were not unloadеd against the face of the petitioner’s wharf but were docked against a camel or wooden float 15 feet wide which was placed between the wharf and the vessel. This procedure was necessary as the water was too shallow next to the wharf and any dredging might endanger the sea wall which had been built subsequent to the Civil War by putting loose stones in a trench and building a masonry structure upon the stones. These vessels were unloaded by a crane trаvelling along a track so as to place its boom at right angles to the wharf and over the holds and removing a part of the cargo from each hold so as to avoid straining the vessel until the vessel was entirely unloaded.
The respondent was created by St. 1946, c. 562, as amended by St. 1947, c. 626, to build a bridge for vehicular traffic between Chelsea and Boston. It was authorized to locate the bridge, to acquire land and easements, to make contracts for its erection, to issue bonds, to collect tolls, and to supervise and maintain the bridge until its costs were fully paid, and the bridge was then to be turned over to the Commonwealth. In erecting the bridge a pier known as pier M2 was placed in the bed of the river upon land admittedly owned by the Commonwealth as a part of the public domain. The side of this pier was not parallel to the face of the petitioner’s wharf for the nearest downstream corner was 77 fеet and the upstream corner 95 feet distant from the wharf. This pier was completed on May 29, 1949.
The petitioner in 1946 contracted for the construction of two self unloading vessels which were larger than those it *133 had been using. These vessels were completed in 1947, but the first one did not arrive in Charlestown until August 20, 1948, after the cofferdam for the pier had been built. These new vessels were 441 feet in length and 64 feet in breadth, and their draft when loaded was 24 feet 6 inches. The cargо is discharged by permitting the gypsum to fall through gates at the bottom of V shaped holds, which regulate the flow, upon a belt conveying the gypsum to the stern and then by means of another belt to a shore installation equipment, by which it is deposited in one of the silos. This installation equipment was planned for in 1947 and was placed prior to August 20, 1948, at a distance from the downstream end of the wharf so as to be opposite to where the stern of the larger vessels would be docked far enough upstream so as to be safe from striking the pier. This installation equipment needed for the unloading of the larger vessels was too heavy to move to permit the travelling crane to pass and so prevented the latter from functioning efficiently in the unloading of the bulk cargo vessels. The crane’s track had been shortened from 223 feet to about 150 feet. The installation equipment unloaded the larger vessels from the stern and, it being dangerous to dock these vessels between the wharf and the pier, this installation device could not be placed nearer to the downstream end of the wharf than it was. It was necessary for the petitioner to use both types of vessels as the smaller vessels could operate during the winter from a port on the Bay of Fundy where the larger vessels could not operate and when Hantsport, the port regularly used by the larger vessels, was closed because of ice. The petitioner had storage facilities for only a three weeks’ supply of gypsum, and an interruption of transportation would cause a closing of its plant resulting in a loss of about $8,000 a day. The petitioner in May, 1948, purchased a parcel having 100 feet river frontage next adjacent upstream to the Reading slip and contemplates closing the open mouth of this slip and extending the tracks of the travelling crane aсross the slip and onto this new parcel. We need not mention the other various losses which the *134 petitioner contends it has sustained by the building of the pier or the amount that the market value of its premises has thereby decreased, for the respondent concedes that, if the petitioner is entitled to recover damages by reason of the construction of the pier, there was evidence sufficient to support the finding of the jury that the damagеs due to this cause amounted to $212,400. The question of law presented is whether the respondent is liable to pay such compensation.
Before passing to this question of law, it is necessary to mention that the respondent on September 8, 1949, took an easement of an air space over part of the petitioner’s property, the base of which was 123.5 feet above mean low water,
1
about 152 feet in length and about 46 feet in width. The air spaсe taken was of unlimited height above this base. The base of this horizontal plane had an area of 6,621 square feet. The bridge occupies the lower.part of this air space. The respondent makes no objection to the award of $50,550 on account of the taking of this easement which actually interferes with the beneficial use of the land and which the parties properly regarded as the taking of an easement on the petitioner’s land.
Smith
v.
New England Aircraft Co. Inc.
The important question is whether the petitioner is entitled to compensation for damages due to the construction of the pier which is located in the bed of a navigable river at a place always covered by tide water and upon land owned by the Commonwealth as a part of the public domain. The
*135
Commonweаlth consented to such use of the locus as may be “necessary for the construction or operation of the project,” St. 1946, c. 562, § 14,
1
for which it was to receive no compensation. § 5. No part of the pier rests upon any land, in which the petitioner has any proprietary interest.. The placing of this structure by a governmental agency authorized by the Legislature to do so, for the accomplishment of some public purpose, or by a rаilroad or some other pub-lie service corporation if likewise authorized, would not constitutionally require the payment of compensation to a landowner who had thereby sustained an impairment of access to his wharf. Our Constitution, Declaration of Rights, art. 10, merely provides that “whenever the pub-lie exigencies require that the property of any individual should be appropriated to public use, he shall receive a reasonable compensation therefor.” The owner of a wharf upon land bordering on an arm of the sea is not entitled to compensation under our Constitution or at common law if navigation between his property and the sea is destroyed by the authorized construction of a bridge without a draw between his property and the sea. It was said in
Butchers Slaughtering & Melting Association
v.
Boston,
The grounds upon which these decisions rest, including the origin of the rights of the Commonwealth to tide water lands and to supervise and regulate the public right in navigable waters in the interests of navigation — and it has sometimes been said for other public purposes
1
— and the privileges of owners abutting on navigable waters, have been exhaustively examined and settled in leading decisions by eminent judges and need not be repeated hеre.
Commonwealth
v.
Alger,
The rights of the Commonwealth in tide water lands are subject to the authority of the United States for the purpose of improving navigation, and if the pier had been erected by the Federal government in the course of construction of a high level bridge to take the place of the old drawbridge and so in the interest of navigation and damages, similar to those now in question, had been thereby sustained in its property by the petitioner, the latter would not be entitled to compensation under the Constitution of the United
*137
States
1
or at common law.
Gibson
v.
United States,
The Legislature, however, is not limited in providing compensation to damages which the landowner is entitled to receive as a matter of constitutional right but may extend compensation to instances where an exercise of eminent domain would result in a real hardship to one whose property been damaged or injured if he were deprived of compensation.
Burr
v.
Leicester,
The respondеnt contends that damages similar to those sustained by the petitioner’s land on account of the pier have never been allowed as compensable damages where the land has been injured by a public improvement. It relies upon the earlier cases which have already been cited. Many of these earlier cases were decided upon general principles without any reference to the special statutes in accordance with which the public improvement was undertaken, or to the general laws governing the payment of compensation in eminent domain cases. It was held in
Boston & Worcester Railroad
v.
Old Colony Railroad,
Our inquiry is whether the Legislature intended that the damages caused by the pier were to be paid for by the respondent. The pertinent part of § 14 reads as follows: “Any person damaged in his property by the exercise of any of the powers granted by this act may recover his damages from the authority under chapter seventy-nine of the General Laws.” The terms of the section are broad and general. The damages caused by the erection of the pier come within the. description in the. act of the damages for which compensation is to be made. The respondent was held liable in
Woodbury
v.
Beverly,
The damages sustained by the construction of the bridge were to be enforced and assessed in accordance with G. L. (Ter. Ed.) c. 79. The present petition was properly brought under § 12 of c. 79
1
to obtain all the damages sustained by the construction of the bridge. This structure was planned, erected, and completed as a single public improvement.
Quinn
v.
Mayor & Aldermen of Springfield,
The evidence was sufficient to warrant an inference at least that the petitioner had the right to lay vessels against its wharf for the purpоse of unloading them,
Jubilee Yacht Club
v.
Gulf Refining Co.
As it does not appear that the location and construction
*141
of the pier were effected by any formal vote or order of the respondent, it is contended that the damages thereby sustained came from an act in pais and that the petition for damages must be filed within the time prescribed by G. L. (Ter. Ed.) c. 79, § 10.
1
The respondent also contends that the pier was built up to mean low water on January 24, 1949, when all the injury to the petitioner’s land had been fully accomplished, and that the рetition filed more than a year thereafter was filed too late. The point is open although not pleaded.
Nicklas
v.
New Bedford,
The Legislature granted permission to the respondent to use the land of the Commonwealth for the construction of the bridge, and there was no need of any formal vote or order by the respondent to effect any “specific taking, entry, seizure or other act” mentioned in G. L. (Ter. Ed.) c. 79, § 10. The quoted words “specific taking, entry, seizure” are unequivocal terms denoting that the landowner has actually parted with his property or its possession or some interest therein. They signify a physical invasion of the land and they would comprehend a trespass if unauthorized by the owner. Each of them represents a completed transaction. The respondent relies upon the words “other act” appearing in this section as applying to the erection of the pier. The statute refers to an act which causes damage of one kind or another. We think the words “other act” must be construed to mean something of the same kind and character as to definiteness and finality in creating rights in the landowner as do the words with
*142
which they are associated. The building of the pier required several months. At some stage in its construction it began to deprive the petitioner of the use of the downstream end of its wharf. The respondent contends that the full extent of the damage was realized when the pier reached mean low water level on January 24, 1949, but it is admitted that its construction continued thereafter and that it was not finished until May 29, 1949. The statute requires a definite and distinct act as beginning the period in which a petition for damages may be filed. The Legislature did not intend to put the burden upon the landowner to determine when in the partial performance of a piece of work the period for bringing a petition would start to run against him. See
United States
v.
Dickinson,
In view of what has been said it is not necessary to discuss any of the specific exceptions taken by the respondent. All of them have been considered. The exceptions must be overruled.
So ordered.
Notes
The base of this space was about 110 feet above the surface of the petitioner’s land and a short distance from the exhaust stacks which are between the silos and almost under the bridge. These silos were about 80 feet high. The tops of the stacks are so near the base of the bridge that it will be necessary to move the stacks.
The sections hеreinafter, mentioned, unless otherwise designated, refer to the sections contained in St. 1946, c. 562.
Many of our cases involved the construction of railroad bridges, such as
Davidson
v.
Boston & Maine Railroad,
The Fifth Amendment to the Constitution is the only pertinent provision and reads in part as follows: “nor shall private property be taken for public use, without just compensation.”
“The damages for property taken under this chapter shall be fixed at the value thereof before the taking, and in сase only part of a parcel of land is taken there shall be included damages for all injury to the part not taken caused by the taking or by the public improvement for which the taking is made .... In determining the damages to a parcel of land injured when no part of it has been taken, regard shall be had only to such injury as is special and peculiar to such parcel . . ..”
Indeed, this section is captioned “Measure of damages,”
Charles I. Hosmer, Inc.
v.
Commonwealth,
Section 10 so far as material reads as follows: “In case of a specific taking, entry, seizure or other act causing destruction or damage or depriving the owner of the use of his property permanently or for a definite period of time the damages shall be assessed as of the date of such taking, entry, seizure or other act and the right thereto shall vest on such date and a petition for an award of damages therefor under this section may be filed within one year thereafter; otherwise damages shall be assessed with respect to any parcel of property as of the date when such property was first injuriously affected, the right thereto shall vest upon the completion of the public improvement which caused the injury, and a petition for an award of damages therefor under this section may be filed within one year after such completion.”