United States for the Use and Benefit of Kinlau Sheet Metal Works, Inc. v. Great American Insurance CompanyUnited States for the Use and Benefit of Kinlau Sheet Metal Works, Inc. v. Great American Insurance Company
Appellant supplier sued a general contractor and its payment bondsman when a subcontractor failed to pay supplier in full for three improvement projects on a Air Force base. These were a theater job (job 1) that ended on August 16,1973, a nondestruct-lab job (job 2) that ended on May 3, and a child-care-center job (job 3) that ended on May 23. This appeal challenges the lower court’s finding that appellant had not satisfied the 90-day notice requirement which the Miller Act,
Section 270b of the Miller Act provides that on any federal construction project for which
upon giving written notice to [the general] contractor within ninety days from the date on which [the supplier] did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed, (emphasis added)
As we held in
United States ex rel. Jinks Lumber Co. v. Federal Ins. Co.,
AFFIRMED.
Notes
.
See also United States ex rel. Bailey v. Freethy,
. At which time the subcontractor, who first informed the supplier in August that it intended to make no additional payments, was still promising to pay. In fact, it did make four substantial payments in early August, about which appellant did not advise the general contractor or its surety.
. The body of this letter, addressed to the subcontractor, states:
Enclosed is a copy of our record of your due and past due accounts on the above referenced jobs. Repeated requests for payment has been made. Please help us keep a friendly relationship and keep this matter out of the courts by letting your check come forward now.