36 Ga. App. 396 | Ga. Ct. App. | 1927
The Provident Trust & Security Company brought suit in Fulton superior court against Palmer Brick Company, as principal, and United States Fidelity & Guaranty Company, as surety, upon a bond. This bond was in the sum of $10,000 and was executed to indemnify and save harmless the Provident Company from any pecuniary loss resulting from the breach by the Palmer Company of any of the terms arid conditions of clause 4
J. W. English Jr. was president of the Palmer Company. The bond in suit provided that the surety should not be liable for a greater sum than the penalty of the bond or subject to any action or proceeding thereon instituted later than February 3, 1913. The suit was not filed until March 31, 1913.
Among other things . the petition alleged: The plaintiff, in terms of clause 4 of the lease contract, with the Palmer Company, furnished for repairs and for the costs of operating the kiln during the first test a sum in excess of $10,000. This test proved that the kiln was a failure, demonstrating that it did not possess the required capacity as to production. J. W, English Jr', did not elect to make a second test. Both parties to the lease, however, desired that the kiln should be made a success, and if this could be done, that the lease should be continued in force; so that notwithstanding the Provident Company considered that the Palmer Company had now breached its contract and that the liability of the surety company had attached, the Provident Company, on November 4, 1912, after many negotiations between it and the defendants “relative to the breaches of the contract aforesaid and the liability of the” defendant surety company upon its bond, wrote the latter company a letter with regard to the matter, as follows: “In re: Bond dated August 3, 1912, made by the Palmer Brick Company, as principal, and your company as surety,- to our company, the 'Provident Trust Company, as obligee, we beg to say that on the 28th day of October, 1912, we wrote you a letter in which we stated that divers breaches of said contract had been committed as therein specified and set forth. Since writing you said letter we have taken up the situation as a whole, with the view of endeavoring to
The surety company answered, and also filed general and special demurrers. The general demurrer was aimed at the failure of the plaintiff to file suit before the expiration of the contractual limitation named in the bond. In response to this demurrer the plain
The case was then referred to an auditor. The auditor heard evidence and made his report, which was adverse to the plaintiff. When the court was about to render final judgment against the plaintiff, in accordance with the conclusions of the auditor, the plaintiff moved to amend its petition by alleging that because of certain facts the surety company had waived its right to insist upon the contractual limitation as expressed in the contract, and was prevented also from pleading the same by the doctrine of estoppel. This amendment was allowed over various objections interposed thereto by the surety company. In view of this amendment and on motion of the surety company the court recommitted the case to the auditor, with power to take such additional testimony as might be offered in connection with the amendment, but providing that “for the purpose of this rehearing, the entire case is recommitted to the said auditor with leave to file a supplemental report.” The auditor, after hearing evidence offered only by the surety company, filed his report under the recommitment, in which his conclusions of law and of fact were for the most part in favor of the plaintiff. There w;as one notable exception, however, in his conclusions of law, having reference to the liability of the surety for interest. To this conclusion the plaintiff excepted, and to various other conclusions, both of law and of fact, the surety company excepted.
Pending the action, the Provident Company was adjudicated a bankrupt, and J. P. Allen, as trustee in bankruptcy, was made a party plaintiff in its stead by an appropriate order of the court on November 2, 1914. On March 29, 1923, the surety company made a written motion alleging that Allen, as trustee, on February 24, 1916, sold and transferred his rights in this suit, including the bond upon which it was based, to Mrs. Emma Koehler, and that, having disposed of all other assets of the estate, he was, on April 7, 1916, fully and completely discharged as trustee by the bankruptcy
The court overruled all exceptions by either party to the au
Ultimately the case proceeded to trial before a jury on the exceptions of the surety company to the auditor’s conclusions of fact. The jury found against each of the defendant’s exceptions, after which the defendant filed a motion for a new trial which, as amended, contained the usual general grounds and a number of special grounds. After the verdict in favor of the plaintiff, the defendant moved the court, upon the whole record, to render a judgment in its favor notwithstanding the verdict. This motion and the motion for a new trial were both overruled, and the defendant excepted.
Exceptions pendente lite were taken to the various rulings with which the defendant was not satisfied, and these exceptions are presented in the record for our consideration. The substituted plaintiff, Mrs. Emma Koehler, also sued out a bill of exceptions, in which she complains of the judgment because, as alleged in exceptions pendente lite, the court erred in overruling her exceptions to the auditor’s conclusion of law refusing to allow a recovery for interest. Some further facts will be stated in the opinion.
Notwithstanding the voluminous record and the many exceptions and assignments of error, the principles which must control our judgment are few. In our view of the case, the rulings made in the opinion below are controlling, rendering it unnecessary to deal seriatim and in detail with the many exceptions and assignments.
This case first went to the Supreme Court and was by that court transferred to this court. In the opinion of that court, rendered in connection with its judgment transferring the case, it was said: “An amendment to the petition was filed, seeking to reform the contract on the ground that the agreement to modify included modification of the above-quoted clause of the bond, but alleging that such part of the agreement was omitted from the letters by mutual mistake of the parties. The case was submitted to an auditor, and his report found against the application to reform the contract. The plaintiff filed exceptions of law and fact to the auditor’s report, and at a hearing the judge announced his decision
Under the auditor’s construction of the contract the Palmer Company, the lessor, breached its contract and became liable for the sums advanced by the plaintiff for repairs and also for operating the kiln during the first test, as soon as this test was made and proved that the kiln did not possess the capacity as to production which was required under the contract. From this construction it follows that when the Palmer Company had failed to reimburse the plaintiff for these expenditures and the plaintiff had demanded payment of the surety company, the cause of action against the latter was ripe. Counsel for the surety company, however, contend that the bond was-not breached until and unless a second test was made by English and this test also proved unsuccessful. The determination of the question thus presented will
The amendment in which the plaintiff sought to set up grounds of waiver and estoppel against the surety company, so as to avoid the effect of the contractual limitation of the bond that any action or proceeding thereon should be instituted not later than February 3, 1913, alleged, among other things, the following: On October 28, 1912, it had been demonstrated by the first test provided for by clause 4 of the lease contract that the kiln, with' the outlay originally contemplated, could not be made to meet the requirements of the contract as to production, and that since English did not exercise his right to make a second test, but failed and refused to do so, the Palmer Company and the surety com
“20. With this situation existing, petitioner shows and avers that proper officers of the Provident Company, the Palmer Company, and the U. S. Fidelity Company met and held a conference in the office of T. B. Felder, on Nov. 4, 1912, said officers being G. H. Fiedler, president of the Provident Company, J. P. Allen, vice-president, T. B. Felder, attorney of said company, James W. English Jr., president of Palmer Company, W. A. Smith, general agent of U. S. Fidelity Company, Victor L. Smith, its attorney, and A. C. Supplee, underwriter for the said Fidelity Company.
“21. Petitioner shows that at said conference the officers of the Provident Company and the Palmer Company discussed the feasibility of making further repairs and doing additional constructive work on said kiln and securing suitable cars, either by purchase or rebuilding those already in use, in order to handle the brick through said kiln; that it was believed by said Provident Company and Palmer Company that by making said improvements and doing said additional work that said kiln could be made a success and would successfully burn 30,000 commercial hard brick per day of 24 hours for a period of 60 days; and it was thereupon agreed that said Provident Company would furnish additional snips under clause 4 of said original contract to the extent of $3,000, in order that said improvements might be made and thereafter a 60-day test made to determine if said kiln could be made a success. This agreement was made in the presence and with the consent and acquiescence of the surety company, and it was discussed in the presence of the officers of the defendant Fidelity Company, that the making of such expenditures and the conducting of such test could not be accomplished by February 3, 1913,
“22. Petitioner further shows and avers that from a discussion had in the office of T. B. Felder on November 4, 1912, between the officers of said Provident Company and Palmer Company, in the presence of the officers of the Fidelity Company, it was manifest to the representatives of the said Fidelity Company that the further work on said kiln and the carrying out of an additional 60-day test could not be completed by February 3, 1913, but that if such additional work were undertaken and such additional test were made, an additional period beyond' February 3, 1913, would be required; and it was the intention on the part of the said Provident Company, if it advanced such additional sums and modified the then liability of said defendants that had already accrued on said bond, that such additional time should be granted as would be reasonably necessary.
“23. Petitioner shows that the whole situation relative to the matters hereinabove referred to was discussed by the plaintiff, defendant, Palmer Company, and James W. English Jr., before and in the presence of the defendant surety company, and to the surety company that it was the urgent desire of the plaintiff, the defendant, Palmer Company, and English to repair and reconstruct the kiln and make an additional 60-day test. The plaintiff proposed and intended to spend money to construct the kiln, and defendant, Palmer Company, and English consented thereto, and all of said parties intended to have the surety consent to remain bound under the bond and to have the surety consent to extend the time limit of the bond, which limit, as fixed in the bond, was February 3, 1913; and all of said intentions and consent were so declared to the surety at their conference.
“24. Petitioner shows that although, in the letter written by the plaintiff to the surety company in reference to said matters, there was no definite proposal with reference to an extension of the time limit of the bond, and although the surety did not by express words agree to extend the time limit, that the leaving out of its letter said intention to have the time limit extended was from no intention on the part of the plaintiff to waive the claim
“25. Petitioner shows and avers that said surety company knew and in good faith must have known that said plaintiff was incurring said additional expense for making said improvements and for conducting said test on the faith that said surety company waived and would not claim that the.time limit of said bond should expire February 3, 1913.
“26. Petitioner shows that said surety company, with full knowledge of all the facts and circumstances hereinbefore set forth, stood by and permitted said plaintiff to go ahead and make said further improvements and expend large sums of money, exceeding the amount of $3,000 for perfecting and reconstructing said kiln and for conducting the test referred to in clause 4 of the said contract, and to forego its right to bring suit against the surety on said bond prior to February 3, 1913, on the liability that had accrued on or about October 28, 1912, as herein alleged, without notifying plaintiff that said surety company had not agreed and did not intend to extend said original time limit, and would not do so, as it was in good conscience and equity required to do, unless it was willing for such time limit to be waived or extended.
“27. Petitioner shows and avers that said conduct of said surety company in standing by with the knowledge hereinabove specified and allowing said plaintiff to expend said large sums of money and to forego its right to sue on said bond prior to February 3, 1913, in the belief that said surety company would not insist on said time limit and the knowledge of the surety company that but for the belief that said time limit had been waived, plaintiff
“28. Petitioner shows that while said surety company may not have, by any express statement or agreement in writing, consented that said additional work could be done and said 60-day test could be made without prejudicing the rights of said plaintiff under the terms of said bond, it did by its conduct and its knowledge, as herein alleged, and its duty to speak when it knew of the intention and expectation of said plaintiff, estop it from taking advantage of said limitation in said bond, and did thereby waive said limitation in said bond, and that to allow said defendant surety company now to plead said time limitation would be a fraud upon said plaintiff.
“29. Wherefore plaintiff shows to the court that by the statements hereinabove set forth, said defendant surety company is prevented by law from pleading said time limit, both under the doctrine of waiver and estoppel; and the petitioner prays that the court so find.
“30. Petitioner further shows that in view of the agreement entered into between the plaintiff and the defendant surety company on November 4, 1912, by virtue, of which said defendant company consented that said plaintiff should go ahead, expend at least $3,000 in making further improvements on said kiln, and conducting a 60-day test in the burning of brick after the completion of said kiln, and in further view of the statements made at the conference held on November 4, 1912, that more than 30 days would be required to secure cars and make the other improvements contemplated in connection with said kiln, that said time limit of February 3, 1913, was expressly waived.”
The letters referred to in paragraph 24 of this amendment are those which are copied in full in the statement of facts preceding this opinion.
The court did not err in allowing the plaintiff to amend the petition so as to set up waiver and estoppel. Although the petition might not have set forth a complete cause of action prior to this amendment, that fact alone would not necessarily be cause for refusing an amendment, adding matter of substance. Ellison
In the use of the word “plaintiff” we have not, up to this time, intended to refer to any particular person as the party prosecuting the suit, but have used the term in a more or less general way to designate any one of the persons who have occupied the position of plaintiff during the course of the litigation. The Provident Company, after filing the suit, was adjudicated a bankrupt. On November 2, 1914, J. P. Allen, as trustee in bankruptcy, was made party plaintiff in its stead. The trustee, after selling and assigning the cause of action and the suit, with all other assets of the bankrupt, to Mrs. Emma Koehler, applied for and obtained discharge from his trust by the court of bankruptcy, and notwithstanding the knowledge of Mrs. Emma Koehler and her attorneys of this fact, the case continued in his name through certain proceedings, namely, an order allowing an amendment to the petition;’ an order recommitting the entire case to the auditor; and the hearings before the auditor and the making and filing of his report. Immediately upon the discovery of the trustee’s previous discharge the surety company moved to quash the proceedings just enumerated. Attorneys for Mrs. Koehler filed a motion in which she alleged that “since the purchase by her of the choses in action involved in said suit, she has been the real party at interest in said suit and the person having the legal interest in the same, and the master of said suit, and has been prosecuting the same by her said attorneys at law, in the name of Allen, trustee, etc.”; and that she “confirms and completely and fully ratifies the action heretofore taken by her attorneys in said suit in her behalf, and says that she is the only person having any interest in said suit or the proceeds thereof, and the right to prosecute the same.” This motion concluded with a prayer that the name of the trustee be stricken and that the name of Mrs. Koehler be substituted instead. By a stipulation in the record the affidavits attached to the respective motions were ac
In our opinion the suit did not cease to have a party plaintiff merely because the trustee was discharged in bankruptcy. The situation is unlike that which arises on the death of an individual plaintiff, in which case the proceedings must be halted until some one else is made a party. Allen continued to live and to act in this litigation as trustee in bankruptcy. He acted without authority, it is true, but the mere fact that ho acted without authority would hot, ipso facto, remove him from the case as a party. Assuming that ho was subject to removal and that if objection had been made the court would not have permitted him to continue the action even for the use of the assignee (see Hargrett v. Jolley, 34 Ga. App. 662 (2), 130 S. E. 602), the proceedings were not suspended where no such objection was made and acted upon. The question relates not to the existence of a party plaintiff, but to the authority of a plaintiff actually existing and conducting the litigation. The surety company might have raised the question of authority, if necessary for its protection. It did ultimately raise the question, but was met with conclusive proof that Mrs. Koehler, the assignee of the cause of action, had been present through hef attorneys at all stages of the case, approving and ratifying all that had been done or was being clone in the name of Allen as trustee, and that no other person had any right or interest in the suit or the cause.of action. We think this was a complete answer to the defendant’s motion to quash. Peoples Bank v. Cleveland, 117 Ga. 908 (44 S. E. 20); Gate City Cotton Mills v. Cherokee Mills, 128 Ga. 170 (3) (57 S. E. 320); Liverpool &c. Ins. Co. v. Ellington,
What we have said with reference to the motion of the surety company to quash the proceedings will apply equally to the exceptions to the order allowing Mrs. Koehler to be substituted in place of the trustee as party plaintiff. This is true because an examination of the record discloses that the objections to making Mrs. Koehler a party were limited to the same grounds as those which were relied on in the motion to quash. Thus we are not confronted with the question as to whether the order making Mrs. Koehler a party was a violation of the rule that new and distinct parties can not be added by amendment unless expressly authorized by law, or of the general principle that the plaintiff, in order to recover, must show that he had the title to the cause of action at the institution of the suit. See Suwanee Turpentine Co. v. Baxter, 109 Ga. 597 (35 S. E. 142); Dunlap-Huckabee Auto Co. v. Central. Ga. Auto Co., 31 Ga. App. 617 (122 S. E. 69). But, without deciding this question, it would seem that the purchaser of a cause of action at a bankruptcy sale upon which a suit is pending in behalf of the trustee in bankruptcy as plaintiff would not be a new and distinct party within the first of the rules mentioned, and that such purchaser, if made a party, would not be prevented from recovering on the theory of a want of title at the filing of the suit. See Gate City Mills v. Cherokee Mills, supra, and § 46 of the bankruptcy act. There was, no error in the rulings to which we have just alluded.
On principle, the above disposes of all contentions of the plaintiff in error. There was no material error in any of the court’s rulings. The verdict against the exceptions to the auditor’s conclusions of fact was as to each exception authorized. There was no merit in any of the special grounds of the motion for a new trial.
But it is said that if interest be added, the liability of the surety company will be increased beyond the penalty of the bond. A sufficient reply to this contention is found in Frink v. So. Express Co., 82 Ga. 33 (5) (8 S. E. 862, 3 L. R. A. 482). The stipulation that the surety was not to be liable for an amount exceeding $10,000 clearly had reference to the principal, and was not intended to relieve the surety from liability for interest if it failed to pay the principal when due. See further, in this connection, 9 C. J. 130, § 242, and citations. We have here no cross-bill of exceptions. There are two independent bills.
Judgment in case No. 17237 affirmed; in case No. 17238 reversed.