The facts in this Miller Act case present a question of law: whether the delay and termination components of the subcontractor’s Miller Act claim constitute “labor or material [furnished] in the prosecution of the work provided for in [the] contract.” 40 U.S.C.A. § 270b(a) (1986).
Plaintiff T.M.S. Mechanical Contractors, Inc., subcontractor on a government construction project, appeals from a judgment denying its delay and termination claims against Miller Act surety Millers Mutual Fire Insurance Company of Texas. Defendant Millers Mutual Fire Insurance Company of Texas cross-appeals from a judgment of $100,104.19 plus interest and costs awarded to the Plaintiff on its contract work claim.
I. FACTS AND PROCEDURAL HISTORY
The Craftsmen, Inc. (“Craftsmen”) contracted with the Veterans Administration (“Government”) on April 5,1984 to perform fire and safety corrections on the Veterans Administration Medical Center in Waco, Texas (“Contract”). Craftsmen secured a payment bond from Millers Mutual Fire Insurance Company of Texas (“Millers”), as required by 40 U.S.C.A. § 270a(a) (1986)
Craftsmen subcontracted all the mechanical work under the Contract to T.M.S. Mechanical Contractors, Inc. (“TMS”) on May 4, 1984 (“Subcontract”). The Subcontract incorporated the Contract’s plans, specifications, and general conditions of the specifications. TMS based its Subcontract price of $727,000 on a bid that considered the value of the labor and materials necessary to complete the Subcontract work, overhead, profit, tools and equipment, labor burden, insurance costs, food, and shelter.
[b]efore any contract, exceeding $25,000 in amount, for the construction, alteration, or repair of any public building or public work of the United States is awarded to any person, such person shall furnish to the United States the following bonds, which shall become binding upon the award of the contract to such person. ... (2) A payment bond with a surety or sureties satisfactory to such officer [awarding the contract] for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person.
After discovering asbestos in some of the buildings involved in the performance of the Contract, the Government issued change orders enlarging the scope of the Contract work to include asbestos abatement. The' Government partially terminated the Contract on October 10, 1985 pursuant to paragraph 18 of the Contract, entitled “Termination for Convenience of the Government.”
Upon receipt of a Notice of Termination from the Government, Craftsmen in turn terminated the Subcontract. At that time, TMS had provided $387,735.00 worth of labor and materials in the performance of the Subcontract and $485,845.90 in the performance of the change orders. TMS, however, continued to provide labor and materials until March of 1986.
TMS subsequently sued Craftsmen as prime contractor and principal on the Bond and Millers as surety on the Bond,
II. THE MILLER ACT
This is a Miller Act
[e]very person who ... furnish[es] labor or material in the prosecution of the work provided for in [the] contract ... who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done ... or material wasfurnished ... for which such claim is made, shall have the right to sue on such payment bond for the amount ... unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him.
40 U.S.C.A. § 270b(a) (1986).
The Supreme Court has instructed us to liberally interpret the Miller Act “to effectuate the purpose of Congress.” Illinois Surety Co. v. John Davis Co.,
Certain limitations, however, stem from the language of the Miller Act. The Act extends the right to sue on the payment bond “to those who ha[ve] a contractual agreement with the prime contractor or with a ‘subcontractor.’ ”
The central issue here concerns another, still-evolving limitation on the scope of a supplier’s recovery against a Miller Act surety: the extent of recoverable “labor or material [furnished] in the prosecution of the work provided for in the [government construction] contract.” 40 U.S.C.A. § 270b(a) (1986). TMS contends that the district court erred in denying recovery for amounts expended because of delayed performance and partial termination. We examine each of these claims separately.
A. Delay
TMS claims that delays caused by the asbestos abatement work dramatically increased its direct and indirect project overhead.
Many courts have confronted delay claims in cases brought on Miller Act payment bonds; some primarily consider the cause of the delay, e.g. United States ex rel. Superior Insulation Co. v. Robert E. McKee, Inc.,
We are persuaded by the Court of Appeals for the Eleventh Circuit’s recent decision in United States ex rel. Pertun Construction Co. v. Harvesters Group, Inc.,
In Pertun the contractor contracted with the Navy to construct improvements at the Reserve Training Center in Miami and secured the requisite Miller Act payment bond from its surety. The contractor subcontracted the concrete work to a subcontractor. Various problems, including the discovery of toxic wastes and the lack of running water and electricity on site, delayed the beginning of work on the project. Once construction started, the contractor’s failure to schedule and supervise its subcontractors’ work translated into additional delays. The contractor wrongfully terminated the subcontract before the subcontractor completed its work and refused to allow the subcontractor to return to the construction site to finish work or collect its tools and equipment.
The district court granted the subcontractor recovery against the surety for
We agree with the reasoning of the Eleventh Circuit and thus hold that the district court erred in concluding that none of the components of TMS’s Delay Claim were recoverable against the Miller Act surety. We stress, however, that the subcontractor can only recover from the surety for additional or increased costs actually expended in furnishing the labor or material in the prosecution of the work provided for in the contract and attributable to the delay.
Our decision in United States ex rel. Edward E. Morgan Co. v. Maryland Casualty Co.,
We held in Morgan that the use value of the subcontractor’s own equipment for the period of delay did not constitute “labor or material” within the meaning of the Miller Act. Morgan,
B. Partial Termination
TMS asserts that the Government’s partial termination of the Contract for its convenience and Craftsmen’s subsequent termination of the Subcontract resulted in significant costs to TMS.
Moreover, the language of the Contract buttresses our holding that a subcontractor cannot recover on a Miller Act payment bond for the cost of labor and materials provided after the termination of work under a government construction project. The Contract provision entitled “Termination for Convenience of the Government” incorporated 48 C.F.R. § 52.249-2 (1984) of the Federal Acquisition Regulations (“FAR”),
III. CONCLUSION
For the reasons stated in this opinion, we REVERSE in part, AFFIRM in part, and REMAND for further proceedings in accordance with this opinion.
Notes
.In relevant part, 40 U.S.C.A. § 270a(a) provides that
. The district court found that the Government partially terminated the Contract for its own convenience, not because of a default on the part of Craftsmen, the contractor.
. This Court granted TMS’s motion to sever for purposes of proceeding against the non-bankrupt appellee, Millers, on February 6, 1991.
. Pursuant to an Indemnity Agreement executed in favor of Millers, Millers filed a third party complaint against Craftsmen, Joseph Breedlove, J.D. Richmond, Jr. and Doris Richmond ("In-demnitors"), seeking indemnity for all costs, fees, and expenses incurred because of its issuance of the payment bond. The Indemnitors agreed to an entry of judgment of indemnity against them for the $176,190.89 previously paid by Millers to TMS, plus $100,104.19 awarded to TMS on its contract work claim against Millers, $20,000.00 attorney’s fees, and $18,018.75 in pre- and post-judgment interest.
. Jurisdiction was correctly based on 40 U.S.C. § 270b(a) in the district court and on 28 U.S.C. § 1291 in this Court.
. We briefly dispose of the issues raised by Millers in its cross-appeal. First, the "pay-when-paid” clause in the Subcontract does not preclude TMS's recovery on its contract work and change order claim because under the Miller Act, the liability of the contractor is to the subcontractor, despite non-payment by the government to the contractor. See Fanderlik-Locke Co. v. United. States ex rel. Morgan,
Second, Craftmen’s alleged failure to notify Millers of “material alterations” to the Contract fails to discharge Millers from its liability on the Bond because Millers waived notice of "duly authorized modifications” of the Contract in the Bond. See infra note 8.
Third, because we will reverse an award of costs "only on a clear showing of abuse of discretion,” we affirm the district court’s award of costs to TMS. Fogleman v. Arabian Am. Oil Co.,
. 40 U.S.C.A. §§ 270a-270f (1986). The Miller Act replaced the Heard Act in 1935. United States ex rel. Texas Bitulithic Co. v. Fidelity and Deposit Co.,
. Under the Bond secured by Craftsmen, "if the Principal shall promptly make payment to all persons supplying labor and material in the prosecution of the work provided for in said contract and any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications to the Surety being hereby waived, then the ... obligation shall be void and of no effect.”
. See Standard Accident Ins. Co. v. United States ex rel. Powell,
. The district court found that TMS entered into the Subcontract with Craftsmen, which entitled it to seek recovery on the Bond for the amount allegedly unpaid at the time it brought suit.
. TMS filed its complaint within “one year after the day on which the last of the labor was performed or material was supplied by [it].” 40 U.S.C.A. § 270b(b) (1986).
.TMS asserted that the delay resulted in the following costs, totalling $467,738.00: 1) direct project overhead, including overhead labor (salaries for supervisory personnel, laborers, and a secretary, plus 40% of the salary expense for "decreased efficiency for demobilization and re-mobilization” and 28.76% of the salary amount for "labor burden”) and expenses (offices, buildings, trailers, vans, trucks, equipment, tools, utilities, housing rental, fuel, subsistence, insurance, postage, pulmonary tests on employees, and copy charges from increased paperwork); and, 2) indirect project overhead, including accounting and attorney fees, amounts paid to settle sub-subcontractors’ delay claims, general project overhead figured at 21.19% of all items listed above, and profit of 20% on all items listed above, including general project overhead (collectively, “Delay Claim").
. Pertun relied on the logic of three cases considering similar claims under the Miller Act: United States ex rel. Heller Electric Co. v. William F. Klingensmith, Inc.,
We find the rationale underlying Mariana, the most instructive of the three decisions, quite persuasive. The court held that a Miller Act surety is liable to a subcontractor for increased costs for labor or material furnished "‘in the prosecution of the work provided for in- [the] contract,’ ” provided that the costs were actually incurred due to delay not attributable to the subcontractor. Mariana,
The court reasoned and we agree that the subcontractor's claims fell "within the literal language of the statute” because the outlays were "for labor or materials that were furnished and used by the subcontractor in performing his contractual obligations”; the recovery "afford[ed] the subcontractor the financial protection of an action against the surety’ and thus ”promote[d] the underlying purpose of the Miller Act”; and, finally, the principle of unjust enrichment forms the basis of both a mechanic’s lien and a Miller Act lien and favors compensating ‘“those whose actual expenditure of work or utilization of material has enhanced the value of the property in question.’ ” Mariana,
. A subcontractor cannot recover from a Miller Act surety for additional or increased costs caused by its own delay. Mariana,
. We endorse the Mariana court’s view that a subcontractor "must be able to demonstrate with reasonable certainty and specificity the increased costs resulting from the delay_par-ticularly ... with respect to the claim for home office overhead and general and administrative expenses." Mariana,
. The Subcontract here, as in Mariana and Otis Elevator, contemplated payment to the subcontractor for increased costs of performance caused by suspensions, delays or interruptions of the contract work for the convenience of the government. Otis Elevator,
. TMS claimed the following items as termination costs, totalling $203,430.00 after Millers paid TMS $48,150.00 for the segment of the claim attributable to "metals”: 1) “other costs," including labor, salary for supervisor, living expenses for supervisor, trailers, vans, extended insurance, and software design; 2) general project overhead figured at 21.19% of all items listed above; 3) profit of 20% on all items listed above, including general profit overhead; 4) “settlement expenses"; and 5) amounts paid to settle suppliers’ claims (collectively, "Termination Claim”).
.Paragraph 18 of the Contract fully incorporated the "clause in Section 1-8.703 of the Federal Procurement Regulations ... in effect on the day of this Contract_” The Federal Acquisition Regulations System codified at chapter one of Title 48 of the Code of Federal Regulations, however, replaced the Federal Procurement Regulations System for civilian contracts, chapters one through forty-nine of Title 41, for all contracts entered into after FAR’s April 1, 1984 effective date. 50 Fed.Reg. 26,987-02 (1985). Because of the April 5, 1984 Contract date, the Court hereinafter references 48 C.F.R. § 52.249-2 of FAR, the substantive equivalent of 41 C.F.R. § 1-8.703.
