MEMORANDUM AND ORDER
In filing the present lawsuit, Qui Tam Plaintiff Mike Stierli (“Stierli”) has attempted to invoke false claims provisions contained within both state and federal law. Stierli’s company, MDS Construction, Inc. (“MDS”), was an unsuccessful bidder for a California Department of Transportation (“CalTrans”) project, and Stierli has now sued the lowest bidder on the project in question, Shasta Services. Inc. dba Timberworks (“Timberworks”) on grounds that Timberworks’ bid was fraudulent and hence violated both the federal False Claims Act, 31 U.S.C. § 3729, et seq., and its California counterpart, California Government Code § 12650, et seq. The United States of America (“United States”) and the State of California (“State”) now move to dismiss Stierli’s Complaint on grounds that no False Claims Act violation has occurred. In addition to those motions to dismiss, both Stierli and Timberworks have also filed Cross Motions for Summary Judgment requesting that this matter be adjudicated in their respective favors. As set forth below, the Court determines that dismissal is warranted as to Stierli’s state and federal claims.
On June 18, 2002, Timberworks submitted a bid to CalTrans for construction of a truck inspection facility in Siskiyou County, California. The terms of the project proposal required bidders to either subcontract five percent of contract work to disadvantaged business entity (“DBE”) companies, or to demonstrate good faith, but unsuccessful, attempts to do so. Timberworks’ bid, which was found to be lowest, contained the requisite good faith certification indicating that no DBEs had responsed to Timberwork’s solicitation for work on the contract.
On or about June 21, 2002, two days after bids were opened, MDS submitted a bid protest letter to CalTrans claiming that Timberworks had not incorporated a bid from a certified DBE, EnTerra Remediation, Inc. (“EnTerra”). In the meantime, CalTrans proceeded to evaluate Timberwork’s good faith DBE efforts and concluded those efforts were sufficient on June 26, 2002.
After MDS submitted a second protest letter on July 13, 2002 and included a copy of EnTerra’s letter of interest, on July 25, 2002, CalTrans reiterated its previous decision that Timberwork’s efforts to obtain a qualified DBE were sufficient. On July 26, 2002 MDS appealed yet again to Cal-Trans’ Civil Rights Program, and an additional investigation ensued. CalTrans contacted EnTerra and determined that its faxed quote had been sent to Timberworks at 8:36 a.m. on June 18, 2002, just over five hours before final bid packages had to be submitted. CalTrans further spoke to involved Timberworks personnel who explained that given the distance between Timberworks’ office in Mt. Shasta, California, and CalTrans’ Sacramento headquarters, the bid package had been delivered by Federal Express to a bid courier on June 14, 2004, four days before bids were due, in order to ensure timely submission. Timberworks explained that it had not received any affirmative responses from DBEs as of June 14, 2002. Timberworks was determined by CalTrans to have been “responsive and forthright” in providing this information, and CalTrans found yet again that Timberworks had demonstrated good faith efforts towards DBE compliance despite EnTerra’s last-minute bid submission. (Decl. Of Olivia Fonseca, ¶¶ 6-7). CalTrans then approved the award of the contract in question to Tim-berworks on August 9, 2002, after it had full knowledge of Timberwork’s alleged noncompliance.
Although MDS filed a complaint with the United States Department of Transportation (“USDOT”) Federal Highway Administrative Office of Civil Rights on September 13, 2002 (given the fact that federal monies were earmarked for the project), Timberworks was not notified of the pendency of that complaint and commenced its work. (Deck of Harold J. Knight, ¶ 11). CalTrans paid each claim presented for payment, however, “fully aware of the pending federal complaint.” (Fonsceca Deck, ¶ 9). Furthermore, Cal-Trans accepted the completed project on December 31, 2003. Finally, by the time the USDOT issued its determination on April 16, 2004 that the project was not in fact eligible for federal funding because of insufficient DBE participation, all pay applications for the project had already been submitted by Timberworks. (Knight Deck, ¶ 13).
Although the USDOT ultimately concluded that the project was noncompliant, by admission from the author of its report, USDOT’s investigation “was limited to evaluating procedures used by CalTrans.” (Deck of Lance Yokota, ¶ 7). Timber-works’ own role with respect to any false claim was not investigated, and as stated above, Timberworks was not even in
The current lawsuit was filed against Timberworks on September 20, 2004. Sti-erli instituted the action as a qui tam plaintiff in order to recover, on behalf of both the State and the federal government, monies that were allegedly fraudulently obtained by Timberworks. The United States and the State of California initially declined to intervene for purposes of affirmatively protecting their interests, leaving Stierli to prosecute the matter in their stead. Now, however, through the Motions to Dismiss presently before the Court, both governmental entities now seek to dismiss Stierli’s Complaint as unwarranted.
STANDARD
Dismissal of a
qui tam
plaintiffs complaint requires a two-step analysis. The governmental real party in interest must identify both a valid government purpose in moving for dismissal and a rational relation between dismissal and accomplishment of that purpose.
U.S. ex rel. Sequoia Orange Co. v. Baird-Neece Packing Corp.,
If the government makes a showing that dismissal is warranted, the burden then switches to the
qui tam
plaintiff to demonstrate that dismissal is in fact fraudulent, arbitrary and capricious, or illegal.
Sequoia Orange,
ANALYSIS
The federal False Claims Act, 31 U.S.C. § 3729, et seq., permits a private party to bring a false claims action, on behalf of the government, in order to prevent fraud against the public treasury resulting in financial loss.
U.S. v. Neifert-White Co.,
The California False Claims Act was patterned after, and closely resembles, its federal counterpart.
Rothschild v. Tyco Int’l, Inc.,
California’s legislation also provides for a
qui tam
private right of action (Cal. Gov’t Code § 12652), and is also designed to prevent the submission of fraudulent claims for payment by the public fisc.
S. Cal. Rapid Transit Dist. v.Super. Ct.,
A
qui tam
action is initially filed under seal in order to afford the governmental entity
time to
determine whether it wishes to prosecute the action. In the present case, both the United States and the State of California elected not to intervene, therefore allowing Stierli, as the qui
tam
plaintiff, to represent their rights in prosecuting the claim against Timber-works. Even if the government elects not to intervene, however, it remains the real party in interest.
State ex rel. Bowen v. Bank of Am. Corp.,
The governmental real parties in interest retain the right to dismiss a qui tam claim for good cause, despite objection by the qui tam plaintiff, even if said parties have not previously moved to intervene. California Government Code § 12652(e)(2)(A) states:
“The state or political subdivision may seek to dismiss the action for good cause notwithstanding the objections of the qui tam plaintiff if the qui tam plaintiff has been notified by the state or political subdivision of the filing of the motion and the court has provided the qui tam plaintiff with an opportunity to oppose the motion and present evidence at a hearing.”
Similarly, the federal Act also provides that the United States may dismiss an action in its name
“notwithstanding the objections of the person initiating the action if the person has been notified by the Government of the filing of the motion and the court has provided the person with an opportunity for a hearing on the motion.”
31 U.S.C. § 3730(c)(2)(A).
Stierli claims that because the State Act’s authorization for dismissal comes within the context of a subsection applicable to instances where intervention has in fact occurred, the State lacks any standing to pursue a motion to dismiss in the absence of such intervention. It cites the
Allied Mold
case, which uncritically recites the language of the statute under circumstances where further statutory construction was not necessary since the State had intervened in the controversy there present.
Allied Mold,
Significantly, this interpretation is in accord with the constitutional mandate that the False Claims Act passes muster under a separation of powers analysis only if the government retains sufficient control over
qui tam
actions pursued in its name.
Ridenour,
Having established the initial propriety of both motions, we now turn to the merits. Both real parties in interest contend that the action has no merit inasmuch as no False Claims Act violation has occurred. As set forth above, the overall relative merits of an action may determine whether a governmental entity has good cause to request its dismissal.
Laraway,
The facts show that there had been full disclosure as to the particulars concerning Timberworks’ bid both before CalTrans awarded the project in question to Timber-works, and before any claim for payment was submitted by Timberworks. By August 9, 2002, when Timberworks formally obtained the contract, CalTrans had received three separate protest letters from Stierli, knew the circumstances of the last-minute EnTerra bid, and knew Timber-works’ justification for not including that bid in its proposal. In addition, CalTrans had otherwise investigated the sufficiency of Timberwork’s good faith DBE compliance. Not only did CalTrans award the project with full knowledge as to all those issues, it approved and paid Timberworks’ invoices even in the face of the ongoing USDOT investigation, an investigation with respect to which Timberworks had no participation and no knowledge. Timber-works had both completed the project and submitted all its payment requests by the time the USDOT issued its decision on April 16, 2004.
In
U.S. ex rel. Hopper v. Anton,
The
Allied Mold
case provides further explication in noting that there cannot be a knowing presentation of a false claim for payment where the government is fully aware of the facts surrounding the claim and approves it. The court approvingly cited the Seventh Circuit’s decision in
U.S. ex rel. Durcholz v. FKW, Inc.,
“The government’s prior knowledge of an allegedly false claim can vitiate a FCA action. If the government knows and approves of the particulars of a claim for payment before that claim is presented, the presenter cannot be said to have knowingly presented a fraudulent or false claim. In such a case, the government’s knowledge effectively negates the fraud or falsity required by the FCA.”
In the present case, because CalTrans had full knowledge of the circumstances surrounding Timberworks’ bid before any payment request was ever submitted, there was no false claim, actionable under the Act and directed to CalTrans, for which liability can attach. With respect to the United States, not only did Timber-works never submit a payment directly to the federal government (its indirect submission through CalTrans for federal funding necessarily implicates the same analysis applicable to CalTrans), but in withdrawing federal funding and never paying any monies there was not any “false or fraudulent claim paid or approved” by the federal government in any event. See, e.g., 31 U.S.C. § 3729(a)(2).
It follows that Stierli cannot make any viable claim here on behalf of the governmental entities, and that failure constitutes good cause for dismissing this action at the request of both the State of California and the United States. Other factors, however, also point towards dismissal. The State points out that the allegations of Stierli’s Complaint points towards improprieties on behalf of CalTrans, a supposed victim on behalf of which Stierli purports to be suing. The Complaint, for example, alleges at ¶ 26 that CalTrans acted in excess of its authority because if failed to comply with federal law and regulations governing DBE participation. The Complaint also, at ¶ 23, relies upon the US-DOT’S finding that CalTrans had improperly awarded the contract to Timberworks, despite the fact that the USDOT report is ultimately a review of CalTrans rather than Timberworks.
(See
Yokota- Decl., ¶ 7). ■ These allegations, involving as they do CalTrans’ own policies and procedures in awarding contracts, are not properly the subject of a claim under the Act. The
Allied Mold
court notes that “the FCA is not an appropriate vehicle for policing technical compliance with administrative regulations.”
Allied Mold,
The State further points to its legitimate interest in ensuring that the False Claims Act is not “misused by unsuccessful, disgruntled public contract bidders as a device to intimidate competitors.” (Moving Points and Authorities, 9:24-26). Otherwise, the State argues, “every award process could potentially be converted into a CFCA action with the winning bidder facing the specter of civil penalties and treble damages 1 even when the state — the real party in interest — contends no false claim was committed.” (Id. at 10:1-3). This also constitutes a valid justification for moving for dismissal in this matter.
CONCLUSION
Based on the foregoing, both the State of California and the United States have demonstrated valid justification for dismissing the present action. First and foremost, no fraudulent claim upon which liability can attach has been demonstrated. In addition, the gravamen of Stierli’s claim is not susceptible to remediation under the
IT IS SO ORDERED.
Notes
. Although no issue has been raised concerning the work done by Timberworks on the project in question, and even though CalTrans had full knowledge of the circumstances surrounding its bid before any request for payment was made, Stierli nonetheless seeks treble damages in the amount of three times the 1.107 million contract price (totaling $3,321,000) and an additional $10,000 per each of eighteen payment requests for a total claimed liability of $3,501,000 on the part of Timberworks. (See Stierli’s Memo of Points and Authorities in Support of Motion for Summary Judgment, 12:9-14).
. Because oral argument will not be of material assistance, the Court orders this matter submitted on the briefing. E.D. Cal. Local Rule 78-230(h).
