146 F.2d 379 | 5th Cir. | 1944
Smith, the appellant, rented four tractors and a bull dozer to Glassell-Taylor Co. & Robinson-Young, as Associated Contractors, who had a contract with the United States to do grading at the site of an ordnance plant to be constructed at Karnack, Texas. Maryland Casualty Company was surety on the construction bond furnished by the Contractors.
The contract was terminable at the option of Contractors upon notice to lessor, but they were required to redeliver equipment to lessor at the point from which it had been shipped, or at some other place no more distant than the point of original shipment.
In the course of time Contractors telegraphed lessor as follows: “Terminating your four 75 tractors tomorrow. Advise where to ship.” In response to the wire, lessor promptly went to Karnack to inspect his equipment and found that, in conformity with some previous and general directive, order, or regulation, Army officers in charge of construction had ordered that the equipment not be moved so long as the Contractors were using similar equipment
The theory of the defense and evidently of the lower Court seems to have been that the Contractors were prevented by the Government from redelivering the tractors, and the completion of the contract having thus been made impossible the Contractors were relieved of performance or from liability for non-performance.
We do not agree.
The expression attributed to the lower Court by stipulation of counsel that “the Government had prior to that time frozen all privately rented equipment on the job site” is neither apt nor accurate. Lessor’s equipment was not frozen by the Government but by the act of the Contractors in “freezing on to” the equipment rented from the Government at less cost, thereby making the so-called “freezing order” applicable to lessor’s tractors. The fact that the Contractors could secure tractors from the Government for less money than they were obligated to pay lessor would not relieve Contractors from their liability under their contract, nor would it immunize them from liability for their part, in bringing about the tying up of lessor’s property from May 19 to July 7. The consequences to lessor of the so-called freezing order were optional with lessees and not absolute. No immutability was attached to the freezing order unless the lessees chose to continue the use of the Government tractors. They could have released the Government’s equipment and used that which was privately owned, or they could have released the Government’s equipment as well as any privately owned equipment that they saw fit, but the optional and continued use of the equipment of the Government did not relieve them from the obligation of their contract' to lessor.
Furthermore, it is undisputed that lessees continued to use some of lessor’s equipment after it sent the telegram purporting to terminate the contract. This was not a contract in which a party could cast aside the incidents that were burdensome and hold fast to those which were advantageous. See Sec. 444, 12 Am.Jur., p. 1027. For instance, one ordinarily would not be upheld in the assertion that he had canceled his obligation to pay rent on a house if thereafter he had voluntarily continued to live in it without the lessor’s permission.
The contract with lessor required lessees to pay rent on or redeliver the tractors. They did not protect themselves by a contract which provided that they would pay rent or redeliver only in the event another of their contractees would permit them. This so-called freezing was not a web of the lessor’s weaving. Where one of two innocent persons must suffer the burden should fall upon him who had it within his power to have prevented it but failed to do so. The Contractors, and not the lessor, made the grading contract with the Government as well as the leases of its equipment, and their failure to make appropriate provisions to safeguard themselves against the unbridled discretion of the representatives of their principal contractee is in no wise attributable to lessor, and if the rental and retention of Government equipment wrought injurious consequences upon the lessees, no just or legal reason is shown as to why the consequences should be cast upon one who had no part in making such leases or in the continued use of Government equipment.
If the covenant to return the equipment is independent of the covenant
The case is remanded for further proceedings not inconsistent with the views herein expressed.
Reversed and remanded.