This mаtter comes before the Court on the defendant T.H.R. Enterprises, Inc.'s ("THR") Motion to Compel Arbitration, ECF No. 14, and accompanying motion to stay this action pending arbitration ("Motion to Stay"), ECF No. 16. Despite THR's request for a hearing on same, the Court dispenses with oral argument because the facts and legal contentions are adequately presented in the materials before the Court, and argument would not аid in the decisional process. For the reasons below, THR's Motions to Compel Arbitration and to Stay are GRANTED and this action is STAYED for a period of six months as set forth in this Order.
I. PROCEDURAL HISTORY
On December 15, 2017, Plaintiff United States of America for the use of Harbor Construction Company, Inc. ("Subcontractor" or "Harbor") filed a complaint against T.H.R. Enterprises, Inc. ("Contractor" or "THR") and Hanover Insurance Co. ("Hanover" or "Surety") (collectively, "Defendants") pursuant to the Miller Act,
II. FACTUAL BACKGROUND
At all relevant times, THR has been the prime contractor for the United States government on a construction and building repair project at Langley Air Force Base in Hampton, Virginia ("Project"). Compl. ¶ 6. At all relevant times, Hanover has been the surety under the Project contract having furnished to the United States a payment bond under such contract and pursuant to the Miller Act. Id.; see Payment Bond executed 10/24/2011,
On October 19, 2011, THR entered into a written subcontract agreement, as amended, with Plaintiff Harbor ("Subcontract") to perform certain work under the Project contract.
Harbor last performed work under the Subcontract in Seрtember 2017.
Count I of Harbor's complaint seeks action on THR's payment bond with Hanover to recover the monies owеd under the Subcontract; Count II alleges breach of contract by THR; and Count III alleges unjust enrichment by THR.
III. MOTION TO COMPEL ARBITRATION
THR asks the Court to compel arbitration pursuant to the Federal Arbitration Act,
At CONTRACTOR's sole election, any and all disputes arising in any way or related in any way or manner to this Agreement may be decided by mediation, arbitration or other alternative dispute resolution proceedings as chosen by CONTRACTOR....
The remedy shall be SUBCONTRACTOR's sole and exclusive remedy in lieu of any claim against CONTRACTOR's bonding company pursuant to the terms of any bond or any other procedure or law, regardless of the outcome of the claim. The parties further agree that all disputes under this Subcontract shall be determined and interpreted pursuant to the laws of the Commonwealth of Virginia....
Subcontract ¶ 13, Compl. at Ex. B.
To show that THR has elected arbitration under Article 13 to resоlve the contract disputes at issue here, THR submitted the following documents in support of its Motion to Compel Arbitration: (1) a copy of its letter, dated April 12, 2018, to the American Arbitration Association ("AAA") requesting initiation of arbitration with Harbor, enclosing its Arbitration Demand with respect to same, and remitting fees to the AAA in the amount of $2,500; and (2) a copy of THR's letter, also dated April 12, 2018, to Harbor's counsel furnishing copies of THR's Arbitrаtion Demand and its related correspondence with the AAA. See ECF No. 14 at Ex. 1.
A. THE FEDERAL ARBITRATION ACT
The Federal Arbitration Act ("FAA") provides:
A written provision in any ... contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction ... shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.
Whether Harbor's breach of contract claim falls within the parameters of Article 13 in the Subcontract is not at issue. Rather, Harbor argues that the ADR provision of Article 13 is invalid and unenforceable for three different reasons: (1) the provision is impermissibly vague; (2) it fails to comply with the Miller Act; and (3) it is illusory because there is no mutuality of obligation. Harbor also argues that, regardless of the provision's validity, THR has waived its right to elect arbitration at this stage. The Court shall address each argument in turn.
B. VALIDITY OF THE ADR PROVISION
1. Vagueness Claim
First, Harbor argues that the ADR provision of Article 13 is unenforceable because it is "impermissibly vague." Opp., ECF No. 19, ¶ 7. Specifically, it argues that the use of the word "may" in the provision is vague or, in the alternative, makes the entire provision permissive requiring Harbor to consent to any ADR procedures even upon THR's "election" of same.
In TM Delmarva Power, L.L.C. v. NCP of Virginia, L.L.C.,
(b) Resolution by Arbitration. If any material dispute, disagreement or controversy concerning this Agreement is not settled in accordance with the procedures set forth [in a prior section] ... then either Party may commence arbitration hereunder by delivering to the other Party a notice of arbitration.
Id. at 120,
Likewise, here, Harbor asks the Court to render the ADR provision of the Subcontract meaningless and unnecessary by interрreting it as requiring a mutual agreement to arbitrate. But such interpretation is not permissible because another reasonable interpretation can be given. TM Delmarva Power,
2. Validity under the Miller Act
Harbor next argues that Article 13 of the Subcontract is unenforceable because it "unlawfully negates Harbor's Miller Act rights against the Surety." Opp., ECF No. 19, ¶ 9. In support, it points to a provision in the Miller Act, which states:
A waiver of the right to bring a civil action on a payment bond required under this subchaрter is void unless the waiver is-(1) in writing; (2) signed by the person whose right is waived; and (3) executed after the person whose right is waived has furnished labor or material for use in the performance of the contract .
However, Harbor's reliance on the Miller Act is misplaced. THR does not argue that Harbor's Miller Act claim (Count I) is subject to the ADR provision in Article 13. Rather, THR argues that the Miller Act claim should be stayed pending arbitration of the contract dispute. That is a separate issue. See discussion infra Part IV. The arbitrability of the claim itself has not been raised. Therefore, Harbor's claim that the ADR provision is unenforceable рursuant to the Miller Act is unavailing.
3. The Unilateral Nature of the ADR Provision
Third, Harbor argues that the ADR provision in the Subcontract is unenforceable because it requires only Harbor to submit to ADR procedures and thus is an "illusory" agreement. In support, Harbor cites to a case from the District of Maryland in which the district court held that a unilateral arbitration agreement requiring only the employee, not the employer, to submit to arbitration was invalid "for want of сonsideration" because it lacked "mutuality of obligation." Raglani v. Ripken Prof'l Baseball,
Neither party has identified, nor is this Court aware, of any case in which a Virginia court has addressed the validity of unilateral arbitration agreements under Virginia law.
Virginia contract law appears to comport with the latter, broader view of mutuаlity of obligation. The Virginia Supreme Court has held that a contract can be sufficiently mutual in its obligations, and thus have adequate consideration, even if some conditions of the contract are imposed on one party and not the other. C.G. Blake Co. v. W.R. Smith & Son,
Mutuality of contract [is] sufficiently complied with when there are promises on each side that something shall be done for the benefit of the other side furnishing therefor considerations by each party, although they may relate to different terms of the contract and may be conditioned upon performance by the other party.
Id. at 971-72,
When applying this precedent to unilateral arbitration agreements, it appears that Virginia law aligns with West Virginia and North Carolina law on the issue. That is, as long as the contract as a whole is supported by adequate consideration, an arbitration provision need not impose a mutual obligation to arbitrate in order to be valid.
C. WAIVER
Finally, Harbor argues that, even if the ADR provision in Article 13 is valid, it cannot be enforced here because THR has waived its right to elect arbitration after its "voluntary and active participation in this pending Federal Court case." Opp., ECF No. 19, ¶ 10. In support, Harbor highlights the fact, that even prior to the filing of this lawsuit, THR was on notice of a dispute with Harbor when THR received several demands for payments that it refused to pay. Id. ¶ 10. Then, once the lawsuit was filed in December, 2017, THR waited until it filed its motion to dismiss/stay in February to "elect" ADR procedures under the Subcontract,
"A litigant may waive its right to invoke the Federal Arbitration Act by so substantially utilizing the litigation machinery that to subsequently permit arbitration would prejudice the party opposing the stay." Maxum Foundations, Inc. v. Salus Corp.,
Here, there was a two-month delay between the commencement of this lawsuit and THR's "election" of the ADR procedures under the Subcontract, and an additional two-month delay between THR's election and THR's filing of a demand for arbitration and the instant motion to compel arbitration. However, the Fourth Circuit has held that a four-month delay between commencement of litigation and demanding arbitration, without more, is insufficient to show waiver. Patten Grading & Paving, Inc. v. Skanska USA Bldg., Inc.,
In sum, because THR has not demonstrated a "significant resort to the machinery of litigation" or otherwise prejudiced Harbor by its delay in demanding arbitration, the circumstances constituting waiver do not exist in this case. Therefore, the Court finds that THR has not waived its right to demand arbitration pursuant to Article 13 of the Subcontraсt and the FAA. Absent other challenges to the validity of the ADR provision of the parties' Subcontract,
IV. MOTION TO STAY
In conjunction with its Motion to Compel Arbitration, THR also moves the Court to stay the entire action "pending final adjudication of the arbitration between THR and Harbor" pursuant to Section 3 of the FAA and this Court's inherent power to control its docket in favor of judicial economy and other interests.
A district court has broad discretion to stay proceedings as part of its inherent power to control its own docket. Landis v. North American,
The fact that Harbor has alleged a Miller Act claim does not tip thе balance of interests against a stay as Harbor suggests. A case from the District of Maryland, United States ex rel. MPA Construction, Inc. v. XL Specialty Insurance Company,
However, the Court also finds that the balance of interests in this case weighs in favor of a stay only if arbitration is used for dispute resolution, not as a delay tactic. For this reason, the Court hereby GRANTS THR's Motion for Stay but only STAYS this action for a period of six
V. CONCLUSION
In sum, THR's Motion to Compel Arbitration is hereby GRANTED . ECF No. 14. THR's Motion for Stay is also GRANTED insofar as the Court hereby STAYS this action for a period of SIX (6) MONTHS from the date of this Order. ECF No. 16. At the end of such period, the Court may, upon motion and upon showing of good cause, extend the stay if the parties are diligently arbitrating.
The Clerk is DIRECTED to forward a copy of this Order to all Counsel of Record.
IT IS SO ORDERED.
Notes
On that same day, THR also filed an "Alternative Answer" to Harbor's complaint as well as an "Alternative Counterclaim" pursuant to the Court's April 9, 2018 Order. ECF No. 18.
THR states that the enforceable arbitration agreement at issue in TM Delmarva Power allowed "one party to unilaterally exercise discretion to compel arbitration." ECF No. 17 at 3. However, because that agreement allowed either party to elect arbitration, it was not "unilateral" because the obligation to arbitrate upon election was imposed on both parties. TM Delmarva Power,
Virginia's strong public policy favoring arbitration lends further support to this conclusion. Mar. v. Tysinger Motor Co., No. 3:07cv508,
As the Court noted on the record at the April 9, 2018 hearing, Defendants' motion to dismiss or stay did not ask the Court to compel arbitration. See ECF No. 7. Rather, Defendants sought a stay pending arbitration that had not been initiated or compelled.
At the end of its opposition brief, Harbor also cites to Hooters of America, Inc. v. Phillips,
While Defendant Surety is not identified as a movant in the body of the motions, defense counsel signed each motion on behalf of both defendants. ECF Nos. 14 and 16. Therefore, the Surety presumably joins the pending Motion to Stay.
