ORDER
This action was instituted pursuant to the Miller Act, 40 U.S.C.A. § 270a et seq.
The facts surrounding this controversy are essentially undisputed. On October 30, 1964, the defendant, Fullerton Construction Company, and its surety, Continental Casualty Company, entered into a contract with the United States of America for the construction of a central heating and refrigeration plant at Fort Jackson, South Carolina. This contract contained a one-year guaranty provision covering materials and workmanship which began running upon the date of beneficial or final acceptance by the government, whichever came earlier
On May 23, 1966 all construction required by the government contract was substantially complete. On August 9, 1966, and September 22, 1966, the entire project, including the work performed by the plaintiff, was inspected and approved by the government. Approximately six and one-half months elapsed after the government had inspected the project. Then between April 6 and April
After a careful review of the authorities, the court has concluded that the issue must be resolved in the negative and, therefore, that the plaintiff’s action is untimely under Section 270b (b), (Note 1, supra). The applicable legal test of Section 270b(b), as recently stated by the Fourth Circuit in United States of America for Use of Noland Company v. Andrews and Parrish, et al.,
Unquestionably, the labor and material furnished by the plaintiff in April of 1967 was for the sole purpose of correcting the previously supplied defective materials and/or making repairs to such previously supplied materials or parts. It cannot be said that the materials supplied in April of 1967 by the plaintiff were materials that were called for by the terms of the original contract and not supplied until April of 1967. The factual situation here does not present a case where there has been a failure in some manner to fully complete the original contract, such as where some parts or materials called for by the contract have never been supplied. It is undisputed that all work performed and materials supplied during April of 1967 were merely for the purpose of correcting defects, or making repairs, to materials or parts already furnished, following the inspection and acceptance of the project by the government, and the fact that the one-year guaranty existed as a part of
Plaintiff cites the case of Trinity-Universal Insurance Company v. Girdner,
The commencement of an action within the one year statutory time limitation is a condition precedent to the maintenance of an action under the Miller Act. The correction of the defects and the making of the repairs by the Use plaintiff in the month of April 1967, although performed pursuant to the one-year guaranty in the prime contract (Note 2, supra,), did not serve to toll the running of the one-year statutory limitation.
Accordingly, it is concluded that plaintiff failed to timely institute suit as required by Section 270b(b) of the Miller Act (Note 1, supra), and that defendants’ motion for summary judgment in their behalf should be granted.
Let judgment be entered accordingly.
And it is so ordered.
Notes
. The Miller Act, 40 U.S.C.A. Section 270b(b) provides:
“(b) Every suit instituted under this section shall be brought in the name ■ of the United States for the use of the person suing, in the United States District Court for any district in which the contract was to be performed and executed and not elsewhere, irrespective of the amount in controversy in such suit, but no such suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied by him. * * * ”
. The guaranty provision on which plaintiff relies and as found in the prime contract between the government and Fullerton Construction Company is as follows:
“The following equipment to be furnished under this section of the specifications shall he guaranteed for a period of 1 year from the date of acceptance, either for beneficial use or final acceptance, whichever is earlier, against defective materials, design and workmanship :” (Among other equipment listed were the boilers furnished by plaintiff).
The guaranty provision further provided:
“Upon receipt of notice from the Government of failure of any part of the guaranteed equipment during the guaranty period, the affected part or parts shall be replaced promptly with new parts by and at the expense of the Contractor.”
. It is recognized that the precise issue herein involved is one of novel impression. Counsel for the parties in their able and persuasive briefs and arguments before the court have been unable to cite a case in which the effect of a contractor’s providing labor and materials for repairs and/or correcting defects pursuant to a warranty or guaranty provision of the prime contract, after the work required by the contract has been fully performed, inspected and accepted by the government, has been expressly adjudicated. Neither has the court been able to find such a case.
