83 Vt. 278 | Vt. | 1910
At tbe close of tbe evidence tbe defendant moved for a verdict on tbe grounds, (1) that tbe coal wbicb tbe evidence tends to sbow was furnished, is not “material” witbin tbe meaning of the United States statute, tbe bond, contract, or specification; and (2) that there is no competent evidence tending to sbow that any part or all of tbe coal was used for the purpose of beating any of tbe buildings named in tbe specifications attached to tbe principal contract. To tbe overruling of tbe motion defendant excepted. By agreement of counsel tbe issue was then withdrawn from tbe jury and submitted to tbe court by wbicb there was a finding of facts.
One question was, whether the coal furnished by'the use plaintiff was all used to heat the barracks and the bachelor officers’ quarters. A witness called by the plaintiff testified that it was used “to heat the buildings.” Whereupon counsel for defendant objected, stating that there seemed to be no necessity for any evidence outside of the contract and specifications. The court said the question of fact put in issue is, whether the coal in question was used for the purpose specified in the specifications, and if no question is made concerning it that will eliminate the evidence. In answer to this, counsel for defendant said: “We make no question but that the coal was used to heat the buildings covered by these specifications.” The plaintiff afterwards being allowed to put in evidence on the same question, the defendant’s counsel undertook to withdraw this concession, but made no claim that it was made improvidently, or by mistake. The record states that leave was not granted by the court to withdraw the concession, and we are controlled by the record in this respect. Later without objection that it contradicted the concession, the defendant introduced evidence tending to show that some of the coal was used in the stables. If in the circumstances the defendant was bound by the concession, the court found that all the coal was used to heat the two barracks
There can be no doubt that such admissions by attorneys, so made for that purpose, are binding upon their clients, and cn motives of policy and justice are in general conclusive. Young v. Wright, 1 Campb. 139, 141; 1 Greenl. Ev. §186; 1 Taylor Ev. §§772, 783, 820. And the party will be held to the admission, except that when it is clearly shown that the same was made improvidently, and by mistake, the court in its discretion may relieve him of the consequences of his error. 1 Greenl. Ev. §206; 1 Taylor Ev. (10th ed.) §838.
This holding results in substantiating the finding that all the coal in question was used to heat the two barracks and the bachelor officers’ quarters; which finding, taken with the further findings that at the time the coal was so used — between the 25th day of November and the last days of January following — these buildings were nearing completion, the work of plastering, putting on finish, painting, and the like, under the contract, being done thereon, and that the coal was reasonably necessary for the purpose for which it was used, fairly makes the coal “material” within the implied terms of the principal contract, which the contractor thereby obligated itself to furnish, and which was used in the prosecution of the work provided for in the contract; and consequently, under our holdings in this case when previously before us, it is within the scope of the bond. It follows that the defendant’s motion for a verdict was properly overruled.
The principal contract by its terms was to be completed on or before the first day of December, 1903. The time was extended by the government to January 1, 1904, with the consent of the defendant; and later it was further extended by the government. It is said, however, that the second extension was without notice to, or consent by, the defendant, and therefore it is not bound thereby. By express provision, the bond is security to the government for the performance of the principal contract according to the true intent and meaning thereof, as
Under tbe provisions of tbe bond it was within tbe power of tbe government, without notice to tbe surety and without its consent beyond that contained in tbe bond, to grant such extension of time for tbe performance of tbe principal contract as it saw fit; and tbe covenant for tbe protection of persons supplying labor and materials manifestly was intended to cover tbe full term allowed for such performance, whether it includes an extension of the original time specified or otherwise.
Judgment affirmed.