MEMORANDUM OPINION AND ORDER
In this qui tаm action alleging various violations of the False Claims Act, 31 U.S.C. § 3729, et seq. (the “False Claims Act” or the “Act”), defendants Riewit/AFC Enterprises, Inc., Kiewit Eastern Co. and AFC Enterprises, Inc. (collectively, “Kiewit”), move, pursuant to Federal Rules of Civil Procedure 9(b), 12(b)(1), 12(b)(6) and 56(b), 1 to dismiss the complaint (1) on the ground that Philip De- *1041 Carlo (“DeCarlo”) released Kiewit in settlement of a related civil matter; (2) for lack of subject matter jurisdiction; and (3) for failure to plead fraud or false claims with particularity. For the reasons set forth below, Kiewit’s motion is granted in part and denied in part, and the complaint is dismissed without prejudice.
BACKGROUND
On July 15,1991, DeCarlo commenced employment as Massachusetts Electric Construction Co., Inc.’s (“Mass Electric”) manager for the Hutchinson River Parkway Bridge Rehabilitation Project (thе “Project”), 2 and was stationed on the project site between July 1991 and August 1992. On or about August 11, 1992, Mass Electric terminated DeCarlo’s employment, and on April 23, 1993, DeCarlo commenced a civil suit in this Court for wrongful termination against Mass Electric, Kiewit and Harry Shaver, a Kiewit employee. See DeCarlo v. Massachusetts Electric Constr. Co., 93 Civ. 2690 (SWK) (the “Mass Electric” action). During the pen-dency of this litigation, DeCarlo wrote letters to various New York state and federal officials regarding conditions on the Project site. One such letter to the United States Department of Transportation, dated November 27, 1993, stated, in part:
I have brought legal action against both Kiewit and Mass [Electric] as per the enclosed Summons and Complaint, and as a result of my document inspection which begаn on November 4, 1993 it has become clear that many other violations of various laws have occurred, with the obvious knowledge of the on site D.O.T. personnel, as well as the Construction Manager.... These include widespread violations of the prevailing wage/Davis Bacon Law, jurisdictional irregularities, inferior and unsafe work, overpayments, continued hazardous working conditions involving asbestos and lead paint abatement, and a lack of Hazard Communications to my fellow workers.
Letter to U.S. Dep’t of Trans., dated Nov. 27, 1993, annexed to the Affidavit of Terrence Dwyer, sworn to on Sept. 11, 1995 (the “Dwyer Aff”), as Exh. “H.”
On May 19,1994, DeCarlo executed a stipulation of settlement with Kiewit in the Mass Electric action, and on June 1,1994, DeCarlo executed a general release, releasing Kiewit
from all actions, causes of action, suits, ... controversies, agreements, promises, variances, trespasses, damages, judgments, extents, executions, claims, and demands whatsoever, in law, admiralty or equity, which against the RELEASEE, the RE-LEASOR ... ever had, now have or hereafter can, shall or may, have for, upon, or by reason of any matter, cause or thing whatsoever from the beginning of the world to the day of the date of this RELEASE.
This Release embraces any and all matters which were or could have been asserted in the matter presently pending in the United States District Court, Southern District of New York, “entitled Philip DeCarlo, plaintiff v. Mass Electric Construction Co., Kiewit AFC/Enterprises, Inc., Kiewit Eastern Company and Harry L. Shaver, Defendants”, bearing Case No. 93 CIV 2690 (SWK).
Release, dated June 1, 1994, annexed to the Dwyer Aff. as Exh. “C” (emphasis in original).
Shortly thereafter, on July 28, 1994, De-Carlo filed the present complaint against Kiewit under the qui tam provisions of the False Claims Act. 3 The complaint seeks damages and civil penalties arising from alleged false claims for payments submitted by Kiewit to the New York State Department of Transportation, the Federal Highway Administration, the United States Department of Labor, the United States Department of *1042 Transportation and other federal and state agencies. Following the filing of this action under seal, the United States conducted an investigation into the allegations in the complaint in accordance with the requirements оf the False Claims Act, see 31 U.S.C. § 3730(b), but ultimately declined to intervene in the suit.
Kiewit now moves to dismiss the complaint (1) on the ground that DeCarlo released Kiewit in settlement of the Mass Electric action; (2) for lack of subject matter jurisdiction under the False Claims Act; and (3) for failure to plead fraud or false claims with particularity.
DISCUSSION
I. Standard of Law
Pursuant to Rule 56(c) of the Federal Rules of Civil Procedure, summary judgment is appropriate where “the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). The moving party must initially satisfy a burden of demonstrating the absence of a genuine issue of material fact, which can be done merely by pointing out that there is an absence of evidence in support of the nonmoving party’s ease.
Celotex Corp. v. Catrett,
The court “must resolve all ambiguities and draw all reasonable inferences in favor of the party defending against the motion.”
Eastway Constr. Corp. v. New York,
Once the nonmoving party has successfully met the burden of establishing the existence of a genuine dispute as to an issue of material fact, summary judgment must be denied unless the moving party comes forward with additional evidence sufficient to satisfy his or her ultimate burden under Rule 56.
See Celotex Corp. v. Catrett,
*1043 II. Prefiling Release of Claims
Kiewit first moves to dismiss the complaint on the ground that DeCarlo released Kiewit from all liability pursuant to the stipulation of settlement and the release in the Mass Electric action. Kiewit reasons, and DeCarlo does not contest, that the present qui tam action falls within the scope of the release, as DeCarlo discharged all claims which were or сould have been brought in the Mass Electric case. DeCarlo has reasserted in this action many of the same underlying allegations presented in the earlier case, and the Court finds the release sufficiently broad to encompass the present claims.
In response, however, DeCarlo urges the Court to adopt a rule rendering the prefiling release of a qui tam claim void as a matter of public policy where the agreement was entered into without the assent of the United States. In the alternative to finding that such a public policy exception does not exist, Kiewit asks that, in cases where a valid release is given by a relator, the Court establish a “middle ground” by barring a subsequent qui tam action in those cases in which the government ultimately declines to intervene.
A. Public Policy Exception
1. Northrop
The question whether the release of a subsequent
qui tam
action is void as a matter of public policy is one of first impression in this circuit. Recently, however, the Ninth Circuit Court of Appeals held that a
qui tam
action survives a general release for reasons of public policy.
See United States v. Northrop Corp.,
Thereafter, Northrop moved to dismiss the qui tam action, arguing that the claim was barred by the settlement of plaintiffs earlier claims. As a preliminary matter, the Ninth Circuit found the enforceability of a prefiling release entered into without the United States’ knowledge or consent to be governed first by the intent of Congress in enacting the False Claims Act. The court observed that, while the False Claims Act explicitly permits a plaintiff to settle a qui tam claim after its filing, see 31 U.S.C. § 3730(b)(1) (permitting settlement where “the court and the Attorney General give written consent to the dismissal and their reasons for consenting”); 31 U.S.C. § 3730(d)(2) (recognizing a relator’s right to “settl[e] the claim” where the United States has chosen not to intervene), the statute is silent on the issue of pre-filing qui tam settlements.
The Ninth Circuit found that Congress’s failure to explicitly address the enforceability of prefiling releases did not suggest that such releases were therefore enforceable. Northrop urged the court to observe the canon of statutory construction which holds that, where Congress has enacted a “comprehensive legislative scheme including an integrated system of procedures for enforcement” the courts must presume a remedy was deliberately omitted from a statute.
Northwest Airlines, Inc. v. Transport Workers Union of Am., AFL-CIO,
Rather, the court found that Congress’s failure to address this issue constituted a “gap” in the statutory scheme. The court rejected the application of state law, finding that such reliance would lead to inconsistency and frustrate the objectives of the False Claims Act. Accordingly, the court turned to federal common law to.examine the scope of a relator’s authority to settle a qui tam action after its filing.
Seeking a uniform federal common law rule, the Ninth Circuit applied the test articulated by the Supreme Court in
Town of Newton v. Rumery,
2. Federal Common Law
The Court finds the Ninth Circuit’s reasoning in
Northrop
persuasive. A threshold determination is whether in “filling in” the interstices left open in a federal statutory scheme the federal courts should fashion fеderal common law
5
or resort to state law. It is well-established that federal common law governs the validity of purported releases of liability in connection with federal causes of action.
Dice v. Akron, Canton & Youngstown R.R. Co.,
The principle consideration in determining whether to incorporate state law or fashion a uniform federal standard is congressional intent.
Olin Corp. v. Consolidated Aluminum Corp.,
Here, all three factors militate in favor of a consistent federal rule. With respect to uniformity, as mentioned in
Northrop,
there is a reasonable likelihood that state law would overemphasize the interest favoring final, ironclad and enforceable general releases.
United States v. Northrop Corp.,
Second, the application of state law would frustrate the purpose of the federal False Claims Act. In revising the Act in 1986, Congress expressed its concern that the “widespread fraud” directed toward the government could be successfully combatted only by “a coordinated effort of both the Government and the citizenry.” S.Rep. No. 345, 99th Cong., 2d Sess. 2-3 (1986),
reprinted in
1986 U.S.C.CA.N. 5266, 5267-68.
6
As a result, Congress sought to “inerease[] incentives, financial and otherwise, for private individuals to bring suits on behalf of the Government.”
Id.
at 23,
quoted in
1986 U.S.C.CA.N. at 5288-89. Thus, a relator who properly brings a claim will receive a percentage of the recovery even if the government chooses to intervene and conduct the action itself, 31 U.S.C. § 3730(d)(1), or pursue its claim in an administrative proceeding, 31 U.S.C. § 3730(c)(5). The extent of recovery is directly tied to the importance of the relator’s participation in the action and the relevance of the information brought forward. 31 U.S.C. § 3730(d)(1) (where the government chooses to conduct the action the relator receives “at least 15 percent but no more than 25 percent of the action or settlement of the claim, depending upon the extent to which the person substantially contributed to the prosecution of the action”). This facet
*1046
of the Act’s structure evidences a congressional intent to provide a larger incentive for relators “best able to pursue claims that the government could not, and bring forward information the government could not obtain.”
United States v. Northrop Corp.,
Third, the Court holds that the application of a uniform rule will not disrupt commercial relationships predicated on state law. Such a rule would neither run the risk of arbitrary application nor would it “undercut the reliability of [a] systеm which plays a crucial role in commercial dealings.”
See United States v. Kimbell Foods,
3. Public Interest
Applying federal common law, the Court agrees with the Ninth Circuit that the
Rum-ery
test must be employed. In
Rumery,
the Supreme Court held that “a promise is unenforceable if the interest in its enforcement is outweighed in the circumstances by a public policy harmed by enforcement of the agreement.”
Town of Newton v. Rumery,
In the present case, in contrast, serious public interests are at stake, to wit, the interest of the taxpayers and the government in recouping lost proceeds, and the public interest in the disclosure of fraudulent activity.
See Stamford Bd. of Educ. v. Stamford Educ. Ass’n,
Kiewit relies on
Coleson v. Inspector Gen. of the Dep’t of Defense,
*1047
In addition, any generalized interest in settlement is heavily outweighed by the costs of “eviscerating the incentives created by the [False Claims Act].”
United States v. Northrop Corp.,
Presumаbly, the defendants who will be deterred most from settling non-[False Claims Act] claims because of the possibility of a qui tam suit are those who face the greatest exposure under the Act. These defendants, of course, are the very defendants who are most likely to have committed fraud in the first place, and a central objective of the qui tam provisions is precisely to augment the incentives for employees of such entities to come forward. Therefore, if refusal to enforce the Release in this case increases defendants’ costs, this actually might have the salutary effect of further deterring defendants from engaging in fraud, which, in the long-run, might render the costs [defendants] foresee insubstantial.
United States v. Northrop Corp.,
B. Subsequent Government Intervention
Kiewit argues, in the alternative, that public policy interests should not render void the prefiling settlement of qui tam actions at least where, as here, the government declines to intervene in the litigation. Kiewit theorizes that “where a valid and sufficient release is given by a qui tam plaintiff, the relator [should] be barred thereby from maintaining a subsequent qui tam action in which the government has declined to intervene.” Such a policy would, for the settling relator, leave the question of whether a release is ultimately enforceable in the hands of the government.
This reasoning is flawed in several respects. First, the government’s decision not to participate in the qui tam action is not equivalent to a consent to voluntarily dismiss a claim against a defendant with prejudice. Non-intervention does not necessarily signal governmental disinterest in an action, as it is entitled to most of the proceeds even if it opts not to intervene.
Second, a relator would be less likely to bring suit after a release if the action could be subsequently invalidated by the government’s decision not to intervene. Although it ultimately declined to intervene in the present case, the government only learned of the present allegations of fraud as a result of the filing of the
qui tam
complаint. If the prevailing rule were that prefiling releases entered into without the government’s knowledge or consent were enforceable, DeCarlo likely would not have filed his
qui tam
complaint, the government would not have had the opportunity to decline, and Congress’s intention to deter fraudulent activity would have been effectively diluted.
See United States v. Northrop Corp.,
III. Subject Matter Jurisdiction
Kiewit next argues that the Court lacks subject matter jurisdiction on the ground that DeCarlo was not an “original source” of the information within the meaning of sections 3730(e)(4)(A) and (B) of the False Claims Act.
See United States ex rel. Kreindler & Kreindler v. United Technologies Corp.,
(A) No court shall have jurisdiction over an action under this section based upon the public disclosure of allegations or transactions in a criminal, civil, or administrative hearing, ... unless ... the рerson bringing the action is an original source of the information.
(B) For purposes of this paragraph, “original source” means an individual who has direct and independent knowledge of the information on which the allegations are based and has voluntarily provided the information to the Government before filing an action under this section which is based on the information.
*1048
31 U.S.C. § 3730(e)(4). This provision is designed to bar “parasitic lawsuits” based upon publicly disclosed information in which would-be relators “seek remuneration although they contributed nothing to the exposure of the fraud.”
United States ex rel. Kreindler & Kreindler v. United Technologies Corp.,
Kiewit argues that the information forming the basis of this action was publicly disclosed (1) through its own submission of reports to government officials; and (2) as a result of the filing of the related Mass Electric action. Kiewit also argues that since DeCarlo was not an “original source” of the information upon which his false claim allegations are based within the meaning of section 3730(e)(4), the Court lacks subject matter jurisdiction over the present action.
Kiewit relies primarily upon Kreindler for the proposition that information gleaned during the course of litigation or in discovery is “publicly disclosed” within the meaning of section 3730(e)(4). In that case, the qui tam relator was an attorney whose knowledge of the fraud (the allegation and its proof) originated from his exposure to discovery responses submitted while representing a client in an earlier unrelated action against the qui tam defendant. The Court held that discovery materials filed with the Court constituted a public disclosure of the information. Kreindler argued that because it obtained some of the information through independent investigation, and thus did not rely “solely” on the material disclosed through the prior litigation, it should not be barred from bringing suit. The Second Circuit summarily dismissed this argument:
The phrase “solely,” however, is not included in § 3730(e)(4)(A), which addresses actions “based upon” public disclosure of the underlying allegations or transactions. Further, United States ex rel. Precision Co. v. Koch Indus., Inc., 971 F.2d [548, 552-53 (10th Cir.1992) ], explicitly repudiates the notion that § 3730(e)(4)(A) bars only actions based “solely” upon publicly disclosed information, concluding that the statute applies to a “qui tam action ... based in any part upon publicly disclosed allegations or transactions.”
United States ex rel. Kreindler & Kreindler v. United Technologies Corp.,
An exception to the public disclosure bar exists, however, where the relator is the “original source” of the information. 31 U.S.C. § 3730(e)(4)(B);
see also United States ex rel. Kreindler & Kreindler v. United Technologies Corp.,
The direct knowledge requirement was intended to avoid parasitic lawsuits by “disinterested outsider[s]” who “simply stumble across an interesting court file.”
United States ex rel. Stinson, Lyons, Gerlin & Bustamante v. Provident Life & Accident Ins. Co.,
Kiewit argues that since the complaint was filed upon information and belief, DeCarlo tacitly admits that he is not the original source, lacking the requisite “direct and independent” knowledge. Kiewit contends that DeCarlo was not an original source of the information as he neither worked for Kiewit nor had any involvement in, or personal knowledge of, Kiewit’s submission of documents to the government other than that gained through the
Mass Electric
action. The Court disagrees. DeCarlo had independent knowledge of Kiewit’s allegedly fraudulent conduct, obtaining information and making first-hand observations during the course of his employment on the Project.
See Wang v. FMC Corp.,
IV. Failure to Plead with Particularity
Finally, Kiewit moves to dismiss the complaint on the ground that it does not comply with Federal Rule оf Civil Procedure 9(b)’s requirement that fraud claims be pled with particularity. Specifically, Kiewit argues that because DeCarlo’s claims are made “upon information and belief’ and lack the specificity required under Rule 9(b), the complaint should be dismissed.
Federal Rule of Civil Procedure 9(b) provides, in relevant part: “In all aver-ments of fraud or mistake, the circumstances constituting fraud or mistake shall be stated with particularity.” Fed.R.Civ.P. 9(b). Rule 9(b) applies to all allegations of fraud, including actions brought pursuant to the False Claims Act.
Gold v. Morrison-Knudsen Co.,
In general, Rule 9(b) pleadings cannot be based upon information and belief.
Segal v. Gordon,
Here, DeCarlo has conducted extensive and wide-ranging discovery in the related Mass Electric case. Both actions arose out of alleged events that transpired during the performance of Kiewit’s contract with the New York State Department of Transportation to act as general contractor on the Project. Principals of Kiewit and Mass Electric and New York State Department of Transportation offiсials were deposed, and DeCarlo reviewed thousands of Kiewit and Mass Electric Project documents.
The complaint’s allegations of fraud in light of the prior discovery compels the Court to conclude that the fraud allegations are deficient under Rule 9(b) in several respects. First, the complaint contains twenty-five fraud-based allegations made on information and belief, 7 pertaining to all of the categories of false claims alleged to have been made by Kiewit. 8 Yet, despite a substantial period of discovery, none of DeCar-lo’s operative False Claims Act averments are made on direct knowledge.
Second, the complaint fails to refer to specific employees who may have been involved in submitting false claims. In
United States ex rel. Robinson v. Northrop,
CONCLUSION
For the reasons outlined above, Kiewit’s motion to dismiss the complaint based on (1) the parties’ prior settlement; and (2) lack of subject matter jurisdiction under 31 U.S.C. § 3730(e)(4), is denied. Kiewit’s motion, pursuant to Federal Rule of Civil Procedure 9(b), to dismiss the complaint for failure to plead fraud with particularity is granted and the complaint is dismissed without prejudice. An amended complaint may be submitted within thirty days from the date of this Memorandum Opinion and Order.
SO ORDERED.
Notes
. Although Kiewit’s notice of motion states that it also seeks dismissal under Rule 12(b)(6), both sides have filed supporting affidavits. Accordingly, the Court shall treat the motion as one for summary judgment.
See Grand Union Co. v. Cord Meyer Dev. Corp.,
. Kiewit was awarded a contract by the New York State Department of Transportation to act as general contractor on this federally funded project. Mass Electric was the electrical subcontractor of the Project. The Project is being carried out pursuant to Federal Aid Constructiоn Contract F.A. Project IT-213(102).
. The phrase "qui tam” is shorthand for “qui tam pro domino rege quam pro se imposo sequi-tur,” interpreted as "who sues on behalf of the King as well as for himself." Black’s Law Dictionary 1251 (6th ed. 1990). Qui tam plaintiffs are frequently referred to as "relators."
. In addition, one other court has explicitly adopted Northrop's reasoning. In
United States ex rel. Pogue v. American Healthcorp, Inc.,
No. 3-94-0515,
. The lack of analytical precision in the term "federal common law” confronted by the Ninth Circuit in Northrop has been frequently noted by commentators and judges alike:
The demarcation between “statutory interpretation” or “constitutional interpretation,” on the one hand, and judge-made law on the other, is not a sharp line.... |T|he term, federal common law, [is used] to refer generally to federal rules of decision whose content cannot be traced by traditional methods of interpretation to federаl statutory or constitutional command.
Bator, Mishkin, Meltzer & Shapiro,
Hart and Wechsler’s The Federal Courts and the Federal System
863 (1988);
see also Olin Corp. v. Consolidated Aluminum Corp.,
. Estimates suggest that the United States Treasury loses somewhere between $25 and $70 billion a year as a result of fraud by its contractors. See Erwin Chemerinsky, Controlling Fraud Against the Government: The Need for Decentralized Enforcement, 58 Notre Dame L.Rev. 995, 995 n. 1 (1983).
. See Complaint at ¶¶ 18, 20, 21, 23, 25, 26, 28, 29, 31, 32, 34, 35, 38, 40, 41, 43, 46, 49, 50, 52, 55, 58, 60, 62 and 64.
. See Complaint at ¶¶ 49, 50, 52, 55, 58, 60, 62 and 64.
. For example, paragraph 50 states: "Upon information and belief, each and every weekly payroll report was false for at least one of the following reasons.” Complaint at ¶ 50. The complaint then lists three categorical areas which purportedly apply to each and every of the 180 weekly payroll reports, including: (1) the reports did not contain thе names and wages paid to Kiewit’s administrative personnel who were openly performing undescribed direct labor on the Project; (2) the reports certified that the workers listed were paid by Kiewit, when in fact they were paid by "other undocumented employers and disallowed second tier subcontractors"; (3) the reports certified that unidentified workers were paid prevailing wages, when the workers in fact had performed work in other classifications requiring a higher wage rate. Id. Such generalizations could not possibly apprise Kiewit of which Kiewit employees were allegedly performing what direct labor, which workers were being *1051 paid by which undocumented subcontractors, or which workers were performing work in classifications that required a higher wage rate.