The United States of America, for the use of E. L. Bailey,
It is uncontested that plaintiff, Bailey, supplied all the labor and materials called for by his subcontract with the prime contractor and that the terms of said subcontract were fully and conscientiously met; and, that Bailey is in no way responsible for the fact that complete final payment under the terms of the prime contract has not yet been made by the Government.
The single issue before the Court is whether the action in question is premature for the reason that the Government has not yet made a complete “final payment” under the prime contract.
Under the express terms of the subcontract between the principal contractor and Bailey, Bailey was not to receive payment until the principal contractor received “final payment” from the Government.
In the instant case the plaintiff is in the position of having filed this suit within this one year statutory limitation. However, if this action is held premature, that is, that complete payment to the principal contractor by the Government is a condition precedent to plaintiff’s right to maintain this suit, then plaintiff Bailey will lose his right to sue on the bond for the reason that one year since “final settlement” has now elapsed and suit could not be refiled at a later date.
The Court has concluded that the instant suit is not premature for two reasons:
First, although the subcontract provided that the principal contractor did not become liable to Bailey until “final payment” was made by the Government to the principal contractor this term must not be interpreted to mean complete final payment. Such a construction would amount to a forced forfeiture of rights given a subcontractor under the required
In addition, even if “final payment” were construed to mean complete payment to the principal contractor, under the facts in this case the plaintiff still would have the legal right to now assert his claim. Where a “condition precedent” is placed in a contract, it is elementary that the one party to whose benefit such condition inures and who has the right to demand that the condition precedent be met, cannot assert a failure of the condition in defense where said party defendant by his or its own conduct has prevented the happening of said condition precedent.
The plaintiff is entitled to judgment in the amount of $1,375.83, plus interest and costs.
Counsel should submit journal entry to conform with this opinion within fifteen days.
. D/B/A City Electric Company.
. 40 U.S.C.A. § 270a et seq.
. The subcontract provided in part: “No payment is due hereunder, whether a progress payment or final payment, until such progress payment or final payment has been made by the Government to The Holloway Company.” In addition, the individual purchase orders, which became a part of the subcontract, each provided, “ * * * Final payment to be made upon receipt of final payment from U. S. Government by prime contractor.”
. 40 U.S.C.A. § 270b (b).
. Whether there has been a “final settlement” is an administrative determination. See R. P. Farnsworth & Co. v. Electrical Supply Co., 5 Cir., 1940, 112 F.2d 150, 130 A.L.R. 192, certiorari denied 311 U.S. 700, 61 S.Ct. 139, 85 L.Ed. 454; Illinois Surety Co. v. U. S., 1916, 240 U.S. 214, 36 S.Ct. 321, 60 L.Ed. 609; U. S. for Use and Benefit of F. B. Spear & Sons v. Arthur Storm Co., 6 Cir., 1939, 101 F.2d 524, certiorari denied 307 U.S. 630, 59 S.Ct. 833, 83 L.Ed. 1513. In the instant case such “final settlement” was made over one year ago, but not one year prior to July 14, 1953, the date this case was filed.
. Cf. Robinson v. United .States, 2 Cir., 1918, 251 F. 461, 466, 467, involving a prior act which contained similar language, where the Court in ruling that the action by the subcontractor was not premature, even though certain final payment amounts were being contested in the Court of Claims by the prime contractor, said: “So to hold is not to rewrite the contracts as between Robinson and the subcontractors, as counsel earnestly contend, but is merely to give the languáge of the parties the meaning which they intended it should have, for they were referring directly to the contract with the United States, with its necessary security, and it is clear that the language thus used in the subcontracts could never have been intended, in effect, to require the subcontractors to waive their rights upon the bond, or to be postponed indefinitely after the United States had so acted as to discharge all liability on the bond against it, and after the necessary six months had elapsed. * * * !>
. This general principle is recognized in 12 Am.Jur. (Contracts) § 329 wherein it is said: “One who prevents or makes impossible the performance or happening of a condition precedent upon which his liability by the terms of a contract is made to depend cannot avail himself of its nonperformance. In other words, he who prevents a thing from being done shall never be permitted to avail himself of the nonperformance which he himself has occasioned.”