THE UNITED ILLUMINATING COMPANY v. PUBLIC UTILITIES REGULATORY AUTHORITY
(SC 20795)
Supreme Court of Connecticut
Argued December 11, 2023-officially released October 29, 2024
McDonald, D‘Auria, Mullins, Ecker, Alexander, Dannehy and Alvord, Js.
*
The “officially released” date that appears near the beginning of an opinion is the date the opinion will be published in the Connecticut Law Journal or the date it is released as a slip opinion. The operative date for the beginning of all time periods for the filing of postopinion motions and petitions for certification is the “officially released” date appearing in the opinion.
All opinions are subject to modification and technical correction prior to official publication in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.
The syllabus and procedural history accompanying an opinion that appear in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced or distributed without the express written permission of the Commission on Official Legal Publications, Judicial Branch, State of Connecticut.
**
Syllabus
The plaintiff, U Co., an electric distribution company, appealed from the judgments of the trial court, which had dismissed its consolidated administrative appeals from two final decisions of the defendant, the Public Utilities Regulatory Authority (PURA). In one of its decisions, PURA found that U Co. had violated its statutory obligations in connection with its emergency planning, storm recovery performance, and other actions taken in response to an August, 2020 tropical storm, and announced its intention to impose a fifteen basis point reduction of U Co.‘s authorized return on equity (ROE). In its other decision, PURA imposed more than $1.2 million in fines on U Co. pursuant to statute (
PURA‘s subsequent decision, made during the pendency of this appeal, not to implement the fifteen basis point ROE reduction rendered moot the issue of whether PURA lacked statutory authority to implement that ROE reduction, and neither the voluntary cessation nor the collateral consequences exception to the mootness doctrine applied.
The application of the equitable remedy of vacatur to the portion of PURA‘s order authorizing the ROE reduction and to that portion of the trial court‘s judgment upholding that order was appropriate.
The failure to report a minor accident, as contemplated by
* The listing of justices reflects their seniority status on this court as of the date of oral argument.
Because PURA improperly treated U Co.‘s delay in reporting the two minor accidents as a continued violation and imposed a $500 daily penalty for each unreported accident rather than a $500 penalty for each month in which U Co. failed to report each minor accident, the case was remanded to the trial court with direction to order PURA to recalculate those penalties.
There was sufficient evidence to support PURA‘s finding, in connection with its imposition of $1.2 million in fines, that U Co. had violated
Argued December 11, 2023-officially released October 29, 2024**
Procedural History
Appeal from, inter alia, the finding of the defendant that the plaintiff had failed to fully comply with previously established standards of acceptable performance of an electric distribution company after an emergency and a reduction of the plaintiff‘s authorized return on equity, and appeal from the defendant‘s imposition of civil penalties on the plaintiff, brought to the Superior Court in the judicial district of New Britain, where the court, Klau, J., granted the motion to intervene filed by the Office of Consumer Counsel in each appeal; thereafter, the appeals were consolidated and tried to the court, Cordani, J., which rendered judgments dismissing the appeals, from which the plaintiff appealed. Appeal dismissed in part; vacated in part; reversed in part.
Seth A. Hollander, assistant attorney general, with whom were Scott Muska, general counsel, and, on the brief, William Tong, attorney general, for the appellee (defendant).
** October 29, 2024, the date that this decision was released as a slip opinion, is the operative date for all substantive and procedural purposes.
William E. Dornbos, legal director, with whom, on the brief, were Claire E. Coleman, consumer counsel, and Andrew W. Minikowski, for the appellee (intervenor Office of Consumer Counsel).
Opinion
MULLINS, J. In this appeal, the plaintiff, The United Illuminating Company, appeals from the judgments of the Superior Court dismissing its consolidated administrative appeals from two final decisions of the defendant, the Public Utilities Regulatory Authority (PURA). The plaintiff challenges PURA‘s determination that the plaintiff had violated its statutory obligations with respect to its emergency planning, storm recovery performance, and other actions taken in August, 2020, in connection with Tropical Storm Isaias and its aftermath. The plaintiff further contends that PURA improperly reduced the plaintiff‘s authorized return on equity (ROE) and imposed various civil penalties, including more than $1.2 million in fines. We conclude that the plaintiff‘s challenge to the ROE reduction is moot, insofar as the reduction was never implemented. We also conclude that PURA miscalculated the fines it imposed for the plaintiff‘s delayed reporting of two minor accidents. Otherwise, we find no error and thus affirm the trial court‘s judgments in all other respects.
I
We begin with the relevant facts and procedural history, as set forth in the administrative record. In 2012, in the aftermath of Tropical Storm Irene and an
gencies and empowered PURA to impose civil penalties for noncompliance with performance standards. See
On August 4, 2020, Tropical Storm Isaias produced damage throughout nearly all of the plaintiff‘s service territory in southern Connecticut. Early in the storm recovery process, on August 6, 2020, the city of Bridgeport filed a motion with PURA to compel the plaintiff to undertake additional restoration action. Bridgeport requested that PURA take immediate action to force the plaintiff “to live up to its obligations as a ‘public service company‘” because, in its view, the plaintiff had “done little, if anything, to serve the public of Connecticut‘s largest city [during restoration of service in the aftermath of Tropical Storm Isaias].”
In the days following the storm, PURA initiated two proceedings addressing the plaintiff‘s storm preparation and response performance. The first proceeding (investigation proceeding) was a broadly scoped investigation concerning the plaintiff‘s actions before, during, and after the storm. In 2021, after a series of hearings, PURA issued a final decision in the investigation proceeding, finding that the plaintiff‘s response times for service restoration generally satisfied the performance standards that the plaintiff had adopted as part of its approved emergency response plan. PURA faulted the plaintiff, however, for deficiencies with respect to its make safe crews,1 its responses to life-threatening situations and related emergencies, its duty
to timely report minor accidents, and its communication and coordination with municipalities. As a result, PURA ordered numerous modifications to the plaintiff‘s storm response protocols. PURA also announced its intention to impose a fifteen basis point reduction of the plaintiff‘s authorized ROE at the plaintiff‘s next regular rate case. According to PURA, this reduction was not a penalty but, rather, was meant as an incentive to “encourage [the plaintiff] to cure” management and operational deficiencies.
The second proceeding (penalty proceeding) was initiated so that PURA could consider appropriate civil penalties for the deficiencies identified in the investigation proceeding. Following a hearing, PURA issued a final decision in the penalty proceeding, imposing approximately $1.2 million in civil penalties for the plaintiff‘s noncompliance with certain identified performance standards. One half of that penalty-$593,823-was for the plaintiff‘s noncompliance with its obligations with respect to make safe crews, and one half was for failure to adequately communicate with Bridgeport officials and to prioritize restoring power to critical sites, such as senior living homes, in that city.
PURA also imposed civil penalties for the plaintiff‘s failure to timely report two
of a $500 penalty for each day that each report was late, for a total of $61,000 in additional civil penalties.
The plaintiff appealed PURA‘s decisions in the investigation and penalty proceedings to the Superior Court, pursuant to the Uniform Administrative Procedure Act (UAPA). See
The Office of Consumer Counsel (OCC) intervened as a defendant in both appeals,4 which the trial court thereafter consolidated. Following a hearing, the court issued a memorandum of decision, upholding PURA‘s determinations and dismissing the plaintiff‘s appeals. The plaintiff appealed from the trial court‘s judgments to the Appellate Court, again raising each of the three previously mentioned challenges, and we transferred the appeal to this court pursuant to Practice Book § 65-1.
During the pendency of the appeal, in late 2022 and early 2023, PURA conducted hearings in the plaintiff‘s next regular rate case (2022 rate case). After the present
appeal was fully briefed, PURA issued a decision in the 2022 rate case, wherein it declined to implement the previously ordered reduction to the authorized ROE. We then ordered the parties to file supplemental briefs addressing the question of whether PURA‘s failure to implement the ROE reduction rendered that portion of the plaintiff‘s appeal moot or unripe. Additional facts will be set forth as necessary.
II
We first address PURA‘s argument that its decision in the 2022 rate case not to implement the fifteen basis point ROE reduction rendered moot-or unripe-the plaintiff‘s first set of claims, which contend that PURA lacked the statutory authority to implement that penalty in the investigation proceeding. See footnote 7 of this opinion. The plaintiff contends that the issue is not moot and remains ripe for adjudication. In the alternative, the plaintiff
A
The following additional procedural history is relevant to this issue. The investigation proceeding addressed the performance of Connecticut‘s two EDCs, the plaintiff and The Connecticut Light and Power Company, doing business as Eversource Energy (Eversource), both of which were found to have performed deficiently
with respect to Tropical Storm Isaias. In its final decision, PURA stated that it “will order a reduction in each company‘s ROE in order to incentivize the EDCs to improve their management of future storm responses. The ROE approved for the EDCs in the next applicable ratemaking proceeding in which a final decision is issued . . . will accordingly be reduced. For [the plaintiff, PURA] will impose a fifteen basis point ROE reduction.” (Footnote omitted.) PURA indicated that Eversource would be subject to a larger, ninety basis point reduction because a fifteen basis point reduction imposed on Eversource in 2014 had failed to incentivize that company to improve its storm preparedness and response. PURA characterized these reductions as “indefinite . . . .”
After briefing had been completed but before argument in the present appeal, PURA submitted a letter stating that PURA had issued a final decision in the plaintiff‘s 2022 rate case. PURA concluded that it was not necessary to impose the fifteen basis point ROE reduction on the plaintiff that PURA had authorized in the investigation proceeding. PURA explained this countermand by noting that the purpose of the reduction had been to incentivize the plaintiff to remedy the deficiencies noted during that proceeding. By 2022, as further explained by PURA, the plaintiff had provided evidence establishing that it had taken PURA‘s feedback seriously and, in most instances, had either remedied the deficiencies or effected operational changes calculated to remedy them. PURA concluded: “[PURA] finds that the fifteen . . . basis point reduction . . . appears to have achieved the . . . objective of incentivizing [the plaintiff] to implement improved storm response systems overall. With this objective met, [PURA] determines that the ROE reduction is not necessary to implement in this proceeding. However, [PURA]
will continue to closely monitor and review [the plaintiff‘s] storm preparation and response performance.”
In the ensuing supplemental briefing ordered by this court, PURA argued that its decision not to implement the ROE reduction rendered moot the plaintiff‘s appellate challenges to that penalty. It argued that, because it had never actually reduced the plaintiff‘s ROE as a result of the investigation proceeding, and has no pending plans to do so, resolution of the appeal can afford the plaintiff no practical relief. The plaintiff responds that the appeal is not moot because both the voluntary cessation and collateral consequences exceptions to the mootness doctrine apply.
B
The principles and rules that govern the mootness doctrine are well established.
Our focus here is on the two exceptions to the mootness doctrine invoked by the plaintiff, voluntary cessation and collateral consequences. We conclude that
neither exception applies and, therefore, that this portion of the appeal is moot.
1
The voluntary cessation doctrine is predicated on the principle “that a party should not be able to evade judicial review, or to defeat a judgment, by temporarily altering questionable behavior. . . . This exception applies especially to parties who cease the challenged behavior for the purpose of avoiding litigation. . . . [W]hen considering whether to apply the voluntary cessation exception in a particular case, the court must consider when and why a party ceased the challenged action.” (Citations omitted; internal quotation marks omitted.) CT Freedom Alliance, LLC v. Dept. of Education, 346 Conn. 1, 23, 287 A.3d 557 (2023).
In addition, “[a]s between private parties . . . we have stated that a defendant‘s voluntary cessation of a challenged practice does not deprive a . . . court of its power to determine the legality of the practice . . . because, [i]f it did, the courts would be compelled to leave [t]he defendant . . . free to return to [its] old ways.” (Internal quotation marks omitted.) Id., 20. “When governmental actors have voluntarily ceased the conduct alleged to have been unlawful, however, we have determined that some deference is appropriate. . . . [This deference] to governmental actions is consistent with that given in numerous federal court decisions.”6 (Citations omitted.) Id., 21-22.
These considerations counsel against applying the voluntary cessation exception in the present case. PURA represents that its decision not to apply the ROE reduction was not made in response to the present litigation or for other strategic reasons. Rather, the decision was made in due course, at the plaintiff‘s next scheduled rate case, because the threatened reduction had served its purpose of incentivizing the plaintiff to substantially remedy the storm preparedness and response issues that PURA had identified. PURA further represents that it opted not to implement the reduction, that the reduction does not remain pending, and that the issue will arise again only if a
As a matter of Connecticut law, however, we have not been asked to revisit this aspect of CT Freedom Alliance, LLC, at this time, and we see no reason to do so. That decision permits us to assume the good faith of a coequal branch of government, without requiring that we approve of patently strategic behavior, accept uncritically what appear to be flimsy or self-serving representations, or otherwise pay greater solicitude to government actors than is warranted under the circumstances of a particular dispute. See CT Freedom Alliance, LLC v. Dept. of Education, supra, 346 Conn. 22 (“[this deference] does not constitute a guarantee of unquestioned acceptance of governmental representations” (internal quotation marks omitted)).
We are not persuaded by the plaintiff‘s argument that PURA‘s vague warning that it “will continue to closely monitor and review [the plaintiff‘s] storm preparation and response performance” is tantamount to “reserving to itself the unreviewed power to reimpose the same ROE penalties in the future.” When PURA intends to threaten the imposition of a specific penalty, it does so expressly, as it did in the 2014 Eversource rate case. See Public Utilities Regulatory Authority, Decision on the Application of The Connecticut Light and Power Company To Amend Rate Schedules, Docket No. 14-05-06 (December 17, 2014) p. 152 (“[i]f [Eversource] fails to improve [with respect to] major storm preparedness and response and is found not to be in compliance with the outage restoration standards established by [PURA‘s] November 1, 2014 [d]ecision . . . [PURA] may impose penalties as defined in that [d]ecision and reduce [Eversource‘s] going forward ROE to create an incentive for [Eversource] to improve its performance“). We understand the cited language in the present case, by contrast, to be nothing more than a benign statement of the fact that, notwithstanding PURA‘s decision not to implement the penalty for the plaintiff‘s response to Tropical Storm Isaias, PURA will continue to carry out its mission of ensuring that EDCs, such as the plaintiff, provide the public with safe, clean, reliable, and affordable utility service and infrastructure.
2
Turning to the collateral consequences exception, we note that “[t]his court has recognized . . . that a case does not necessarily become moot by virtue of the fact that . . . due to a change in circumstances, relief from the actual injury is unavailable. We have determined that a controversy continues to exist, affording the court jurisdiction, if the actual injury suffered by the litigant potentially gives
to invoke successfully the collateral consequences doctrine, the litigant must show that there is a reasonable possibility that prejudicial collateral consequences will occur. . . . The reviewing court therefore determines, based [on] the particular situation, whether . . . the prejudicial collateral consequences are reasonably possible.” (Citation omitted; internal quotation marks omitted.) State v. Gomes, supra, 337 Conn. 839-40.
The plaintiff offers two theories as to why the collateral consequences exception applies, neither of which we find persuasive. First, the plaintiff lists various legal errors that PURA allegedly committed-the same errors that are the basis for the plaintiff‘s appeal of the ROE order7-and contends that allowing those errors to go uncorrected would harm it in ways unspecified. But an opinion resolving those issues would be purely advisory; it could afford the plaintiff no present relief. That sort of purely academic dispute does not give rise to a live controversy between the parties or allow for effective relief so as to qualify as a collateral consequence. See, e.g., Waterbury Hospital v. Connecticut Health Care Associates, 186 Conn. 247, 250, 440 A.2d 310 (1982) (“[when] the question presented is purely academic, we must refuse to entertain the appeal” (internal quotation marks omitted)). If it did, the exception would swallow the rule, and few if any appeals would be moot.
Second, and more plausibly, the plaintiff contends that there is a reasonable possibility that, in some future proceeding, PURA will treat the never imposed fifteen basis point ROE reduction as precedential and use it to justify the imposition of a more serious penalty. The plaintiff points out that PURA followed precisely that approach in the proceedings that gave rise to this litigation, imposing a ninety basis point ROE reduction on Eversource because a prior fifteen basis point reduction issued in response to that company‘s 2011 storm performance had not sufficiently incentivized Eversource to make the necessary improvements. In other words, the plaintiff posits, if we decline to resolve its challenges to PURA‘s decision, then, in the future, there is a reasonable possibility that the plaintiff will be treated more harshly as a recidivist.
We agree that the plaintiff has identified a cognizable collateral consequence to PURA‘s decision. The concern is that, in future proceedings, PURA would treat the plaintiff as it did Eversource and impose a higher ROE reduction next time on the basis of already having determined that the plaintiff should receive a fifteen basis point reduction. That action would undoubtedly qualify as a collateral consequence. The question is whether, “based [on] the particular situation . . . the prejudicial collateral [consequence is] reasonably possible” to occur. (Internal quotation marks omitted.) State v. Gomes, supra, 337 Conn. 840.
We think that
Moreover, at oral argument before this court, the OCC‘s attorney took the position that the fifteen point
ROE reduction, although styled as “indefinite,” is now a dead letter. The OCC‘s attorney further contended that PURA would not afford any precedential value to a reduction that was never applied. PURA‘s counsel also represented that the agency has no intention of relying on the Tropical Storm Isaias proceedings in future storm investigations (although it reserved the right to do so).
On the basis of the foregoing, considering together the low likelihood that the plaintiff would reoffend and the extremely low likelihood that PURA would opt to rely on the Tropical Storm Isaias proceedings, we conclude that there is not a reasonable possibility that the plaintiff will suffer a collateral consequence as a result of the challenged order. See, e.g., Rek v. Pettit, 222 Conn. App. 132, 140, 303 A.3d 926 (2023) (concluding that prospect of further litigation between parties regarding child visitation was mere conjecture), cert. denied, 348 Conn. 948, 308 A.3d 36 (2024).8 In any event, if PURA were to impose, or reimpose, such penalties in a future action, the plaintiff would have the opportunity to challenge the legality of such action and PURA‘s interpretation of its legal authority at that time. The plaintiff‘s appeal of the ROE reduction is moot.
C
Having determined that the ROE reduction issue is moot, we next consider whether the portion of PURA‘s order authorizing that penalty, and that portion of the trial court‘s judgment upholding the order, should be vacated. The following principles govern our analysis.
“[W]hen an appeal is dismissed as moot, the party who is unable to obtain judicial review should not be
barred from relitigating the factual and legal issues decided in rendering that judgment.” (Internal quotation marks omitted.) Thornton v. Jacobs, 339 Conn. 495, 501, 261 A.3d 738 (2021). “Vacatur is commonly utilized . . . to prevent a judgment, unreviewable because of mootness, from spawning any legal consequences. . . . In determining whether to vacate a judgment that is unreviewable because of mootness, the principal issue is whether the party seeking relief from [that] judgment . . . caused the mootness by voluntary action. . . . A party who seeks review of the merits of an adverse ruling, but is frustrated by the vagaries of circumstance, ought not in fairness be forced to acquiesce in the judgment. . . . The same is true when mootness results from unilateral action of the party who prevailed below.”9
Less well settled in Connecticut is the question of whether we may direct the vacatur of a mooted decision of an administrative agency or whether we can vacate only the judgment of the trial court affirming that decision. Although the parties have not directed our attention to any cases in which this court has vacated, or directed the vacatur of, an agency decision that has
become moot, we note that the Appellate Court has directed the vacatur of a mooted decision of an administrative agency on at least one occasion, albeit without discussion of the issue. See Savin Gasoline Properties, LLC v. Commission on the City Plan, 208 Conn. App. 513, 515, 262 A.3d 1027 (2021).
Moreover, we have generally followed the federal courts’ approach in applying the equitable remedy of vacatur. State v. Charlotte Hungerford Hospital, 308 Conn. 140, 143, 60 A.3d 946 (2013). The federal courts have a policy of vacating agency decisions when such decisions have been rendered moot by the vagaries of circumstances outside of the plaintiff‘s control or by the unilateral action of the party who prevailed in the underlying proceeding. See, e.g., A. L. Mechling Barge Lines, Inc. v. United States, 368 U.S. 324, 329, 82 S. Ct. 337, 7 L. Ed. 2d 317 (1961) (concluding that rules regarding vacatur of unreviewed judgment adopted in United States v. Munsingwear, Inc., 340 U.S. 36, 39-40, 71 S. Ct. 104, 95 L. Ed. 36 (1950), are “equally applicable to unreviewed administrative orders“); Public Citizen, Inc. v. Federal Energy Regulatory Commission, 92 F.4th 1124, 1126-27, 1131 (D.C. Cir. 2024) (vacating mooted agency orders); Valspar Sourcing, Inc. v. PPG Industries, Inc., 780 Fed. Appx. 917, 921 (Fed. Cir. 2019) (“[the United States Court of Appeals for the Federal Circuit] has . . . repeatedly relied on [Munsingwear, Inc.] to vacate agency actions“). PURA does not contest that this court likewise has the equitable authority to direct vacatur of a mooted agency decision.
In the present case, the plaintiff has met its burden of demonstrating equitable entitlement to vacatur of PURA‘s contested ROE order and that portion of the trial court‘s judgment sustaining the order. It was the prevailing party, PURA, whose unilateral action rendered the plaintiff‘s appeal moot, who then invited us to hold that it is moot, and who later represented in a
supplemental brief submitted in this appeal that it has no intention of reinstating the challenged penalties. The plaintiff has pursued every available avenue both to reverse PURA‘s ROE order and to overturn the legal precedent that it established. Directing the vacatur of that portion of the order also eliminates any lingering concerns regarding collateral consequences, such as that the plaintiff may in the future be subject to heavier penalties for any misconduct as a result of having been sanctioned in this case.
III
We next consider the plaintiff‘s challenge to the $61,000 penalty that PURA imposed for the plaintiff‘s delay in reporting two minor accidents in the aftermath of Tropical Storm Isaias. The plaintiff‘s
clude that, in 2020,
This claim presents a question of statutory interpretation. PURA does not contend that its interpretation of the relevant statutory and regulatory scheme is time-tested, such that deference to that interpretation would be warranted. See, e.g., Connecticut Judicial Branch v. Gilbert, 343 Conn. 90, 101-102, 272 A.3d 603 (2022) (we defer to agency‘s formally articulated interpretation of statutes it is tasked with enforcing when that interpretation is both time-tested and reasonable). Accordingly, our review is plenary, and our analysis is cabined by
The primary statutes at issue are
of minor accidents shall constitute a continued violation, pursuant to section 16-41, for the period from the date the person, company or electric supplier is required to notify the authority in writing of such minor accident until the date the authority receives such notice in writing.” (Emphasis added.)
occurrence of such accident, unless such accident is a minor accident, as defined by regulations of the authority. Each such . . . company . . . shall report such minor accidents to the authority in writing, in summary form, once each month. . . . Any . . . company . . . failing to
PURA responds that
There is no question that
There is no definition of the term “continued violation” in
The parties do not dispute that the failure to report a major accident “as soon as may be reasonably possible“;
The question before us is whether the same can be said of the failure to timely report a minor accident. We reject the plaintiff‘s contention that the failure to report such an accident is a single, distinct violation that can be committed only once,
PURA‘s interpretation of the statute, by contrast, is a plausible one. When the deadline to report the two minor accidents had passed, the plaintiff arguably remained in violation of its reporting duty and the harm—depriving PURA of the opportunity to investigate and take any appropriate safety measures—continued to accrue each day that the reporting was delayed.
But PURA‘s interpretation is not the only reasonable interpretation of the statutory language. PURA essentially reads
Because both of these interpretations are consistent with the language of the statute, we conclude that
In 1977, the legislature amended the statute to add a different, monthly reporting requirement for minor accidents. See Public Acts 1977, No. 77-254. Although
This balancing of interests, in which the reporting of minor accidents in summary form is required but not deemed to be a matter of urgency, is consistent with the underlying purposes of the legislative scheme and the very nature of a minor accident. A minor accident is, by definition, less serious than a major one, and the failure to timely report a minor accident is correspondingly less harmful than the failure to report a major one. There also is less urgency with respect to PURA‘s interest in learning of minor accidents, as reflected in the more generous reporting deadline and the fact that there is always at least a ten day period to file a written report. See
For these reasons, we conclude that the version of
IV
Lastly, we turn to the plaintiff‘s challenges to the roughly $1.2 million in fines that PURA had imposed for the plaintiff‘s violation of storm performance standards. The plaintiff challenges two findings underlying PURA‘s determination that the plaintiff violated
Our disposition of these claims is controlled by the highly deferential standard of review imposed by statute. Under the UAPA, a trial court “shall not substitute its judgment for that of the agency as to the weight of the evidence on questions of fact. The court shall affirm the decision of the agency unless the court finds that substantial rights of the person appealing have been prejudiced because the administrative findings, inferences, conclusions, or decisions are: (1) In violation of constitutional or statutory provisions; (2) in excess of the statutory authority of the agency; (3) made upon unlawful procedure; (4) affected by other error of law; (5) clearly erroneous in view of the reliable, probative, and substantial evidence on the whole record; or (6) arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion.”
A
The plaintiff first contends that PURA incorrectly found a violation of an established performance standard when penalizing the plaintiff for not timely and consistently providing a dedicated make safe crew to Bridgeport. The following additional facts and procedural history are relevant to this claim.
At the time of the storm, the Connecticut Emergency Support Function 12: All Hazards Energy and Utilities Annex (annex), which was incorporated by reference in the plaintiff‘s emergency response plan (adopted pursuant to
On appeal to this court, the plaintiff does not dispute that there is some support in the record for these findings. For example, it acknowledges that, on August 6, 2020, the second full day of storm recovery efforts, it failed to provide a make safe crew to Bridgeport during a twelve hour period from 7 a.m. to 7 p.m. Rather, the plaintiff contests PURA‘s ultimate determination that the plaintiff violated
To the extent that the plaintiff‘s claim is that
To the extent that the plaintiff‘s argument is that PURA should have credited Toms’ opinion that the plaintiff had complied with its obligations, those sorts of determinations are for the agency, as the trier of fact, and will not be second-guessed by an appellate tribunal. See
B
The plaintiff also challenges PURA‘s determination that the plaintiff violated
Even if we were to agree with the plaintiff as to those challenges, on the merits of which we express no opinion, the civil penalty can be sustained on an independent ground. PURA imposed a civil penalty of $593,823 for (1) the plaintiff‘s failure to adequately communicate with Bridgeport officials regarding storm recovery efforts and (2) its failure to prioritize the city‘s critical restoration sites.15 Maintaining effective communications was an independent requirement of the plaintiff‘s emergency response plan,16 and there is sufficient evidence in the record to support PURA‘s finding that the plaintiff‘s communications with city officials were at times inadequate.17 Accordingly, in light of our “highly deferential” standard of review of such matters; Sams v. Dept. of Environmental Protection, 308 Conn. 359, 374, 63 A.3d 953 (2013); we will not disturb PURA‘s determination that the plaintiff did not fully satisfy the requirements of its emergency response plan.18
The appeal is dismissed in part, the judgment in the administrative appeal concerning the investigation proceeding is vacated with respect to the imposition of the fifteen basis point ROE penalty, and the matter is remanded with direction to vacate PURA‘s imposition of that penalty; the judgment in the administrative appeal concerning the penalty proceeding is reversed with respect to the fines imposed for the plaintiff‘s failure to timely report two minor accidents and the matter is
In this opinion the other justices concurred.
Notes
In
“(2) Any accidents to employees or to members of the public which were or may have been connected with or due to a utility‘s operation, property or facility, including traffic accidents, resulting in property damage of $50,000 or more, or in personal injury, whether or not hospitalization is required, that are not considered a major accident . . . and
“(3) Any fatalities associated with any vehicular accident involving a utility‘s poles or other facilities but not involving the utility‘s employees or operation.”
This investigation is one essential component of PURA‘s broader statutory obligations within a complex, multitiered regulatory system intended to secure the public safety before, during, and after storms and other potential threats to safety and service. Those obligations include reviewing the overall performance and service restoration practices of each EDC after emergencies; see
We have reviewed the plaintiff‘s other challenges to the minor accident reporting penalty and find them to be without merit.
It seems clear that PURA would have imposed the same $593,823 fine, even if it had found violations only of the plaintiff‘s obligations to adequately communicate with Bridgeport officials. PURA‘s general approach has been to impose identical fines for each category of violations, regardless of the number or type of violations that comprise each category. With respect to Eversource, for example, PURA imposed identical $5 million fines for each of fourteen different categories of violations, departing from this pattern with respect to only one category of especially egregious violations, for which it imposed a fine of more than $28 million. Similarly, PURA initially calculated the plaintiff‘s fines by opting to fine the company a total of one half of one percent of the plaintiff‘s annual distribution revenues, and then dividing that total evenly between the three classes of violations. PURA later concluded that one entire category of violations had not in fact occurred, leaving two categories, each with an identical $593,823 fine.
The plan, for instance, commits the plaintiff to “[ensuring that] communications with the public, customers, media, regulatory agencies, and federal, state, and local governments operate effectively in order to exchange accurate and timely information on system conditions and restoration activities.” The plaintiff reiterates throughout the plan that “[e]ffective, timely and accurate communications with internal and external stakeholder groups [are] a critical part of the restoration process.” Although the plaintiff contends that PURA improperly relied on communications standards established in the annex, in fact, the plaintiff‘s emergency response plan itself incorporates by reference the communications standards set forth in the annex.
There was evidence, for instance, that Bridgeport attempted multiple times to identify vulnerable customers and to develop priority restoration locations through the liaison process but received no response or inaccurate information from the plaintiff. There was further evidence that the plaintiff failed to respond to direct inquiries from Bridgeport Mayor Joseph P. Ganim.
We have reviewed the plaintiff‘s other challenges to the factual findings and discretionary decisions underlying the civil penalties that PURA imposed for violations of
