United Gas Pipe Line Co. v. McCombsUnited Gas Pipe Line Co. v. McCombs
delivered the opinion of the Court.
Under § 7 (c) of the Natural Gas Act, producers who sell natural gas to pipelines for resale in interstate commerce must obtain a certificate of public convenience and necessity from the Federal Energy Regulatory Commission. 1 Section 7 (b) of the Act obligates these producers to continue supplying gas in the interstate market until the Commission authorizes an “abandonment.” 2 The principal issue presented by this case is whether a producer may, consistent with § 7 (b), ever terminate this service obligation without obtaining the agency’s express approval.
I
The natural gas involved in this case is produced from a 163-acre tract of land located in Karnes County, Tex., and
After United installed gathering facilities on the property and began receiving gas from a well 2,960 feet deep, the Butler B lease was assigned several times. H. A. Pagenkopf eventually obtained the leasehold, and in 1961, he agreed to extend the term of United’s gas purchase contract through February 7, 1981. Upon Pagenkopf’s application, the Commission issued a new certificate in 1963, authorizing continued service to United under the same terms as the earlier certificate. In March 1966, Pagenkopf assigned the Butler B. lease to a group headed by L. H. Haring,
3
and shortly thereafter, the only successful well on the property stopped producing. Haring’s operator, Bay Rock Corp., notified United some months later that the existing wells were depleted and no other gas would be available at that time. United replied that it would remove its metering equipment for use elsewhere, but would reinstall the equipment “if, at some future date, you have further gas to deliver to us at the above delivery point, which will be subject to the terms of the above-captioned contract.” App. 8A-9A. Despite the Commission’s subsequent warning that § 7 (b) required the filing
During 1971 and 1972, Haring divided the Butler B leasehold horizontally and vertically, and he assigned to a group headed by respondent McCombs a working interest in the eastern 113 acres of the tract between the depths of 6,500 and 8,653 feet. A few months later, the group acquired a similar interest in the entire Butler B tract from depths of 8,700 to 9,700 feet. Drilling to these deeper horizons, the McCombs group discovered new gas reserves. 5 In 1972, they contracted to sell this gas to respondent E. I. du Pont de Nemours & Co. for industrial uses in intrastate commerce. Upon learning of the renewed production, however, United asserted its rights under the 1953 contract, as extended in 1961, to purchase all gas produced from the property. When the McCombs group rejected this claim, United filed a complaint with the Commission.
The Commission upheld the Administrative Law Judge’s determination that the McCombs group could not sell the
“the abandonment of the service in the instant case was accomplished, as a matter of law, when all of the parties recognized that the then known natural gas reserves were depleted in 1966 followed by failure to provide any service under the certificates for a period of five years during which time there was no evidence of other estimated gas reserves recoverable from the subject leaseholds.” Id., at 1382.
In sum, the Court of Appeals considered the facts so clear that the abandonment issue was no longer “within the expertise of the Commission.” Id., at 1381. The dissenting judge found this conclusion “directly contrary to the plain terms of § 7 (b),” which mandate approval by the Commission as the sole means of effectuating a valid abandonment. Id., at 1382.
We granted certiorari,
II
Congress could not have been more explicit in establishing Commission approval as a prerequisite for lawful abandon
“No natural-gas company shall abandon all or any portion of its facilities subject to the jurisdiction of the Commission, or any service rendered by means of such facilities, without the permission and approval of the Commission first had and obtained, after due hearing, and a finding by the Commission that the available supply of natural gas is depleted to the extent that the continuance of service is unwarranted, or that the present or future public convenience or necessity permit such abandonment.” 52 Stat. 824, 15 U. S. C. § 717f (b).
Not only does the statute require companies to obtain the “approval of the Commission . . . after due hearing,” but it also prohibits abandonment absent specific findings by the Commission. The language of § 7 (b) simply does not admit of any exception to the statutory procedure. 9
This plain meaning has been acknowledged in several of our previous decisions. Emphasizing that the Natural Gas Act’s fundamental purpose was to assure the public a reliable supply of gas at reasonable prices, the Court noted in
Atlantic Refining Co.
v.
Public Service Comm’n,
“[I]f the companies, failing to find new sources of gas supply, desired to abandon service because of a depletion of supply, they would have to make proof thereof before the Commission, under § 7 (b). The Commission thus, even though there may be physical problems beyond its control, [keeps] legal control over the continuation of service by the applicants.” Id., at 158 n. 25.
In short, Sunray makes clear that producers must secure Commission approval to abandon service even when there is little or no doubt that gas supplies are exhausted.
This Court expressed a similar understanding of the abandonment provision in
United Gas Pipe Line Co.
v.
FPC,
Thus, we have consistently recognized that the Commission’s "legal control over the continuation of service,” Sunray, supra, at 158 n. 25, is a fundamental component of the regulatory scheme. To deprive the Commission of this authority, even in limited circumstances, would conflict with basic policies underlying the Act.
Requiring Commission approval, “after due hearing,” permits all interested parties to be heard and therefore facilitates full presentation of the facts necessary to determine whether § 7 (b)’s criteria have been met. Contrary to respondents’ assumption, see Brief for Respondents 20-21, the Commission does not automatically approve abandonments whenever production has ceased. Indeed, the agency recently refused to grant an application where the producer had not adequately tested for new gas reserves.
10
Had the lessees in the instant case filed an application for abandonment between 1966 and 1971, United might well have demonstrated that exploration
Moreover, the obligation to obtain Commission approval promotes certainty and reliability in the regulatory scheme. Knowledge that termination of service is lawful only if authorized by the Commission enables producers, prospective assignees, and other interested parties to determine with assurance whether a particular tract remains dedicated to interstate commerce. In contrast, the Court of Appeals’ test for de facto abandonment would invite speculation regarding the extent of the Commission’s jurisdiction. The confusion that would inevitably result from the lack of clear standards as to when producers must seek Commission approval fortifies our conclusion that Congress intended agency supervision of all abandonments.
Ill
Respondents maintain that even if producers must always obtain Commission approval for abandonment, the decision below should nevertheless be affirmed. In their view, the Court of Appeals actually concluded that the Commission had erred as a matter of law by refusing to authorize an abandonment retroactively. Assuming this was the true purport of the decision below, we believe the Court of Appeals lacked
Although respondents urged the agency to authorize an abandonment of service from Butler B, the Administrative Law Judge and the Commission rejected this suggestion in light of the clear evidence that the leasehold was still capable of production. Respondents, however, contend that because Haring acted in good faith in failing to seek agency approval, the Commission was obligated to treat their answer to United’s complaint as if it were an abandonment application filed in 1966. Thus, according to respondents, the Court of Appeals was entitled to conclude that the Commission should have ignored the evidence of subsequent production and authorized an abandonment based on the evidence available in 1966.
We need not determine whether § 7 (b) allows the Commission to approve an abandonment retroactively and disregard evidence of subsequent production.
11
For the agency certainly did not abuse its discretion in declining to do so here. Authorizing abandonments retroactively would often deprive interested parties of the opportunity to be heard at a meaningful time and to present evidence on the likelihood of renewing gas production in the future. Thus, the Commission would be required to determine on a hypothetical set of facts what action it would have taken had an application been timely filed. Additionally, the jurisdictional status of all dedicated acreage would become uncertain, since the property would be subject to retroactive Commission pronouncements in the indefinite future. Frequent retroactive action would
IY
Finally, respondents defend the judgment below on the ground that only the depleted shallow reserves underlying Butler B, as opposed to the newly discovered gas, were subject
Our prior decisions compel rejection of this narrow statutory interpretation. In
California
v.
Southland Royalty Co.,
we expressly agreed with the Commission that the “initiation of interstate service pursuant to the certificate
dedicated all fields subject to that
certificate.”
• The judgment of the Court of Appeals is
Reversed.
Notes
52 Stat. 825, as amended, 15 U. S. C. §717f (e). See
Phillips Petroleum Co.
v.
Wisconsin,
Section 7 (b), 52 Stat. 824, 15 U. S. C. §717f (b), provides:
“No natural-gas company shall abandon all or any portion of its facilities subject to the jurisdiction of the Commission, or any service rendered by means of such facilities, without the permission and approval of the Commission first had and obtained, after due hearing, and a finding by the Commission that the available supply of natural gas is depleted to the extent that the continuance of service is unwarranted, or that the present or future public convenience or necessity permit such abandonment.”
Although Haring advised United that he would apply to the Commission for a successor producer certificate, no application was ever filed. App. to Pet. for Cert, in No. 78-17, pp. A-6 to A-7.
The Secretary of tbe Commission wrote Bay Rock in January 1971 that it would be necessary to file an application for permission to abandon service and a notice of cancellation of rate schedule. Id., at A-100 to A-101. This letter also directed the lessee to submit either a copy of any agreement with United canceling the gas purchase contract or a statement from United “indicating its position with respect to the proposed abandonment.” Ibid. The Secretary had written a similar letter to Pagenkopf in August 1968, but he, too, failed to respond. Id., at A-97 to A-98.
In addition to the Butler B interests, the McCombs group also owned an interest in an adjoining tract of land. In order to operate both tracts as a single entity, the group “unitized,” or combined, their interests in Butler B with those in the corresponding depths of the adjacent tract. As a result, a fraction of the production from each of four successful wells located on the total unitized acreage is attributable to the Butler B leasehold for purposes of the gas purchase contract and the Commission’s certificates. Id., at A-8 to A-10. See generally 6 H. Williams & C. Meyers, Oil & Gas Law 2-3 (1977 ed.).
In determining the scope of Pagenkopf’s certificate, the Commission analyzed separately the depths covered and the duration of the obligation to sell gas in interstate commerce. The Commission based its conclusion that the certificates encompassed all reservoirs on the absence of any reference to particular depths in either the applications 'for certification, which incorporated the contract with United, or in the certificates issued Pagen-kopf and Ms. Quin. App. to Pet. for Cert, in No. 78-17, pp. A-29 to A-35. Referring to the same documents, the Commission interpreted Pagen-kopf’s certificate to encompass all gas produced from wells drilled before the contract’s expiration date, even if the gas is extracted after February 7, 1981.
Ibid.
However, the Commission refused to consider whether the certificate also covered gas produced from wells drilled after the contract’s expiration date.
Id.,
at A-33, and n. 28; see
Sun Oil Co.
v.
FPC,
The Commission did not address the validity of United’s gas purchase contract. McCombs has raised that issue in a separate suit, which is being held in abeyance pending completion of this litigation. McCombs v. United Gas Pipe Line Co., No. SA-73-CA-210 (WD Tex., filed Aug. 2, 1973).
The Court of Appeals rendered this decision on rehearing after withdrawing an earlier opinion by a different panel. See
Although Congress has recently revised the federal scheme for regulating natural gas, see the Natural Gas Policy Act of 1978, 92 Stat. 3351, that legislation does not affect the outcome of this case. With certain exceptions not relevant here, gas reserves dedicated to interstate commerce before November 8, 1978, remain subject to § 7 (b) of the Natural Gas Act. See §§ 2 (18), 104, 106 (a), and 601 (a) of the Natural Gas Policy Act, 92 Stat. 3354, 3362, 3365, 3409,15 U. S. C. §§ 3301 (18), 3314, 3316 (a), 3431 (a) (1976 ed., Supp. Ill); S. Conf. Rep. No. 95-1126, pp. 71-72, 82, 84-85, 123-124 (1978); H. R. Conf. Rep. No. 95-1752, pp. 71-72, 82, 84-85, 123-124 (1978).
See Texaco, Inc., FERC Docket Nos. G-8820 et al, Order Granting Petition for Reconsideration and Modifying Prior Order (Nov. 1, 1977).
Respondents contend that the Commission recently approved a retroactive § 7 (b) abandonment in Arkansas Louisiana Gas Co., FPC Docket No. CP76-329 (Mar. 8, 1977). In that case, a certificated pipeline had agreed to sell excess gas, but its supply became depleted in 1971. Although the pipeline did not seek abandonment permission until 1977, the Commission approved the abandonment because the supply of excess gas was still depleted and there was no likelihood of obtaining additional gas. The agency's decision therefore had no retroactive impact.
Relying on four lower court decisions that did not involve § 7 (b), respondents argue that the Commission was required to approve abandonment retroactively here. None of these cases, however, supports respondents’ contention that the Commission abused its discretion in this suit. In
Ellwood City
v.
FERC,
Plaquemines Oil & Gas Co.
v.
FPC,
146 U. S. App. D. C. 287,
Since the Commission and lower federal courts have held that § 7 (b) prohibits abandonment of service without agency approval even where the producer has not obtained a certificate, see, e.
g., Cumberland Natural Gas Co.,
34 F. P. C. 132 (1965);
Mesa Petroleum Co.
v.
FPC,
The agency’s decisions have reflected a similar understanding of §7 (b). For example, in
Cumberland Natural Gas Co., supra,
where the