¶ 1. December 11, 2007. Defendant Wright & Morrissey, Inc. (Wright) appeals from a superior court judgment awarding $102,477 to plaintiff Union School District #45 for the costs to reconstruct sidewalks damaged by frost heaves less than a year after they were built. Wright contends the judgment must be reversed because: (1) an arbitration agreement between the parties divested the court of subject matter jurisdiction; (2) the District failed to comply with the contract’s alternative-dispute resolution procedures; (3) the court based its decision upon an erroneous finding that the project architect had determined Wright to be liable for the costs to implement recommended design changes; and (4) the court improperly declined to award prejudgment interest on its counterclaim. We reverse the court’s prejudgment interest ruling and affirm in all other respects.
¶ 2. In 1996, the District entered into a contract with Wright for the construction of a new middle school designed by the architectural firm of Banwell White Arnold Hemberger & Partners, Inc. (Banwell). The school was completed in the summer of 1997 and in use by September. That winter, however, a stretch of sidewalk adjacent to the school suffered damage due to frost heaves. The damage became more acute over the next several winters. In May 2000, an engineering firm hired by Banwell to determine the cause of the problem issued a report (the Knight report) indicating that it was partly the result of sub-base gravel which did not conform to the design specifications. Wright, the contractor, was made aware of the Knight report and, in response, engaged its own expert who issued an analysis (the Willis report) concluding that the frost heaves were primarily caused by the architect’s failure to include adequate drainage, or “groundwater control” in its original design. Neither the architect nor the contractor, therefore, accepted responsibility for the frost-heave problem or the cost of repair.
¶ 3. To resolve the apparent deadlock, the District hired its own engineering firm, Lamoureux & Dickinson, to assess what went wrong and recommend a remedy. The resulting report (the Lamoureux report) contained a detailed, comprehen
¶ 4. Accordingly, in December 2001, the District, through its attorney, notified Banwell’s attorney that it was implementing § 4.3.2 of the General Conditions of the Contract for Construction (General Conditions), a standard form agreement promulgated by the American Institute of Architects that was incorporated as an addendum to the construction contract. The provision invoked by the District establishes a two-step alternative-dispute-resolution (ADR) process for claims relating to the contract. It states, in pertinent part, that “[cjlaims, including those alleging an error or omission by the Architect, shall be referred initially to the Architect for action as provided in Paragraph 4.4.” The latter provision prescribes a series of steps to be taken by the contractually designated “Architect,” in this case Banwell, in response to a claim. After reviewing the claim, “the Architect” is to issue a preliminary response, which may include a request for additional data, rejection of the claim in whole or part, approval of the claim, or a proposal for compromise. Thereafter, if the claim has not been resolved, “the Architect” is to issue a final decision “which decision shall be final and binding on the parties but subject to arbitration.” General Conditions, § 4.4.4. Either party may then proceed to the second step in the ADR process, arbitration. As provided in the General Conditions, when a decision of “the Architect” states that it is “final but subject to arbitration,” a demand for arbitration “must be made within 30 days after the date on which the party making the demand receives the final written decision.” General Conditions, § 4.5.4.1 Furthermore, a “failure to demand arbitration within said 30 days’ period shall result in the Architect’s decision becoming final and binding upon the Owner [i.e., the District] and Contractor.” Id.
¶ 5. The District’s letter identified four claims: (1) that the sidewalks were improperly designed; (2) that Wright failed to notify the District and the architect in a timely manner of errors or omissions in the design plans; (3) that Wright failed to construct the sidewalks in conformance with the plans and specifications; and (4) any combination of the above. The District requested “that these claims be resolved by implementation, at no cost to the District, of the recommendations set forth” in the Lamoureux report. In early January 2002, Banwell’s attorney sent a letter to the District “to serve as Banwell Architect’s Decision under § 4.4, et seq. of the General Conditions.” The letter succinctly responded to each of the four claims. With respect to the claim of design error, the letter stated that “[t]he Architect rejects this claim in its entirety.” As to the failure to notify, the letter reiterated Banwell’s conclusion that there were no errors or omissions in the design plans, but “assuming arguendo that there were” agreed that the contractor was required to report them. Finally, with respect to the claim that Wright had failed to construct the sidewalks in accordance with the plans, the letter indicated that “[t]he Architect agrees with this claim in its entirety.” The letter closed with the conclusion “that the responsibility for this claim rests with the Contractor, as supported by the 7/01 [Lamoureux & Dickinson] report.”
¶ 7. Wright neither requested arbitration following Banwell’s decision nor undertook to reconstruct the sidewalks in accordance with recommendations in the Lamoureux report. Accordingly, in August 2002, the District filed a complaint in superior court seeking to enforce Banwell’s “final and binding” decision by compelling Wright to perform the corrective work. The action was later amended to one for monetary damages to recover the costs of performing the work in question. Thereafter, in a series of preliminary rulings, the trial court determined that the parties had effectively waived arbitration, resulting in Banwell’s decision becoming final and binding; rejected Wright’s claim that certain procedural deviations from the General Conditions invalidated Banwell’s decision; concluded that the absence of a specific remedy in Banwell’s decision was not fatal to the decision as a whole; and ruled that damages would be established at trial. Following an evidentiary hearing, the court issued a final written decision concluding that, by approving the District’s claim against Wright, Banwell had implicitly granted the relief sought, to wit, implementation of the recommendations in the Lamoureux report.
¶ 8. Wright first contends that the court lacked subject matter jurisdiction because the dispute was subject to an arbitration agreement. We recently rejected an identical claim in Lamell Lumber Corp. v. Newstress International, Inc.,
¶ 9. Wright next contends that certain deviations from the procedures set forth in the General Conditions render Banwell’s decision invalid. We note, at the outset, that Wright failed to raise any of
¶ 11. Wright next asserts that Banwell’s decision was invalid because it was communicated to the parties in a letter from its attorney. The claim is that Jules Chatot, Banwell’s authorized representative under the contract, was the only person empowered to render a decision and that “a decision by the attorney for Banwell White, or by the firm itself is not a decision by Jules Chatot.” The claim is entirely unpersuasive. First, General Conditions § 4.1.1 provide that “[t]he term ‘Architect’ means the Architect or the Architect’s authorized representative,” and “the Architect” is identified in the contract as the firm of Banwell, White, Arnold, Hemberger & Partners, Inc. (Emphasis added.) Thus, either the firm or its representative was authorized to render a decision. Furthermore, the letters from the attorney state plainly that they are “to serve as Banwell Architect’s decision,” and they go on to describe “the Architect’s” decision with respect to each of the District’s four claims. (Emphasis added.) We find no support, therefore, for the claim that the decision was not rendered by Banwell. The mere fact, moreover, that the decision was communicated in a letter signed by the attorney on behalf of Banwell rather than by its members or authorized representative is a difference, at most, of form rather than substance.
¶ 12. Wright further contends that Banwell was powerless to render a decision because the District failed to file its claim “within 21 days after occurrence of the events giving rise to [the] claim or within 21 days after the claimant first recognized the condition giving rise to the claim,” as provided in § 4.3.3 of the General Conditions. As we have seen, however, Wright waived this issue by failing to raise it in the first instance in the ADR proceeding. Furthermore, because arbi
¶ 13. Wright’s final complaint regarding procedure is that Banwell violated its right to due process by failing to hold a hearing or offer an opportunity to introduce evidence, cross-examine witnesses, or otherwise oppose the District’s claims. Nothing in the record, however, shows that Wright ever requested such a hearing or sought to assert these rights, nor did it exercise its right under the agreement to a more formal arbitration proceeding following Banwell’s decision. The claim, therefore, was waived.
¶ 14. Wright next contends the trial court erred in finding that Banwell’s decision represented a final and binding decision granting relief in favor of the District. Because the Lamoureux report, on which the architect relied, did not recommend reconstruction in accordance with the original design plan, Wright maintains that Banwell’s decision “does not award any relief to the District for the Contractor’s alleged failure to construct the sidewalk in accordance with” that plan. While there may have been some inconsistency in Banwell’s decision, there is no doubt of its purpose to grant the District relief in the form of the Lamoureux recommendations. The District specifically requested that all of its claims “be resolved by implementation, at no cost to the District, of the recommendations” in the Lamoureux report, and Banwell’s decision, in agreeing with the District’s claim against Wright “in its entirety,” can reasonably be construed only as a finding of liability and an award of the relief requested. Indeed, Banwell made plain its intent to hold Wright responsible for the reconstruction pursuant to the report, concluding: “[T]he Architect believes that the responsibility for this claim rests with the contractor, as supported by the report issued by Lamoureux & Dickinson on behalf of the owner in July 2001.” Accordingly, we find no error.
¶ 15. Finally, Wright contends that the court erred in failing to award prejudgment interest on the $5,000 damages it
That portion of the trial court judgment denying prejudgment interest is reversed, and the matter remanded to calculate the interest due and modify the judgment accordingly. In all other respects, the judgment is affirmed.
Motion for reargument denied January 10, 2008.
Notes
Banwell may have intended the first letter to serve as its “preliminary” response, as called for in § 4.4.1 of the General Conditions, and the second letter to serve as its final decision after the parties indicated that the dispute remained unresolved.
This finding by Judge Katz was somewhat inconsistent with the earlier decision by Judge Cook indicating that Banwell had failed to grant relief.
We note that some commentators have criticized ADR proceedings of this type, questioning the ability of the design professional to remain neutral where it has a professional relationship with the owner and where its own professional judgment may be at issue, as was the case here. See, e.g., T. Stipanowich, Beyond Arbitration: Innovation and Evolution in the United States Construction Industry, 31 Wake Forest L. Rev. 65, 74 (1996) (noting concerns about the “conflict of interest inherent in the design professional’s concurrent roles” as contractee with the owner and arbiter of disputes involving design defects); T. Galligan, Extra Work in Construction Cases: Restitution, Relation
