235 Pa. 435 | Pa. | 1912
Opinion by
The contention in this case arose out of the distribution of a fund which resulted from a sheriff’s sale, under a judgment upon a writ of scire facias sur mortgage. The question involved was whether the lien of the mortgage was prior to that of certain mechanics’ liens. Exceptions were filed to the schedule of distribution, as reported by the sheriff, and the matter was referred to an auditor. Testimony was taken on behalf of the lien claimants, and of the mortgagee. The auditor sustained the validity of the mechanics’ liens, and held that they were prior to the lien of the mortgage. The auditor found as a matter of fact that the several buildings described in the mechanics’ liens filed, constituted a single business plant, and he held that the failure of the claimants to state this fact in the claim did not invalidate the liens. The court below confirmed the report of the auditor, and directed distribution to be made in accordance therewith. The mortgagee has appealed, and its counsel here contend that the lien of the appellee was invalid, (1) because it included a claim both for repairs and for
From the findings of fact by the auditor it appears that the work which was done by the appellee under his contract in this case was in substance that of new construction after a fire. A comparatively small part of the work, if standing by itself, would properly have been classed as repairs; but the auditor treated this part of the work as having been merged in the whole work of construction. He says that “the repair work to the houses standing alone would be repairs, but in this case they must be taken in conjunction with the whole work, because the contract really was to reconstruct the plant and buildings, and the work, both the new and the repairs, consisted of actually rebuilding the plant and buildings. All of the work, therefore, is to be considered as new work.” This conclusion seems to us to be sound, and is in line with the main purpose of the mechanics’ lien law, as set forth in the Act of June 4,1901, P. L. 431. Turning to section 2, we find that a lien is authorized for “erection and construction,” and also for “alteration and repair.” And in section 3, it is provided that “a substantial addition to a structure or other improvement shall be treated as a new erection or construction thereof.”
The court below agreed with the auditor that the work which the claimant described as repairs, really constituted a part of the construction of the plant as an entirety. We have, then, the finding of the auditor that this is a case of erection and construction, which finding is expressly approved by the court below, and we see nothing in the evidence which would justify us in disturbing this finding.
The assignments of error are overruled, and the decree of the court below is affirmed.