Lead Opinion
INTRODUCTION
{1 This appeal concerns the voidability of certain government contracts. Specifically, we consider the question of when a contract entered into by a predecessor governing body is voidable by a successor governing body. Throughout the country, substantial case law has developed to distinguish between those government contracts that may be voided and those that may not be voided by a successor governing body. Various common law tests have been articulated, all designed to balance the tension between the right of a successor governing body to implement its own policies and not be bound by those of a former body, and the interest in providing some certainty to parties who contract with governing bodies. Utah courts have relied on the governmental/proprietary test, a test under which contracts involving proprietary functions and having reasonable durations are enforceable against successor governing bodies. -
T2 In this case, the district court granted summary judgment to a county hospital on the theory that the particular contract at issue, a contract for the provision of pathological services to the hospital by a doctor, was voidable by the hospital's governing body-its board of trustees. The district court held that the contract had been entered into by a predecessor board and thus was voidable by successor boards.
T3 Because we conclude that the contract for pathological services involves a proprietary function, we remand with instructions that the district court determine whether the contract's duration was reasonable.
BACKGROUND
T 4 The following facts are undisputed. On November 29, 1994, Dr. Leo Hardy entered into a contract with Uintah Basin Medical
T5 Although Dr. Hardy performed his contractual obligations satisfactorily and received no complaints from UBMC or its medical staff, on July 18, 1996, the UBMC board of trustees voted to give Dr. Hardy ninety days' notice and invite another doctor to join its medical staff as a pathologist and emer-geney room physician. When Dr. Hardy's termination became effective, UBMC sought a declaratory judgment that it had "just cause" to terminate the contract. Dr. Hardy counterelaimed, contending that UBMC materially breached the contract by terminating him because UBMC did not have "just cause." The district court initially denied the parties' respective motions for summary judgment, ruling that the jury would decide whether UBMC had "just cause".
T 6 Following this ruling, the district court accepted supplemental briefing from the parties on an issue UBMC had raised for the first time in its answer to Dr. Hardy's counterclaim: whether the contract violated common law rules against government contracts that bind successor governing bodies. After hearing from the parties, the court granted UBMC summary judgment on the ground that the contract was voidable even without " 'just cause' simply because it could not bind successor Boards." In reaching this conclusion, the district court explained, "Due to the rapid advance of science, medicine [sic] changes and needs of patients there should be no reason for such an agreement to continue into the future or be binding on successor where the governing [bloard is a governmental entity." Dr. Hardy appeals. Section 78-2-2(8)(j) of the Utah Code gives us appellate jurisdiction over this case. Utah Code Ann. § 78-2-2(8)(j) (Supp.2001).
ANALYSIS
I. STANDARD OF REVIEW
17 "In deciding whether the trial court correctly granted [summary] judgment as a matter of law, 'we give no deference to the trial court's view of the law; we review it for correctness" " SME Indus., Inc v. Thompson, Ventulett, Stainback & Assocs.,
II. RATIONALE BEHIND COMMON LAW RESTRICTIONS ON GOVERNMENT CONTRACTS THAT BIND SUCCESSOR GOVERNING BODIES
[ 8 Before addressing Dr. Hardy's specific claims on appeal, we briefly discuss the rationale behind the common law rules regarding contracts that bind successor governing bodies.
19 Government contracts raise public policy concerns beyond those involved with private contracts. See, e.g., Mitchell v. Chester Hous. Auth.,
10 While such concerns militate against enforcing a predecessor governing body's contracts against its successors, the common law also recognizes a countervailing concern: that permitting successor governing bodies to indiscriminately terminate government contracts may make private parties hesitant to contract with government entities, thereby reducing the viability of contracts as a means of solving public problems. See Plant Food Co. v. City of Charlotte,
111 A desire to accommodate these competing concerns animates the various common law tests for determining whether a
{12 Having set forth the governmental/proprietary test, we next apply it to Dr. Hardy's contract to determine whether the contract may be validly enforced against sue-cessor hospital boards of trustees.
III WHETHER DR HARDVS CONTRACT IS ENFORCEABLE AGAINST SUCCESSOR BOARDS OF TRUSTEES
113 Dr. Hardy maintains the district court erred in concluding that his contract was voidable because it bound successor boards.
A. Dr. Hardy's Contract Was Proprietary in Nature
14 The factors on which courts have relied to distinguish between governmental and proprietary contracts strongly support the conclusion that Dr. Hardy's contract for pathological services involves a proprietary function. First, UBMC has not demonstrated that the services Dr. Hardy provides under the contract are "indispensable to the proper functioning of government." County Council v. SHL Systemhouse Corp.,
{15 Moreover, under the terms of the contract, Dr. Hardy merely recommended, but did not have authority to set, policies related to UBMC's pathology laboratory. The board's retention of this policymaking discretion weighs heavily in favor of deeming the contract proprietary. See Rhode Island Student Loan Auth. v. NELS, Inc.,
116 Accordingly, we conclude that Dr. Hardy's contract involves a proprietary function.
117 Under the governmental/proprietary test, Dr. Hardy's proprietary contract is enforceable if its duration was reasonable at the time the parties executed the contract. Bair,
118 As the record has been inadequately developed on the issue of the reasonableness of the contract's duration, we remand to permit the district court to allow further development of the record and to then make this determination. On remand, as a preliminary matter, the district court should interpret the intended scope of the contract's "just cause" provision,
T19 If the district court determines that the contract's duration is reasonable, the contract is enforceable. The court should then determine whether the UBMC board had "just cause" to terminate Dr. Hardy. On the other hand, if the district court determines that the contract's duration is unreasonable, the court should not enforce the contract.
120 The dissent maintains that a term should be implied into Dr. Hardy's contract. In support of its argument, the dissent relies on canons of construction that have been.developed to aid courts in discerning the parties' intent when a contract fails to specify a duration. We reject the dissent's position for several reasons. First, and most importantly, neither party has argued in their briefs in favor of implying a term. To the contrary, both parties maintain that the contract should be evaluated as an indefinite-length contract whose duration is limited only by the "just cause" provision
T21 Second, conspicuously absent from the dissent's analysis is any citation to Utah precedent that supports its position. Contrary to the dissent's position, when a contract for employment or personal services does not recite a fixed term, the law in Utah does not call for the judicial reformation of the contract to impose a term, especially where, as here, neither party disputes the contract was of indefinite duration. Indeed, in a case in which we traced the historical development of the law associated with employment contracts, we specifically noted that courts long ago repudiated a common law rule under which a term was implied when an employment contract did not specify a duration. Berube v. Fashion Centre, Ltd.,
¶ 22 Applying Utah precedent to Dr. Hardy's contract confirms our view that a term should not be read into the contract. First, because Dr. Hardy's contract does not specify a duration, under Utah law we initially presume it is of indefinite duration but terminable at will. Berube,
¶ 23 Finally, we disagree with the dissent's contention that the imposition of a term is justified as a means of easing the calculation of prospective damages.
While a district court has considerable experience in calculating future earnings, some basis must appear in the record for such an award. Some of the factors which district courts have employed to alleviate the speculative nature of future damage awards include an employee's duty to mitigate, "the availability of employment opportunities, the period within which one by reasonable efforts may be re-employed, the employee's work and life expectancy, the discount tables to determine the present value of future damages and other factors that are pertinent on prospective damage awards."
Shore v. Fed. Express Corp., TT7i F.2d 1155, 1160 (6th Cir.1985) (quoting Koyen v. Con-sol. Edison Co.,
CONCLUSION
¶ 24 We conclude that Dr. Hardy's contract for pathological services is a proprie
1 25 Remanded.
Notes
. Citing various criticisms of the governmental/proprietary test, both parties urge us to repudiate it in favor of other common law tests. However, because the parties have failed to show that any of their suggested tests is clearly better than the governmental/proprietary test, we decline to repudiate it at this time. See State v. Menzies,
. Dr. Hardy also argues that the rationale behind the common law rules does not apply (1) to appointed, staggered boards like the UBMC board of trustees, or (2) until a majority of the nine voting members of the board are replaced. These arguments are without merit. First, the rationale behind the common law rules applies to appointed, staggered governing bodies because preexisting contracts may also unduly inhibit these bodies in the performance of their public duties. See Mitchell,
In addition, Dr. Hardy argues that the successor UBMC board was precluded from terminating his contract because the board earlier ratified it. Since this issue was not raised below, we decline to address it. See Monson v. Carver,
. See Miller v. USAA Cas. Ins. Co.,
. Under UBMC's bylaws, although appointments to the medical staff are ostensibly limited to two years, staff members are reappointed unless there is "just cause." Under the bylaws, "just cause"" appears to have a broad scope: for instance, the board may terminate a member of the medical staff for any reason "reasonably related to the delivery of quality patient care."
. Dr. Hardy asserts the following in his appellate brief:
To entice excellent physicians to move to and remain in rural areas, hospitals often add perks to the contracts, including "just cause" termination provisions, or even "lifetime" contracts.... Given the necessities of the situation, such contracts are of reasonable duration. Thus, [Dr. Hardy's contract] passes the second part of the Bair test....
Appellant's Br. at 21.
Despite disagreeing with Dr. Hardy on the ultimate conclusion of whether an indefinite-
The potentially perpetual duration of Dr. Hardy's contract with UBMC was limited only by the "just cause" provision.... [Dr. Hardy's] contract bound Duchesne County indefinitely....
Appellee's Br. at 28-29.
. The dissent acknowledges that parties may enter into an indefinite-length contract.
. The dissent acknowledges that "both parties contend that the contract should be evaluated as an indefinite-length contract limited only by just cause," yet nonetheless argues for the imposition of a fixed duration. The dissent has cited no cases, nor are we aware of any, in which we rejected parties' mutual concessions that are in harmony and clearly expressed. Given that the goal in interpreting contracts is to give effect to the intent of the parties, we should be particularly reluctant to reject the parties' stipulations or concessions in this case.
The clear import of the parties' concessions is that the parties intended the contract to be of indefinite duration. The imposition of a fixed duration is therefore incompatible with the parties' concessions. Moreover, the law in Utah and numerous other jurisdictions recognizes the right of parties to enter into indefinite length contracts terminable for cause. Johnson v. Morton Thiokol, Inc.,
Significantly, the dissent also acknowledges that the parties have not argued in their appellate briefs that a term should be implied into the contract. In the absence of adequate briefing, it would be ill-advised for the court to raise this issue sua sponte, especially if the dissent is correct in asserting that this issue presents a question of first impression. Prince v. Bear River Mut. Ins. Co.,
. Although Berube was a plurality opinion, a majority of the court concurred in the portion of the opinion that traced the historical development of the common law of employment contracts.
. The cases cited by the dissent are (1) from other jurisdictions and therefore not binding and (2) are either distinguishable from, or inapposite to, the present case. In reaching its conclusion, the dissent relies heavily on cases not involving employment contracts. This reliance is tenuous given the fact that courts have developed a unique set of rules for employment and personal service contracts. See generally Berube,
For example, the dissent cites Mid-Southern Toyota, Ltd. v. Bug's Imports, Inc.,
The cases cited by the dissent that involve employment contracts provide little support for its conclusion that a term must be imposed on Dr. Hardy's contract. For example, when faced with an indefinite-length employment contract, the court in Paisley v. Lucas did not impose a term but rather applied rules of construction specific to employment contracts.
. The dissent asks the following:
[If hospital breached the contract], how would Dr. Hardy's damages be calculated? Would Dr. Hardy be entitled to all of his loss of earnings under the indefinite contract? [WJould he be entitled to compensation ... to the date of his death? To the date of his retirement? To the date of his inability to perform his job responsibilities ... ?
Concurrence Opinion
concurring in part and dissenting in part.
127 I concur with the majority opinion that the contract in question is proprietary in nature and could therefore bind the successor trustees of the hospital. However, I differ with the analysis of the opinion as to how the trial court is to determine the reasonableness of the duration of the contract on remand.
{23 Well-settled canons of contract construction and interpretation dictate that the trial court, when faced with a contract of employment that is silent as to its duration, and thus indefinite in length, but expressly terminable only for just cause, should determine by implication a reasonable term of duration under the cireumstances and then imply that reasonable term into the contract as a matter of law. Onee the trial court determines a reasonable term and implies it into the contract as a matter of law, the trial court then should evaluate the implied duration of the contract to determine if the duration of the contract was reasonable for purposes of deciding whether the successor trustees of the hospital are bound by the contract.
{29 The employment contract between Uintah Basin Medical Center and Dr. Hardy did not include a specific term of duration and therefore was of indefinite duration or perpetual in nature. It did, however, expressly indicate that the contract could be terminated only for just cause. Corbin on Contracts provides guidance on how to treat such a contract and indicates what legal ef-feet such a contract is to be given when it states:
When parties make a contract of employment without specifying the length of service, but indicate that it is not terminable at will, the legal effect is that the parties are bound for a "reasonable time." This is based upon "implication" [i.e., the implication of a reasonable term of duration].
Catherine M.A. McCauliff, 8 Corbin on Contracts § 34.11, at 262 (revised ed.1999) (emphasis added); see also Consol. Theatres, Inc. v. Theatrical Stage Employees Union Local 16,
"I 30 The determination of what constitutes a "reasonable time" of duration of the indefinite-length employment contract that is not terminable at will is either "(1) the time that seems reasonable in the light of the circumstances existing when the contract was made [or] (2) the time that seems reasonable in light of the cireumstances as they occur during the course of performance." McCauliff, 8 Corbin on Contracts § 34.11, at 262. The reasonableness of an implied duration term is a question of fact and is determined in reference to the circumstances surrounding the transaction, the situation of the parties, and the subject matter of the contract. See William B. Tanner Co. v. Sparta Tomah-Broad. Co.,
1 31 Corbin on Contracts' suggested treatment of contracts of this nature is based upon and supported by well-settled principles and rules of contract construction and interpretation. In the instant case, the employment contract was silent as to its duration and therefore indefinite or perpetual. Contracts of perpetual duration are generally disfavored by the law. See Paisley v. Lucas,
132 Where a contract is of indefinite or perpetual duration because of the lack of an explicit term, the law will imply into the contract a term that is reasonable under the cireumstances. See McCauliff, 8 Corbin on Contracts § 34.11, at 262; see also Metal Assocs., Inc.,
T33 The majority opinion criticizes this dissent for its lack of citation to Utah precedent in support of determining and implying a reasonable term of duration into the contract. This is empty criticism given that this case presents an issue of first impression in this jurisdiction.
T 34 The majority opinion incorrectly relies on Berube v. Fashion Centre, Ltd., TTl P.2d 1083 (Utah 1989), Brehany v. Nordstrom, Inc.,
11 35 Specifically, the majority opinion's assertion that in Berube we noted (and purportedly endorsed) the notion that "courts long ago repudiated a common law rule under which a term was implied when an employment contract did not specify a duration" is not entirely correct and overstates Berube. The central issue in Berube was whether the termination-related provisions of an employer's employee handbook could be implied into the employment contract as implied-in-fact contract terms between the employer and employee such that the original indefinite-length employment contract would escape application of the "at-will" employment doe-trine that provides an indefinite-length employment contract is terminable by either party for good cause, cause, or no cause at all.
136 In the "historical development" portion of Justice Durham's plurality opinion in Berube, to which the majority opinion in this case cites, Justice Durham merely traced the historical development and adoption of the "at-will" employment doctrine in the United States.
187 In any event, that section of Berube does not stand for the proposition offered by the majority opinion. The historical review section of the Berube plurality opinion simply described the nineteenth century English common law rule stating that English courts, when faced with employment contracts of indefinite duration, would imply an arbitrary one-year term into the contract. Berube, 77l P.2d at 1040-41; see also McCauliff, 8 Corbin on Contracts § 34.11, at 257. Berube's historical review merely noted that American courts rejected the arbitrary one-year term implied by English courts in favor of the "at-will" employment doctrine. Berube,
138 Finally; Johnson and Brehaony likewise do not govern the present case or bar the imposition of an implied reasonable term of duration into the contract. Brekhany and Johnson, like Berube, were employee handbook or implied-in-fact contract term cases but go no further than Berube in their holdings and no more state an on-point or governing rule applicable in this case than does Berube.
139 Berube, Brehany, and Johnson all involved indefinite-length employment contracts and claims of wrongful termination.
€{40 The case at hand involves an indefinite-length contract which contained an express "just cause" provision. Because that provision was expressed, the analysis and rules in Berube, Brehany, and Johnson are not applicable; we already know that the express "just cause" provision takes us out of the general "at-will" employment doctrine rule. The issue here is how the trial court is to determine whether the duration of the contract is reasonable and how it is to arrive at such a reasonable duration. This is a question not previously addressed to this court and to which Berube, Brehany, and Johnson are not instructive. The legal propositions and rules of contract construction and interpretation presented in this dissent are more appropriate for use by the trial court in adjudicating this controversy on remand.
T41 Once the trial court determines the reasonable term under the cireumstances and that term is implied by law into the contract, the contract will necessarily be enforceable against the succeeding board under the see-ond prong of the Bair test articulated in the majority opinion because (1) the activity contracted for is proprietary and (2) the term or duration that was implied into the contract is de facto reasonable under the cireumstances.
€ 42 Having determined the reasonable duration of the contract, and therefore its enforceability, the trial court must then determine if the hospital breached the contract when it terminated Dr. Hardy. It could terminate him before the expiration of the implied term only for "just cause." If the trial court determines that the hospital had just cause to terminate the contract with Dr. Hardy, the hospital did not breach the contract and Dr. Hardy is not entitled to damages. If the trial court determines that the hospital did not have just cause to terminate the contract with Dr. Hardy, then the hospital breached the contract and Dr. Hardy is entitled to damages calculated consistent with the reasonable employment duration term implied into the contract. See Bad Wound v. Lakota Cmty. Homes, Inc.,
T 43 Under the majority opinion's analysis, Dr. Hardy's damages, assuming the hospital is Hable to Dr. Hardy for terminating him without just cause, would be speculative, at best, and undeterminable, at worst, absent a finite term of duration in the contract. See Benham v. World Airways, Inc.,
[ 45 I would remand to the trial court but with instructions consistent with this concurring opinion.
. The majority opinion criticizes this dissent for its citation to applicable, persuasive authority from the highest courts of our kindred states and dismisses that authority as nonbinding. Where this court has not addressed a particular question of law and where authoritative precedent from our own jurisdiction is absent, this court has not been reluctant to seek out the experience, reasoning, and counsel of the decisions of other high courts as persuasive guidance in our deliberations.
The majority opinion also criticizes the dissent for its citation to certain cases involving contracts other than for the provision of employment or personal services. However, all of the cases cited in this paragraph involve contracts for employment or personal services.
This dissent does cite to other nonemployment contract cases later in 132 for the additional proposition that courts generally will imply a term of duration into indefinite-length contracts. The majority opinion maintains that those non-employment cases are inapposite and that this dissent's reliance on them is tenuous because the courts have developed "a unique set of rules for employment and personal services contracts."
. The majority opinion notes that the parties have not argued in their appellate briefs that a term should be implied into the contract and that both parties contend that the contract should be evaluated as an indefinite-length contract limited only by the just cause provision. This incorrectly elevates the parties' arguments in the briefs to the level of an agreement between the parties on this point and treats it as a stipulation. Nothing in the record or the briefs indicates that the parties have stipulated in the manner the majority opinion claims. The parties do not deny that they did not include an explicit provision in the contract expressing their intentions purposely to create an indefinite-length contract. If the parties to a contract intend to create an indefinite-length contract, they must express their intentions to do so through clear, unambiguous, and unequivocal language in the contract. The parties' questionable "concession" in this regard in their briefs on appeal obviously fails to meet this standard and is contrary to the rule of law stated in the cited authority. Both Johnson and Shah may recognize the rights of parties to enter into indefinite-length contracts, but they do not dispute or contradict the requirement that the parties do so using explicit language in their contract.
In any event, under normal circumstances, we will treat particular facts or issues as stipulated to by the parties only where such a stipulation is clear and expressed. Rarely, if ever, do we find
Finally, the majority opinion also admonishes the dissent that "[iJn the absence of adequate briefing, it would be ill-advised for the court to raise [the issue of implying a reasonable term] sua sponte, especially [where] this issue presents a question of first impression." This, however, ignores our settled position that this court has inherent authority to consider arguments and issues that the parties have not raised or recognized if it is necessary to a proper decision and to avoid bad law. See Kaiserman Assocs., Inc. v. Francis Town,
. The majority opinion also argues that under the dissent's analysis courts will "inevitably and routinely need to determine damages associated with a breach of an indefinite employment contract." This is incorrect. The vast majority of cases involving issues of termination under indefinite-length employment contracts will be governed by the "at-will" employment doctrine. In those instances, the issue of damages would not arise because the employment relationship would be terminable by either party for any reason. The problematic issue of damages arises only in the very rare and unique case, such as the one at hand, where an expressed or implied "just cause" term is a part of the indefinite duration contract, thus removing the case from the application of the usual "at-will" employment doctrine rule.
