110 Wash. 391 | Wash. | 1920
On March 4, 1918, the defendant Schaefer and the respondent Uden entered into a written contract whereby the defendant agreed to furnish all the necessary labor and material and install the plumbing and heating system in an apartment building which the respondent was then constructing. The contract price was $17,000, and was payable in monthly installments of eighty-five per centum of the value of the labor and material in place at the end of each monthly period. The contract provided that the defendant should furnish an approved surety bond for the amount of the contract price, “otherwise the contract shall be null and void.” The defendant, in com
11 Third, That the surety shall not be liable for any damages resulting from so-called strikes or labor difficulties, or from mobs, riots, fire, the elements, earthquake, cyclone, tornado, lightning, or any act of Glod, or for repair or reconstruction of any work or materials damaged or destroyed by any such causes; nor for the non-performance of any guaranties of the efficiency or wearing qualities of any work done or materials furnished or the maintenance thereof or repairs thereto; nor for patent infringement; nor for the furnishing of any bond or obligation other than this instrument; nor for damages caused by delay in finishing such contract in excess of ten per centum of the penalty of this instrument; nor for payments made, or for which the obligee shall become liable to pay on account of death or personal injuries suffered by any person or persons.”
The defendant began the performance of the work and pursued it for about two weeks, during which time he amassed some material and did some excavating. He then abandoned the work, and the respondent was compelled to relet it. This he did by calling for new bids. The best bid obtained for the uncompleted work was $19,122, and the work was let for that sum.
In this action, the respondent sues both the Maryland Casualty Company and the defendant Schaefer in damages as for a breach of the contract. The sum demanded totals $3,198.75, made up of the difference between the original contract price and the price for which the work was relet, together with the sum of $616, paid to carpenters for extra work, alleged to have been made necessary by the defendant on account of
The action was tried by the court sitting without a jury, and resulted in a judgment against both the defendant and the Maryland Casualty Company in the sum of $2,565.15, and an additional judgment against Schaefer in the sum of $15. The Maryland Casualty Company alone appeals.
The appellant defended the action on the ground that the defendant’s failure to perform the contract was because of a strike on the part of his workmen, or at least because of labor difficulties, and that it is thus not liable to answer to the respondent for a breach of the defendant’s contract because of that clause of its bond which exempts it from liability “for any damages resulting from so-called strikes or labor difficulties.” Schaefer seems to have given different.reasons at different times for his failure to perform the contract; but, from his evidence given at the trial, we gather that the cause of his failure was, in substance, this: At the time of entering into the contract with the respondent, he was a member in good standing of the Seattle Plumbing and Heating Engineers’ Association, which association had agreed with the plumbers’ unions that its members in their contracting work would employ thereon only members of such unions, and which unions in turn had agreed not to work for any contracting plumber who was not a member of the association in good standing. That, when the respondent called for bids for installing the plumbing and heating appliances in his building, Schaefer, with other members of the association, submitted bids, Schaefer’s bid being somewhat larger than the lowest bid submitted. The respondent, for some reason, probably because he thought them too high, did not accept any of the bids submitted, and afterwards Schaefer entered into nego
In our opinion, these facts do not exonerate the appellant from the obligations of its bond. In the common acceptation of the term, it is not a “strike” for the workmen of an employer to quit his employment and go elsewhere without any intention of returning, nor is it a “strike” for workmen to refuse to enter into the employment of a particular contractor. A “strike,” in such common acceptation, is the act of quitting work by a body of workmen for the purpose of coercing their employer to accede to some demand they have made upon him, and which he has refused; but it is not a strike for workmen to quit work, either singly or in a body, when they quit without intention to return to the work, whatever may be the reason that moves them so to do. It is a matter of common knowledge that, during the late war period, many employers of labor, because of the great demand for labor, had difficulty in employing and keeping a sufficient
■ The addition of the phrase “labor difficulties” to the term “so-called strikes” does not enlarge the meaning of the latter. It is rather definitive than expansive of it. In other words, the phrase is but explanative of the meaning of the word strike, and any act of the workmen which would not constitute a strike would not constitute a labor difficulty.
A further contention is that the judgment as rendered is too large. Schaefer claimed while on the witness stand that there was a balance of $211.90 due him for work performed by him which the respondent had not paid, and this sum the appellant contends should be deducted from the judgment. On the question whether it was paid on not, the evidence was conflicting, and our examination of the evidence does not convince us that the court was in error in so finding.
The judgment is. affirmed.
Holcomb, O. J., Tolman, Bridges, and Mount, JJ., concur.